Update on SLS: Still aiming for very unlikely March launch
A detailed update on the work being done by NASA and Boeing engineers to prepare SLS for its first unmanned test launch suggests that though a March launch is still the target, it is likely to be delayed.
The update at the link is very thorough, and outlines a large number of tests that need to be done to get this very cumbersome and complicated rocket ready for launch. They are just about done with the prep work for the core stage, and are now shifting to final testing of the upper stage, followed by some countdown sequence testing and a test of the flight termination system. In addition there are a number of other tests they wish to perform, all of which will take time.
Once these are done they will be ready to roll the rocket out to the launchpad for a final dress rehearsal countdown — dubbed the Wet Dress Rehearsal (WDR), now scheduled for mid- to late-February.
NASA will not set a launch date until after the WDR is completed and they can factor in any additional tasks with already-known work. “We’ve continually said that until we get through WDR we won’t set a launch date, so us getting out in mid-February for WDR allows them to look at March and April as opportunities,” Lanham said.
“I really can’t put my finger on it again until we come back from WDR and see if we have any issues there that we’ve got to go correct.” After the WDR test, the vehicle and Mobile Launcher will be rolled back to the VAB for final pre-launch maintenance and servicing.
Some have said the earliest realistic launch date is May, with the mid-summer more likely. We shall have to wait and see.
A detailed update on the work being done by NASA and Boeing engineers to prepare SLS for its first unmanned test launch suggests that though a March launch is still the target, it is likely to be delayed.
The update at the link is very thorough, and outlines a large number of tests that need to be done to get this very cumbersome and complicated rocket ready for launch. They are just about done with the prep work for the core stage, and are now shifting to final testing of the upper stage, followed by some countdown sequence testing and a test of the flight termination system. In addition there are a number of other tests they wish to perform, all of which will take time.
Once these are done they will be ready to roll the rocket out to the launchpad for a final dress rehearsal countdown — dubbed the Wet Dress Rehearsal (WDR), now scheduled for mid- to late-February.
NASA will not set a launch date until after the WDR is completed and they can factor in any additional tasks with already-known work. “We’ve continually said that until we get through WDR we won’t set a launch date, so us getting out in mid-February for WDR allows them to look at March and April as opportunities,” Lanham said.
“I really can’t put my finger on it again until we come back from WDR and see if we have any issues there that we’ve got to go correct.” After the WDR test, the vehicle and Mobile Launcher will be rolled back to the VAB for final pre-launch maintenance and servicing.
Some have said the earliest realistic launch date is May, with the mid-summer more likely. We shall have to wait and see.