New problem found on Orion that could delay its launch by a year

The failure of a power unit on the Orion capsule slated to fly on SLS’s first test flight late in ’21 could delay that test flight by as much as an additional year.

Replacing the PDU isn’t easy. The component is difficult to reach: it’s located inside an adapter that connects Orion to its service module — a cylindrical trunk that provides support, propulsion, and power for the capsule during its trip through space. To get to the PDU, Lockheed Martin could remove the Orion crew capsule from its service module, but it’s a lengthy process that could take up to a year. As many as nine months would be needed to take the vehicle apart and put it back together again, in addition to three months for subsequent testing, according to the presentation.

Lockheed has another option, but it’s never been done before and may carry extra risks, Lockheed Martin engineers acknowledge in their presentation. To do it, engineers would have to tunnel through the adapter’s exterior by removing some of the outer panels of the adapter to get to the PDU. The panels weren’t designed to be removed this way, but this scenario may only take up to four months to complete if engineers figure out a way to do it.

A third option is that Lockheed Martin and NASA could fly the Orion capsule as is. The PDU failed in such a way that it lost redundancy within the unit, so it can still function. But at a risk-averse agency like NASA, flying a vehicle without a backup plan is not exactly an attractive option. It’s still not clear what went wrong inside the unit, which was tested before it was installed on the spacecraft, according to a person familiar with the matter.

None of these options are good. The first two will certainly delay the planned November 2021 launch, which by the way is already four years behind schedule. The third will risk a failure of the mission, which though unmanned would certainly lead to further delays in the manned mission expected one or two years later.

That they don’t know why the unit failed and cannot fix it easily speaks very badly to the design of Orion and SLS. Compare this with SpaceX, which in the past month has demonstrated it can in only days switch out engines on both its commercial Falcon 9 rocket and its new next generation Starship rocket. Moreover, SpaceX has demonstrated repeatedly that once they identify an issue they move immediately to understand it and fix it.

With NASA, Orion, and Orion’s contractor Lockheed Martin, such flexibility and agility appears all but impossible. They have designed a monster that cannot be fixed easily, cannot launched quickly, and costs an ungodly amount of money.

I increasingly believe that Starship will reach orbit before SLS/Orion, even though the latter has been in development for almost three times longer, and will cost 25 times more.

13 comments

Chang’e-5 now in lunar orbit

The new colonial movement: China’s lunar sample return probe Chang’e-5 has now entered in lunar orbit, with its landing to occur in three days.

Over the next week, the probe, composed of four parts – the orbiter, lander, ascender and Earth re-entry module – will perform multiple complicated tasks on a tight schedule.

The four parts will separate into two pairs. The lander and ascender will head to the moon and collect samples, while the orbiter and Earth re-entry module will continue to fly around the moon and adjust to a designated orbit, getting ready for the docking with the ascender.

The landing operation is expected in three days. Once touched down on the lunar surface, the lander will collect two kilograms of lunar sample.

The plan once on the surface is to gather a sample from the surface as well as from a six-foot deep core sample.

2 comments

Wealthy environmentalist picks his preferred UK spaceport

Capitalism in space: A wealthy businessman who is also involved in environmental causes has invested almost 1.5 million pounds in the proposed spaceport planned for the Shetland Islands, the northernmost British islands.

What makes this investment especially interesting is this same environmentalist’s opposition to a different spaceport proposed for Sutherland, Scotland.

Danish businessman Mr Povlsen, who is reportedly worth £4.5bn thanks to his Bestseller clothes retail empire, and his wife own thousands of acres of land in Sutherland, and on other estates in the Highlands. [Their company] Wildland Ltd has raised concerns about Space Hub Sutherland’s impact on the Caithness and Sutherland Peatlands Special Protection Area, and has sought a judicial review of Highland Council’s permission for the satellite launch project.

Another of the Povlsens’ companies, Wildland Ventures Ltd, has invested in Shetland Space Centre.

This apparently is the ultimate in NIMBY (not in my backyard!). It seems this couple is throwing its weight behind the Shetland site in order to help keep the Sutherland site (in their backyard) from being built.

4 comments

Next Virgin Orbit LauncherOne test flight set for late December

Capitalism in space: According to Coast Guard notices, the next Virgin Orbit attempt to put its new LauncherOne rocket into orbit should occur sometime between December 18-21.

A Nov. 24 “Local Notice to Mariners” by the U.S. Coast Guard stated that Virgin Orbit “will conduct hazardous operations” offshore from San Nicolas Island, California, between Dec. 18 and 21. Those operations will take place during a four-hour window that opens at 1 p.m. Eastern.

The notice does not explicitly state that a launch will take place, but Virgin Orbit used the same language in a Coast Guard notice for its first orbital launch attempt in May. That earlier notice, which also cited “hazardous operations,” had the same four-hour window and location for the operations.

The company has not officially announced the launch date, but it has said it would fly this mission before the end of this year.

The article also notes that another smallsat launch startup, Astra, has announced its next launch attempt will take place during a 12-day launch window starting December 7th.

0 comments

Problems discovered in new Japanese H3 rocket engine

Engineers at Mitsubishi have discovered technical problems in the engine for Japan’s new H3 rocket, forcing its first test launch to be delayed into 2021.

The Japanese space agency JAXA told SpaceNews that problems were found with the new LE-9 engine’s combustion chamber and turbopump. “Fatigue fracture surfaces were confirmed in the apertural area of the combustion chamber inner wall and the FTP blade of the turbo pump,” according to a JAXA spokesperson.

JAXA and Mitsubishi Heavy Industries (MHI), the prime contractor for the H3, were aiming to hold the inaugural launch by the end of 2020 before the discovery of issues in May. However engineers testing the LE-9 cryogenic liquid hydrogen and liquid oxygen engine for the H3 first stage encountered a potential issue back in May. This led JAXA to announce in September that the first flight would slip to some time in Japanese fiscal year 2021, beginning April 1, 2021. The rocket’s second launch likewise slipped to Japanese fiscal year 2022.

The H3 is intended as a cheaper and more competitive version of Mitsubishi’s H2 rocket, which has failed to garner much business outside of Japanese government launches because of its cost. That the H3 isn’t being built to be reusable however means it will likely not achieve that goal, as it will not be able to lower it enough to compete with SpaceX.

This launch delay further weakens its ability to compete, as it gives more time for other cheaper alternatives to hit the market.

1 comment

Russian company proposes new Russian space station post-ISS

Energia, the division in Roscosmos that manages the Russian manned program, including its share of ISS, has proposed that Russia build its own space station after 2025, and the reasons it gives strongly suggest they are worried about the condition of their 20-year-old and leaking Zvezda module.

The International Space Station’s systems are likely to keep breaking down after 2025, Energia company, which manages the Russian module, said and suggested building a national station instead. “Russia has commitments regarding the ISS through 2025. Several elements are already seriously damaged and about to stop functioning. Many of them are impossible to replace. After 2025, we expect many ISS elements to start breaking down en masse,” the deputy director-general of Energia, Vladimir Soloviev, said at a meeting of the Russian Academy of Sciences. [emphasis mine]

They don’t mention Zvezda by name, but the highlighted words point to it. Assuming the persistent leaks in the module are related to stress damage and age, this statement is recognizing publicly that replacing Zvezda is very difficult, or impossible, and that it is on the verge of complete failure.

Whether Russia has the money or resources to get another station built soon after 2025 is questionable, however. If they do decide to go it alone, I doubt they could launch a replacement before 2030, at the earliest, and likely much later than that.

If they do end the partnership with the U.S., it is unclear what happens to ISS. If the Russians choose to undock their portion of the station it will leave ISS somewhat crippled. It has been my impression that without all of the environmental systems in the Russian half, ISS cannot function. This might no longer be true, and will likely not be true with the planned arrival of Axiom’s private modules by the mid-20s. Timing however of all this remains critical.

6 comments

Starship 50,000 ft hop now scheduled for Nov 30th

Capitalism in space: Having completed all preliminary static fire tests, SpaceX has now set November 30th as the target date for 50,000 foot high hop for its eighth Starship prototype.

SpaceX is understood to be conducting a Flight Readiness Review (FRR) for the test flight, with this final Static Fire test providing key data to the final go to proceed towards SN8’s big day.

Elon Musk has already calibrated public expectations on the expected outcome of SN8’s test, noting that “understanding exactly how the body flaps control pitch, yaw & roll during descent, such that the ship is positioned well to relight, flip & land, would be a big win.” As opposed to expecting SN8 to land feet first on the landing pad.

Musk’s point is important. The primary engineering goal for this first hop will be to find out whether they truly understand how to control and fly Starship. Their knowledge in this area is only computer based, and thus is very incomplete, and could very well be wrong, resulting in a failure that prevents a proper clean landing.

Such as failure however would actually be an engineering success, as it would give them the data needed to make later prototypes work. As for landing, they know how to do that already. Once they get the flying right, the landing should follow.

SpaceX has said it will live stream that hop. Should be a thrill to watch.

9 comments

SpaceX sets numerous launch records in placing 60 more Starlink satellites in orbit

Falcon 9 booster landing for a record 7th time

Capitalism in space: SpaceX tonight broke a whole bunch of new launch records in launching another sixty Starlink satellites into orbit using its Falcon 9 rocket.

First, the leaders in the 2020 launch race:

31 China
22 SpaceX
12 Russia
5 ULA
5 Rocket Lab

The US now leads China 35 to 31 in the national rankings.

For SpaceX, this launch established the following landmarks for the company:
» Read more

9 comments

Rocket Lab declares first attempt at recovering a 1st stage a success

Capitalism in space: Rocket Lab has announced that the company’s first effort to recover a 1st stage of its Electron rocket during a November 19th launch was a complete success.

On Rocket Lab’s latest launch Nov. 19, the rocket’s first stage made a controlled reentry after stage separation, then released a drogue and a main parachute before splashing down about 400 kilometers downrange from its New Zealand launch site, where it was recovered by a boat.

The recovery itself went as planned. “The test was a complete success,” Peter Beck, chief executive of Rocket Lab, said in a call with reporters Nov. 23. “The stage splashed down completely intact. What it proved to us is that this is a feasible approach, and we’re really confident that we can make Electron a reusable launch vehicle from here.”

Eventually they plan to snatch the stage out of the air using a helicopter prior to hitting the water, but are presently focusing instead on developing the proper thermal protection and attitude control systems for the flight back to Earth. They are presently taking that first stage apart and analyzing what worked and didn’t work in protecting it during that flight.

According to Beck, they will do another splashdown recovery early in ’21 to refine things. They also hope to reuse some of the recovered components from both splashdown tests on later flights.

2 comments

Regulators coming after SpaceX’s Boca Chica facility and Starship

Capitalism in space? New FAA documents suggest that government regulators are not happy with the rapid and spectacular development by SpaceX of its Super Heavy/Starship rocket at Boca Chica, Texas, and are eager to impose restrictions and delays.

The issue revolves around revisions to SpaceX’s original FAA approval for its work at Boca Chica because the company has switched from flying Falcon 9 and Falcon Heavy rockets to developing and flying Starship and Super Heavy. While the FAA has been cooperative in issuing the necessary revisions, other agencies have raised red flags.

But the most important document of the bunch is the written reevaluation signed by the FAA on May 22. The file spans 26 pages, was required for SpaceX to receive its suborbital launch license from the FAA on May 28, and incorporates concerns from state and federal environmental agencies.

In the reevaluation, the Texas Parks and Wildlife Department and the US Fish and Wildlife Service took issue with several aspects of SpaceX’s plans and ongoing activities. Those criticisms targeted the “fluid nature” of the company’s construction projects, excessive road closures to Boca Chica Beach (which Brownsville locals prize), around-the-clock work that may affect nocturnal threatened or endangered species, prototype explosions, and sprawling wildfires the company has triggered.

The FAA responded to each concern in the document, ultimately determining “there are no significant environmental changes, and that all pertinent conditions and requirements of the prior approval have been met or will be met” with SpaceX’s suborbital test-flight plans.

However, SpaceX does not yet have the FAA’s go-ahead to launch any Starships to orbit from Boca Chica.

In its replies to concerns noted by other agencies — some of which call for a new EIS [environmental impact statement], which could take years to complete (an eternity in Musk time) — the agency repeatedly noted it is working with SpaceX to draft an “environmental review” of those plans.

Should Joe Biden and the power-hungry and controlling Democrats take control of the executive branch of the federal government, expect the FAA’s desire to help SpaceX to quickly end.

27 comments

Faulty valve on one Soyuz causes Russians to delay second Soyuz launch

Due to the discovery of a faulty valve on a Soyuz rocket being prepared for launch in French Guiana, Roscosmos has delayed today’s Soyuz rocket launch from Plesetsk, Russia, until December 3rd to allow engineers to inspect similar valves on that rocket.

This quote from Dmitry Rogozin, head of Roscosmos, from the first link, describing the problem, is somewhat amusing:

“The ‘faulty valve’ would be launched with the rocket, and it would return to Earth being just a heap of mishap metal, that would be the problem. There are always some flaws, but in our case, they cost too much. Happily, the low-quality detail was timely detected by the quality control system. However, in general, I do note a sharp decline in our suppliers’ responsibility and quality of their work,”

It appears the quality control problems with Russia’s aerospace industry are continuing. No one, including the Russians, should be surprised by this, as that industry has no competition to stimulate quality work and force bad companies out of business. Instead, everything is managed by Roscosmos from on top, with much of that management designed to eliminate competition entirely and protect the companies that presently exist..

0 comments

China successfully launches its Chang’e-5 lunar sample mission

screen capture at Long March 5 launch of Chang'e-5
Screen capture from launch live feed

The new colonial movement: China today successfully used its Long March 5 rocket to launch its Chang’e-5 on the first lunar sample return mission since the 1970s.

If all goes well, the return capsule will return to Earth with its sample on December 15th.

China provided a live stream, in English, which I have embedded below the fold.

The leaders in the 2020 launch race:

31 China
21 SpaceX
12 Russia
5 ULA
5 Rocket Lab

The U.S. still leads China 34 to 31 in the national rankings.
» Read more

1 comment

SpaceX launches oceanography satellite

Capitalism in space: SpaceX today successfully launched an oceanography satellite using its Falcon 9 rocket from the company’s California launch site at Vandenberg Air Force Base..

The first stage, making its first flight, successfully landed back on land near the launch site.

This was also SpaceX’s 21st successful launch in 2020, tying their record from 2018 for the most launches in a single year by a private company, ever. That record should be broken tomorrow, with their next Starlink launch.

The leaders in the 2020 launch race:

30 China
21 SpaceX
12 Russia
5 ULA
5 Rocket Lab

The U.S. now leads China 34 to 30 in the national rankings.

9 comments

Successful Rocket Lab launch and descent of 1st stage

Capitalism in space: Rocket Lab today successfully used its Electron rocket to 30 smallsats into orbit from its launchpad in New Zealand.

They also did their first launch test of their planned method for recovering the first stage for reuse. In their case the first stage will use parachutes to slow its descent, and will then be grabbed by a helicopter to be brought back to land. On this launch they were only testing the parachute portion of this plan, and allowed the stage to land in the water, where they then recovered it.

The leaders in the 2020 launch race:

30 China
20 SpaceX
12 Russia
5 ULA
5 Rocket Lab

The U.S. now leads China 33 to 30 in the national rankings.

6 comments

Stratolaunch begins construction of hypersonic plane

Capitalism in space: Stratolaunch, continuing its shift from an orbital launch company to one providing a flying hypersonic testbed, has begun construction of its first hypersonic plane, dubbed Talon-A.

Talon-A will be air-launched from the bottom of Roc, the world’s biggest airplane, that the company initially built to serve as a launch platform for an orbital rocket.

It appears they have the financing to build Talon-A, and it also appears there is ample interest in both the military, NASA, and the aviation industry for this capability. If it works it will make testing hypersonic technology far easier and more affordable, issues that have acted to slow its development.

1 comment

Relativity raising $500 million in new search for investment capital

Capitalism in space: The new rocket company Relativity Space is in the process of raising another $500 million in new investment capital.

The new fundraise, expected to close in the coming days, would jump Relativity’s valuation to $2.3 billion, those people said. In addition to Tiger Global, Fidelity is also joining the round as a new Relativity investor. Existing investors in Relativity are also expected to be contributing — those include Social Capital, Playground Global, Y Combinator, Bond Capital, Tribe Capital, Jared Leto and Mark Cuban.

Tiger Global, the investment firm founded by Chase Coleman, has more than $43 billion in assets under management.

This new funding will supplement the almost $200 million Relativity raised previously.

The company has successfully completed engine tests, and plans its first orbital test launch of its Terran-1 rocket next year.

0 comments

The SpaceX fleet of Dragons

The first manned Dragon capsule on the launchpad
The first manned Dragon capsule, on the launchpad

Capitalism in space: During the post-launch press briefing after launch of its second manned Dragon mission on November 15, SpaceX CEO Gwynne Shotwell revealed the company’s plans to build and fly a fleet of Dragon cargo and crew capsules, and reuse them repeatedly over the coming years..

Specifically, Shotwell revealed that SpaceX intends to build three reusable Cargo Dragon 2 capsules, one of which is already completed and in Florida preparing for its December 2nd CRS-21 launch debut. On the crew side of things, SpaceX will build “three more” Crew Dragon capsules on top of the flight-proven Demo-2 and currently orbital Crew-1 capsules. It’s unclear if this means that the new Crew Dragon capsule flown on SpaceX’s January 2020 In-Flight Abort (IFA) test will be refurbished for additional flights.

Excluding IFA Crew Dragon capsule C205, SpaceX thus intends to operate a fleet of at least three Cargo Dragon 2 and five Crew Dragon capsules, representing eight reusable spacecraft each capable of at least five orbital missions.

She also hinted that the company has plans to fly its own missions, using these spacecraft, in addition to its contracted flights for NASA and the private company Axiom.

This private capability, which far exceeds anything ever built by NASA or any government worldwide, is entirely because Elon Musk had the freedom and the will to push for his particular vision. He had a bold idea, and with courage he pursued it.
» Read more

16 comments

Sierra Nevada delays first Dream Chaser launch to ’22

Sierra Nevada officials revealed yesterday that they are delaying the first test flight of their Dream Chaser reusable cargo mini-shuttle from late 2021 to some unspecified time in 2022.

‘’COVID has definitely played a role” in that delay, said Steve Lindsey, senior vice president for strategy at SNC Space Systems. One example he gave involved structural testing of the spacecraft’s cargo module at a contractor’s facility in San Diego. COVID-related restrictions prevented SNC engineers from being on site at that facility to oversee the tests. SNC developed a workaround by using a mission control center it developed for Dream Chaser in Colorado so those engineers could remotely oversee those tests. “That worked great. Unfortunately, it took probably three or four times as long as it should have,” he said.

A related problem, he said, involves suppliers who have had to suspend operations because of COVID-19 outbreaks at their facilities. There have also been technical challenges with Dream Chaser, although he did not go into details about specific issues. [emphasis mine]

I underline the unspecified technical issues, because I suspect they might be the real issue. SpaceX has not been slowed in any significant way due to the Wuhan panic, even though it deals with NASA also. I would therefore not be surprised if they are using COVID-19 as a cover for other issues.

It is a new craft, and problems are expected. I’d just rather they didn’t hide it. It contributes to doubts about the company, which by the way has been much slower in its development than one should expect. NASA awarded this contract in January of 2016, with the first launch then planned for as early as October 2019. It is now 2020, and the launch is still now two years away.

6 comments

Arianespace: Cause of Vega launch failure “human error”

According to Arianespace officials, today’s failure of their Vega rocket likely occurred because of “human error” in the installation of cables.

Engineers concluded that cables leading to thrust vector control actuators on the upper stage were inverted, apparently a mistake from the assembly of the upper stage engine, according to Roland Lagier, Arianespace’s chief technical officer. The thrust vector control system pivots the upper stage engine nozzle to direct thrust, allowing the rocket to control its orientation and steering.

The cabling problem caused the engine to move its nozzle in the wrong direction in response to commands from the rocket’s guidance system. That resulted in the rocket losing control and tumbling just after ignition of the upper stage engine around eight minutes after launch.

Lagier characterized the inverted cables as a “human error,” and not a design problem.

The next obvious question is the source of the error. The answer was not revealed, I think partly because of the number of contractors involved in building that upper stage:

The AVUM upper stage’s structure is produced by Airbus, and the Ukrainian rocket contractors Yuzhnoye and Yuzhmash supply the AVUM stage’s main engine, which consumes hydrazine and nitrogen tetroxide propellants. Avio, the Vega rocket’s Italian prime contractor, oversees final integration of the AVUM upper stage.

The goal of the investigation that will now follow will be to point that source among these contracts, and how their interaction might have contributed to it.