The present state of NASA’s Artemis program

Artemis logo

The aggressive effort by NASA administrator Jared Isaacman to rationalize and speed up the agency’s Artemis program to get back to the Moon and build a base there has resulted in a plethora of new missions, almost all of which are being built by the private sector.

Today Isaacman and his Moon Base program manager, Carlos García-Galán, held a press conference where they announced four more missions.

  • Astrobotic won a $297.9 million contract to build and fly two more of its smaller Peregrine lunar landers. This lander attempted a landing in 2024, but a fuel leak right after launch made that impossible.
  • Firefly won a $144.2 million contract to build and fly another Blue Ghost lander, the only commercial lander to successfully achieve a lunar soft landing, in 2025.
  • Intuitive Machines won a $148.3 million contract to build and fly another Nova-C lander. This lander attempted two landings, and in both cases it tipped over just after launch. The Nova-D design, under development, has a lower center of gravity, but for reasons not well explained by García-Galán NASA chose to go with the Nova-C design.

All are considered part of the first phase of the Artemis program and thus are targeting a launch by 2028.

In addition, NASA is considering using back-up equipment developed to build the Curiosity and Perseverance Mars rovers to create quickly and relatively inexpensively a lunar rover that they have dubbed “Promise.”

In order to make some sense of this program and these many misssions, I have created below a chronological list of confirmed missions, with their present status indicated (including uncertainties), as well as some unconfirmed missions based on my own speculations. All dates are tentative at this point, even if NASA has provided us a specific target date.

Several things to note as you review this list. While there are handful of missions going elsewhere, Isaacman is attempting to focus the program toward landing at the planned lunar base near the south pole, and to do so as fast as possible in the most effective way. The cargo missions and rovers are to get there ahead of the manned missions, in order to provide the astronauts supplies and surface transportation once they arrive. Those same missions will also do some preliminary scouting, and likely carry power and excavation equpiment needed to build the base.

It is also important to note that this plan is still in its very early stages of development. Many of the rockets and spacecraft and landers needed for these missions are not yet operational. Many have not yet demonstrated the capability to do what is requested. Thus, the program will certainly not follow the plan as presently outlined by the agency. Moreover, there will be failures along the way.

The program however is designed to accelerate development, to accept those failures within the program’s larger scope. If one mission fails, others are on the table to fly quickly to overcome the loss. And since the program is relying on the entire aerospace industry, the agency will have great redundancy from many companies.

I welcome comments and suggested changes or corrections. I fully intend to publish this list repeatedly over the coming years as the Artemis program evolves. And as the private sector begins flying its own missions to the Moon, independent of NASA, I intend to include those as well.
» Read more

5 comments

NASA’s IG: Boeing must foot the bill to get Starliner certified for manned flights

Starliner docked to ISS
Starliner docked to ISS.

The inspector general (IG) for NASA today released a new audit report [pdf] of the agency’s management of its manned commercial crew program, specifically looking at Boeing’s Starliner capsule and its failures. Though the IG made six recommendations, mostly about management procedures to better run the program, the first was the most important:

As the [Boeing] contract allows, defer payments, including partial or advanced payments, to Boeing for any Starliner-3 milestones until the human-rating certification of Starliner is complete.

In other words, the IG doesn’t want NASA to pay Boeing anything more. Boeing’s contract for Starliner was fixed price. It is Boeing’s responsibility to deliver the product, and until it does so NASA should lay out no more cash.

More significantly, NASA’s management immediately concurred with this recommendation.

This IG report now explains much of what happened in the past few months. » Read more

10 comments

NASA asks industry for proposals for building lunar base infrastructure

NASA today issued a request for feedback from the private sector for building its Moon Base, including the infrastructure for providing “surface power, in-situ resource utilization, [and] advanced manufacturing.”

The solicitation focuses on five technologies that NASA considers necessary but insufficiently developed at this point, some of which it also considers necessary for exploring and colonizing the entire solar system.

  • Solar power generation, including power management and distribution, and energy storage.
  • Radioisotope power, for use by operating spacecraft systems in the solar system’s “darkest, dustiest, and most remote places”.
  • In-situ resource utilization, including using lunar materials to produce fuel, water, and oxygen.
  • In-space advanced manufacturing for producing “essential tools and materials” on the Moon and Mars.
  • Innovative nanomaterials, for use in spacecraft and instruments in order to reduce their weight and size at launch.

The announcement notes that NASA is requesting input from industry, hoping it can “identify any areas of ambiguity, or concerns.” The agency will then revise accordingly.

This solicitation is another example of NASA administrator Jared Isaacman’s push to rationalize the entire Artemis program, to take seriously the real requirements for building a Moon base. Previously NASA made noises along these lines, but management did not do the proper due diligence to figure out what needs to get built in order to actually make a Moon base happen.

8 comments

NASA IG: Isaacman’s decision to cancel Gateway and SLS upgrades saved billions

Isaacman: Saving billions and actually getting more done

According to a report released yesterday [pdf] by NASA’s inspector general, the decision by NASA administrator Jared Isaacman to not only “pause” the Lunar Gateway station (killing its HALO module) but also cancel SLS’s upgraded upper stage (EUS), its related stage adaptor (USA), and the giant mobile launcher (ML-2) needed for that taller upper stage, saved the taxpayer billions in additional cost overruns, and has likely accelerated the Artemis program significantly.

NASA’s reformulation of the Artemis campaign to meet the President’s National Space Policy and increase its cadence of missions by standardizing the SLS heavy-lift rocket resulted in the termination or repurposing of several Artemis-related systems, including the EUS, USA, ML-2, and HALO.

Over the course of their life cycles, the combined contract values for these efforts ballooned from nearly $2.8 billion to $5.9 billion and NASA extended their contracted delivery dates by up to 7 years. However, our projections indicate that if NASA allowed work to continue to completion, the systems would have cost more and taken longer than what was on contract.

Specifically, the IG estimated that the overruns for the upper stage, the stage adaptor, and the mobile launcher would have ended up costing four to five times their original budgets. Gateway’s HALO module was less out of control, but it was still going to go more than 30% over budget. Overall, all four projects would have cost NASA almost $5 billion in additional expenses, with all four likely to also be considerably behind schedule. The upper stage and mobile launcher were certainly not going to be ready when needed.

The IG made no recommendations. It released this report to provide NASA, the White House, Congress, and the public the information so as to properly judge the agency’s actions, as well as provide guidance to the agency itself.

12 comments

Smooth on Mars is apparently not so smooth

Panorama on June 17, 2026
Click for full resolution. For original images, go here and here.

Overview map
Click for interactive map.

Last week I noted how the terrain that stood ahead of Curiosity in its travels on Mount Sharp on Mars appeared to be the smoothest the rover had seen in years.

This week it turns out that upon closer inspection, smooth on Mars is not as smooth as it seems. The panorama above, created from two pictures taken by the rover’s left navigation camera on June 17, 2026 (here and here), provides a much closer view of that smooth ground, and revealed that it isn’t actually smooth at all, but covered with small polygons. The inset on the left shows the area in the white rectangle at full resolution, making the patterned nature of the ground very obvious. From today’s update by the science team:

From up close, the parking spot looks anything but smooth. … There are polygons, veins, lamination, and probably more, once we inspect the higher-resolution images taken today. “Higher-resolution” is the key for why we were in for such a surprise! The features are quite small, a few centimeters across, and therefore we could not see them in the orbital images or from a distance in our navigation and mast camera images. The camera resolution from a distance just isn’t enough to see them. But up close, the terrain revealed all its beauty!

The blue dot on the overview map to the right marks Curiosity’s present position, the white dotted line its actual travels, the red dotted line its planned route. The yellow lines indicate roughly the area covered by the panorama above. The rim of Gale Crater can dimly be seen through the dusty atmosphere 20 to 30 miles away.

Explaining the geological process that caused this patterned surface is beyond my pay grade. My first guess would be it is related to the past presence of water, in the form of liquid or ice, but no one should take that guess very seriously.

As I have said many times, Mars is strange, Mars is wonderful, but above all, Mars is alien.

4 comments

Botswana to sign the Artemis Accords

NASA yesterday announced that the Republic of Botswana will sign the Artemis Accords on June 25, 2026, becoming the 68th nation to join this American alliance in space.

The Republic of Botswana will sign the Artemis Accords during a ceremony at 9:30 a.m. EDT Thursday, June 25, at NASA Headquarters in Washington. NASA Deputy Administrator Matt Anderson will host Botswana’s Minister of Communications and Innovation David Tshere and U.S. Department of State Senior Advisor for Space Gregory Autry for the event.

Since NASA administrator Jared Isaacman took over, the NASA press releases announcing these signings have eliminated much of the pro-globalist language introduced during the Biden administration. No longer does NASA claim the accords are designed to “reinforce” the Outer Space Treaty. In today’s release the language is relatively vague, stating merely that the accords are

responding to the growing interest in lunar activities by both governments and private companies. The accords introduced the first set of practical principles aimed at enhancing the safety, transparency, and coordination of civil space exploration on the Moon, Mars, and beyond.

As the accords were originally conceived by Trump as a long term tool to overcome the Outer Space Treaty’s restrictions on private property and the establishment of American law in its colonies, this vagueness is likely intended to avoid antagonizing Russia and China, to lull them into apathy about the issue at this time. Later, when the U.S. Moon base is largely established expect that vagueness to fade. That will be the time to use the clout of this large alliance to force a major legal change in this international treaty.

The full list of nations in this American space alliance is as follows:

Angola, Argentina, Armenia, Australia, Austria, Bahrain, Bangladesh, Belgium, Brazil, Botswana, Bulgaria, Canada, Chile, Colombia, Cyprus, Czech Republic, Denmark, Dominican Republic, Ecuador, Estonia, Finland, France, Germany, Greece, Hungary, Iceland, India, Ireland, Israel, Italy, Japan, Jordan, Latvia, Liechtenstein, Lithuania, Luxembourg, Malaysia, Malta, Mexico, Morocco, the Netherlands, New Zealand, Nigeria, Norway, Oman, Panama, Paraguay, Peru, Poland, Portugal, Romania, Rwanda, Saudi Arabia, Senegal, Singapore, Slovakia, Slovenia, South Korea, Spain, Sweden, Switzerland, Thailand, the Philippines, the United Kingdom, the United Arab Emirates, the Ukraine, the United States and Uruguay.

0 comments

NASA IG: NASA’s launch infrastructure at Kennedy and Wallops needs attention

Launch sites at Kennedy and Cape Canaveral
Figure 2 of IG report, annotated further by me.

According to a report released today [pdf] by NASA’s inspector general (IG), NASA’s launch infrastructure at both the Kennedy Space Center in Florida and the Wallops Flight Facility in Virginia are aging and need upgrades, but there is a systemic limitation on NASA’s access to funds to do the work.

The IG report — as is always expected from such a government report — of course whines about the lack of funding in recent NASA budgets, noting that Congress recently allocated $250 million for this purpose, but NASA claims it needs four times that amount, or $1 billion.

The report however also recognizes that this not the real problem. The map to the right, Figure 2 from the report, has been further annotated by me to show who is leasing or using each launch complex at both the Kennedy Space Center (managed by NASA) and Cape Canaveral Space Force Station (managed by the military but also supported significantly by NASA). As you can see, almost all launch sites are either leased by private rocket companies, or are being primed for future such leases. Yet, “statutory funding barriers” limit how much money NASA can collect from these companies. From the report’s conclusion:
» Read more

17 comments

Katalyst’s Link rescue satellite goes airborne in advance of launch

Katalyst's proposed Swift rescue mission
Katalyst’s proposed Swift rescue mission.
Click for original image.

Katalyst’s Link rescue satellite — that will attempt to grab the Gehrels-Swift space telescope and raise its orbit — began its journey to its launch area over the south Pacific on June 18, 2026 when Northrop Grumman’s Pegasus rocket that will launch it was taken airborne by company’s Stargazer L-1011 airplane.

Stargazer, a modified L-1011 operated by Northrop Grumman, took off for Kwajalein Atoll, part of the Republic of the Marshall Islands in the South Pacific Ocean. Attached to the belly of the aircraft was one of the company’s Pegasus XL rockets with LINK inside.

…Stargazer will carry Pegasus and LINK to Kwajalein Atoll, part of the Republic of the Marshall Islands in the South Pacific Ocean with stopovers in California and Hawai’i.

Sometime later this month Stargazer will go to its launch area, climb to 40,000 feet, and release the Pegasus rocket, which will then ignite its engines to carry Link into orbit. Link will then attempt to rendezvous with Gehrels-Swift, using its robot arms to catch it (the telescope has no grapple attachment). If successful, it will then raise the telescope’s orbit so that it can resume observations for years to come.

The mission is daring in more ways than just described. Katalyst has never done this before. It is a startup that reconfigured its first demo mission into this rescue mission.

19 comments

NASA awards Relativity the launch and management contract for new Mars orbiter

NASA today awarded the rocket startup Relativity the contract to provide the service module, rocket, and operations for the launch of its proposed four instrument Aeolus Mars orbiter, focused on studying the Martian atmosphere.

NASA will provide the Aeolus atmospheric‑science instrument payload suite, while Relativity Space supplies the spacecraft, rocket, and cruise operations necessary to deliver the instruments to Mars.

…Aeolus, scheduled to launch in 2028, is a NASA‑developed suite of four complementary instruments designed to provide the first integrated, daily, global view of Martian winds, temperatures, dust, and clouds. By improving models for dust, winds, temperature, and seasonal atmospheric behavior, Aeolus will generate the detailed environmental knowledge required to reduce risk for future crewed and uncrewed landings. These measurements will directly inform entry, descent, and landing systems and support safer, more predictable mission planning for astronauts.

…NASA will support operations of science instruments for at least one Martian year, while Relativity Space maintains the spacecraft.

The announcement made no mention of contract price. Relativity meanwhile has only launched once, a failure of its small Terran-1 rocket in 2023, after which the company abandoned that 3D-printed design to focus on its larger Terran-R rocket, which it hopes to launch for the first time before the end of this year.

2 comments

Cargo Dragon splashes down in Pacific after spending a month at ISS

ISS today, after undocking of cargo Dragon
ISS today, after undocking of cargo Dragon.
Click for original.

SpaceX today successfully recovered a cargo Dragon from ISS, the capsule undocking and splashing down in the Pacific, bringing back a variety of experimental samples and hardware.

Research returning includes bioprinted organ and cartilage tissue, data on improving cryogenic fuel storage for future space missions, and DNA‑inspired materials to develop new cancer treatments. The returning hardware includes an ocular imaging device used to monitor crew members’ eye health, an absorbent bed that filters trace contaminants from cabin air, and a separator pump from the waste and hygiene compartment.

The Dragon had spent a month at ISS, just long enough for astronauts to unload its cargo from Earth and place this ISS material aboard.

The graphic to the right, cropped, reduced, and annotated to post here, shows the present spacecraft docked to ISS. It also shows the location of Russia’s leaking Zvezda module, with a Progress docked to its aft port. Note that a Progress and the permanent modulc are also docked to its bow docking hub. Zvezda is an essential part of the Russian half of ISS. Replacing it is impossible.

0 comments

Are the Russians no longer going to dock to its leaking Zvezda module on ISS?

Zvezda module of ISS
The Zvezda module, with aft PrK section indicated
where the cracks have been found.

In a report today at Ars Technica, Eric Berger cites two anonymous NASA officials as saying that the Russians have decided to decommission the aft PrK section of its Zvezda module where it has found numerous cracks and air leaks in the hull, apparently caused by the stress of the many dockings to Zvezda since it was launched almost thirty years ago.

Berger’s report was aimed at providing more information about the kerfuffle between NASA and Roscosmos on June 5, 2026,, when NASA had the astronauts on its half of the station shelter inside their Dragon capsule because Roscosmos was going to have its Russian astronauts cut off a structural bracket in Zvezda as part of the first phase of a new leak patch effort. NASA objected strongly to this action, fearing justifiably that the work could cause a catastrophic failure in Zvezda.

The Russians eventually backed off, merely doing measurements of the module’s new crack, which appearantly appeared after a Progress docking in April

Berger doesn’t really add any significant new details to this June 5 story, but he ends his report with this tidbit:

In the days since, there has been some additional back-and-forth, but Russia has now told NASA it will decommission the PrK module. Effectively, this means cosmonauts will no longer enter the PrK module or attempt to pressurize it. Progress vehicles will still be able to use the docking port to transfer fluids or perform other functions, but Russia will need to use other ports to move supplies on board the space station. [emphasis mine]

This quote however doesn’t tell us anything, and actually raises more questions. The Russians have already been keeping the hatch to Zvezda closed as much as possible, opening it only to unload Progress cargo. And if Progress freighters are still going to dock to Zvezda to “transfer fluids or perform other functions”, the module isn’t decommissioned. Nor is the risk reduced. One of the reasons Zvezda has been stressed over the years is that this port is along the station’s main axis, which makes it ideal for engine burns to raise the station’s orbit. Progresses have been doing this repeatedly from Zvezda for three decades. If they intend to dock with Zvezda to “transfer” fluids”, that also suggests they also plan to continue to use that port for those burns.

It also makes no sense to say other ports will be used to “move supplies” from freighters. Russia isn’t going to dock to Zvezda to transfer fluids, do engine burns, and then move Progress to a different port to transfer cargo.

Thus, we really at this moment do not know what the Russians intend. Nor do we know if they plan to continue to dock with Zvezda. And it appears that each time they do, the chances of a catastrophic failure of Zvezda increases.

23 comments

SpaceX’s IPO sets the stage for the colonization of the solar system — by private enterprise

Elon Musk during the IPO
Elon Musk at the IPO opening.

While most news reports have focused trivially on Elon Musk’s status as the first trillionaire resulting from SpaceX’s successful initial public offering (IPO) last week, the real story of that IPO has to do with SpaceX itself and how that company’s extremely bright future is going to change human history.

Let me run some numbers.

The day’s earnings

First, the IPO was designed to raise capital for SpaceX by selling about 555 million shares of stock, with an opening price of $135. Once IPO opened however that price immediately jumped to $150, rising as high as $176 during the day, and by closing time settled at $160.95.

If we pick a conservative average sale price of $155 per share, this means SpaceX raised more than $86 billion in investment capital on this one day. The actual number will be less, because the brokerage houses that ran the IPO get a cut, but I would guess SpaceX will walk away with at least $75 billion once all accounts are settled.

To give this some context, NASA’s annual budget for the past two decades has been around $24 billion. NASA however cannot use that cash very efficiently, because it is required by Congress to have a huge unneeded labor force in many centers scattered around the country, to create jobs in specific congressional districts and states.

SpaceX doesn’t have that problem. For the company, this is real money. It can focus its use very precisely and efficiently for what needs to be done, and thus get a lot more bang out of the buck.

Annual earnings

SpaceX however is not limited to just the capital raised in the IPO.
» Read more

82 comments

NASA announces crew and flight plan for Artemis-3 Earth orbit mission next year

Artemis logo

NASA today unveiled both the four-person crew that will fly its Artemis-3 Earth orbit mission next year as well as the mission’s basic plan, assuming both SpaceX and Blue Origin can get their respective lunar landers ready in time.

Crew assignments are as follows:

  • NASA astronaut Randy Bresnik, commander
  • ESA (European Space Agency) astronaut Luca Parmitano, pilot
  • NASA astronaut Frank Rubio, mission specialist
  • NASA astronaut Andre Douglas, mission specialist

… NASA astronaut Bob Hines was named as a backup crew member.

Except for Douglas, all are veterans.

The mission details were also announced:

Artemis III includes launching the world’s most powerful rockets in short order. Blue Origin’s lander pathfinder, which is able to stay in orbit for multiple weeks, will launch first and await the crew. NASA will send the astronauts aboard Orion by SLS to orbit Earth, before rendezvousing in space with the company’s lander test article and spending about two days docked together for tests and technology demonstrations, including entering the lander.

After completing docked operations with Blue Origin, Orion will detach and await Starship. SpaceX’s Starship pathfinder will launch and meet up with Orion to spend about a day connected for checkouts and testing. After that, Orion and its crew will undock and return home, splashing safely down in the Pacific Ocean where a team from the U.S. Navy and NASA will recover the astronauts.

In total, the crew is expected to remain in space for about two weeks, with exact mission length to be determined in real-time based on launch, rendezvous, and docked operations.

All of this assumes that New Glenn has been fixed and is operational by late 2027 and can launch the Blue Moon Mark-2 manned lunar lander. It also assumes the lunar lander version of Starship is ready and operational and man-rated. It also assumes NASA can get SLS stacked and ready for launch much faster than previously expected.

All are big assumptions.

Other issues: Orion will be testing its docking system and its newly redesigned heat shield for the first time, with humans on board. As the return will be from low Earth orbit, the stress on the heat shield will be relatively light, reducing the risk considerably. Similarly, if the docking system fails they simply won’t dock, and can return to Earth instead. Both should work, however, as neither is cutting edge technology.

29 comments

NASA’s X-59 completes first no-boom supersonic flight, more than a year after a private company did it

NASA yesterday made a big deal about the first successful supersonic test flight of its X-59 test plane, built by Lockheed Martin for $247.5 million to demonstrate quiet no-boom supersonic flight.

And as usual, our uneducated propaganda press played along, touting the wonders of this new NASA achievement. A few examples:

Poppycock. Not one of these news articles made mention of the fact that the private commercial company Boom Supersonic accomplished the same feat eighteen months earlier, its XB-1 supersonic airplane breaking the sound barrier with no boom three separate times. And it did so using private funds for significantly less and getting the job done faster and in a manner that it can quickly convert into its planned commercial supersonic planes.

The X-59 is a typical NASA test project, designed to test a technology in a manner that is generally too specific and expensive for commercial use. Without doubt the engineering and the data from these flights will be helpful to companies like Boom, but to use it will require major changes and revisions to bring the cost down. It is for this reason Boom did its own engineering and test.

That I appear to be the only news outlet aware of this important background information — that puts a significantly different light on this government project — illustrates the bankruptcy of our modern media. They don’t know anything, and can only rewrite press releases.

20 comments

NASA clarifies air leak situation yesterday on ISS

Figure 3 from September Inspector General report
Figure 3 from September 2024 Inspector General report, showing Zvezda’s location on ISS, as well as the station’s leak rate at that time.

According to a NASA update posted late yesterday, the agency had cause to order its astronauts to shelter in place within their Dragon capsule due to planned repair work proposed by the Russians.

The week of June 1, during Progress 95 spacecraft cargo operations, Roscosmos noted an increase of the previous leak rate to two pounds per day and identified new suspected leak areas in the PrK. Following this observation, Roscosmos made the decision to begin work toward a more extensive inspection and structural repair effort Friday morning. This revised approach involved cutting a bracket to better access an area identified as a possible leak source for further inspection, using a method that could have resulted in elevated risk to the structure in the area. In response, NASA directed the four SpaceX Crew-12 members and NASA astronaut Chris Williams, who flew to station aboard the Soyuz MS-28 spacecraft, to take a heightened safety posture, known as a safe haven, inside the SpaceX Dragon spacecraft during the procedure.

Later Friday morning, Roscosmos paused and did not perform the structural repair work in favor of conducting additional measurements and data assessments, which included inspection of suspected areas of interest and review of areas where sealant was previously applied. NASA strongly supported that decision, and as a result, following that decision, Crew-12 and Williams ended their safe haven activities and returned to normal operations aboard the orbiting laboratory.

In other words, the leak rate had increased to match the high rates seen from 2019 to 2025, and the Russians were planning work that threatened the structure of the module. It appears NASA objected, and eventually the Russians acceded to those objections.

What happens next however remains unclear. If the leak rate has suddenly jumped from one pound per day to two pounds a day, that suggests the situation is worsening, and doing so at an alarming rate. As this new leak occurred shortly after a Progress freighter docked at Zvezda, it suggested the docking instigated it. It also suggests any further dockings there are likely to worsen the situation even more.

12 comments

NASA admits mismanagement and human errors caused 2025 Goldstone antenna damage

NASA today released its completed investigation into the November 2025 incident that severely damaged its Goldstone antenna in California when workers allowed the antenna to “over rotate” beyond its acceptable limits, putting it out of commission.

In its final report, the board found the mishap primarily stemmed from software weaknesses, human error, and an undetected failure in the antenna’s hydraulic limit system. Investigators determined an electrical issue at the antenna the previous day caused the control system to misreport the antenna’s rotation state, an issue that went unnoticed and triggered multiple limit-stops during the Juno track on Sept. 16. While working to identify the limit-stop problem, operators performed several troubleshooting steps that inadvertently bypassed software and hardware safeguards, which ultimately led to the over-rotation incident. After flooding in the antenna base was observed, operators attempted to stow the antenna as a safety precaution, however, because the system had already passed the rotation limits, this action drove the antenna further into over‑rotation, causing additional damage.

Additionally, the investigation found the antenna’s hydraulic limit system, its final mechanical safeguard, was inoperable on Sept. 16 after being damaged in an undocumented prior incident. The system also had not been adequately tested for an undetermined period of time.

Investigators also concluded workplace culture pressured operators to work as expeditiously as possible, often stretching beyond their usual roles, expertise, and training, to keep the antenna operating. The board states the cultural conditions observed at Goldstone were not present at the network’s other sites, where roles and responsibilities are followed more consistently. Other contributing factors outlined in the report include inadequate procedures, reliance on undocumented practices and tacit knowledge, and gaps in the antenna’s control logic. [emphasis mine]

You can read that report here [pdf], but be warned that large sections are redacted, apparently in an effort to protect the identities of those responsible.

Nonetheless, it is very clear from the highlighted text above that the management and work situation at Goldstone was a mess, and that the mishap was caused not by faulty engineering but by faulty work practices and bad management. Unfortunately, nowhere in the report is it said that there will be any management changes. This fact might have been redacted, but I suspect not. It is typical of government agencies like NASA after incidents like this to whitewash the investigation, concluding simply that “we should have done better and we now we will!”

The repairs will cost NASA about $4.6 million, and will likely not be completed until 2028.

14 comments

Venturi Space expands investment in new French factory for building Astrolab’s rover

Venturi Space, the European half of the partnership with the rover startup Astrolab, is increasing its investment in a new French factory from 100 million to 250 million euros.

On 1 June, Venturi Space announced that it had increased its expected investment in the new facility to €250 million. The announcement indicated that it would no longer begin with the initial smaller facility and would instead move directly to the full 16,000-square-metre planned “technology centre.” This likely accounts for the additional €150 million in funding.

According to the company’s 1 June press release, the facility will be used for the “design and manufacture of critical technologies for lunar and Martian mobility, as well as [for] the assembly of the rovers developed by the company.” …Venturi Space is providing wheels, batteries, and battery management systems to US-based Venturi Astrolab for use aboard its rovers. During a 26 May event, NASA announced that Venturi Astrolab was one of two companies selected to build rovers for the agency’s Artemis programme.

The partnership is an unusual one. Venturi Space and Astrolab are separate companies, working together to build Astrolab’s rovers for NASA. Venturi however is also developing its own rover for the European Space Agency.

3 comments

NASA abandons core module idea for its commercial space station program

The American space stations under development

Bowing to the unanimous opposition by the three most advanced commercial space station startups, NASA official Bethany Stevens yesterday announced that it is abandoning its proposed core module space station concept and returning its commercial space station program to its original plan, whereby the private stations all compete independently.

Industry has provided extensive feedback making the case for a sustainable commercial market in which NASA is one customer among many, along with assurances regarding available transportation capabilities. The industry position will now shape the path forward as NASA proceeds with the original commercial strategy.

Over the coming weeks, NASA will work with stakeholders and industry to refine flexible requirements and acquisition plans, with a draft RFP expected later this month.

The original plan was for the private sector to compete for one or two major construction contracts from NASA. The core module approach, put forth under NASA administrator Jared Isaacman’s leadership in March, instead made them all part of a government space station, like ISS, at least initially. Under that plan the new commercial space stations would attach their first modules to a government-built core module that NASA would first build and own. Isaacman proposed this because he and NASA believed it didn’t have the budget to finance more than one commercial station, and that the agency didn’t think there was sufficient market to make up the difference.

Officials from Vast, Starlab, Axiom and elsewhere all expressed opposition to the core module plan, insisting there was sufficient market to finance their stations, even without NASA. They also opposed the core module plan because it would require major changes in their present designs, and they had great doubt NASA could build that core module quickly enough for their financial purposes.

Isaacman and NASA apparently listened to these objections, and were convinced their idea was a mistake and the industry was right. It is now reviewing its budget and will decide whether it can do what it originally hoped, award two stations a major contract.

Either way, the recent news from all these three stations suggests they are increasingly in a strong position, whether or not they win that NASA contract.

6 comments

A call to my readers: Find the location of NASA’s lunar base!

Moon base map from NASA's May 26, 2026 presentation

Moon's south pole, with landers indicated
Click for interactive LRO map.

During yesterday’s NASA press conference outlining the first unmanned missions to the agency’s planned moon base near the Moon’s south pole, Carlos García-Galán, Moon Base program executive, included the graphic above of that base in his presentation.

Though García-Galán said this lunar base map is in the south pole region, the map provided no crater names nor any longitude or latitude information. Nor did it provide a scale to determine the size of these craters. Because of this lack of information, I was unable to identify the map’s precise location near the Moon’s south pole, even after searching extensively at the QuickMap site for Lunar Reconnaissance Rover (LRO) images, now managed by Intuitive Machines images and found here. The map to the right was created from that QuickMap site, annotated by me later with the planned landing locations for Chang’e-7 and Griffin, plus the sites where Nova-C and Vikram landed previously.

I am now asking you, my readers, to do some detective work. See if you can pinpoint the location of the map above with the LRO south pole imagery at the link. The crater patterns should provide the first clue. Remember also that the orientation of the map might require significant rotation to match the LRO data. Remember too that the scale of the map above could require you to zoom in a great deal.

If you think you have a match, post it in the comments below.

29 comments

NASA outlines new program of unmanned missions to Moon

NASA's Moon base plans as of May 2026
NASA’s Moon base plans as of May 2026.

NASA officials today outlined its new reshaped program of unmanned missions to Moon, designed it says to lay the first groundwork for the manned lunar base to follow.

You can watch the press conference here. The map to the right comes from one viewgraph during that conference, and apparently shows the planned lunar base area, which officials said could cover about 100 square miles. Though officials said this is in the south pole region, I have not been able to identify the precise location, using the global map produced by Lunar Reconnaissance Orbiter. The large crater northeast of the base does not appear to be Shackleton Crater.

The schedule includes four already planned missions, two new missions awarded to Blue Origin in a $188 million contract to deliver two new rovers, and a new hopper mission mission to be delivered by Firefly’s Blue Ghost lander. The schedule is as follows:
» Read more

12 comments
1 2 3 116