NASA’s second SLS mobile launch tower now behind schedule

Par for the course: According to one member of NASA’s safety panel, the contractor building NASA’s second SLS launch tower, is having performance problems and is already behind schedule.

On Thursday, during a meeting of NASA’s Aerospace Safety Advisory Panel, one of its members provided an update on Mobile Launcher-2. George Nield, an engineer and scientist who previously led commercial space transportation for the Federal Aviation Administration, said the 90-percent design, review, and fabrication drawings for the large structure are behind schedule. These are the engineering drawings that should closely represent the final design and inform a construction schedule and logistics plan.

“Mobile Launcher-2 has encountered some challenges,” Nield said. “The selected contractor, Bechtel, has experienced some performance issues associated with underestimating the complexity of the project and some supplier related issues, as well as COVID.”

Note that NASA spent about $1 billion on the first tower, to be used only three times, at most. Its contract with Bechtel says the second tower will cost $383 million, but no one expects that number to be met.

Assuming Bechtel does not go over budget (hah!), NASA will have spent $1.4 billion on SLS’s launch towers, one of which will be used two or three times and then abandoned. That’s three times the cost of what SpaceX spent developing Falcon Heavy, and about a third the total development cost of Starship/Superheavy, including its planned launchpads in both Boca Chica and Florida.

SpaceX aiming to launch 52 times in 2022

According to NASA officials, SpaceX is hoping to complete as many as 52 launches in 2022, a pace of one launch per week.

The impressive figure was given during a virtual meeting of NASA’s Aerospace Safety Advisory Panel, or ASAP, which gives guidance to the space agency on how to maintain safety within its biggest programs. “NASA and SpaceX will have to be watchful during 2022 that they’re not victims of their success,” Sandy Magnus, a former NASA astronaut and member of the panel, said during the meeting. “There’s an ambitious 52-launch manifest for SpaceX over the course of the year. And that’s an incredible pace.”

Based on other sources, I had previously estimated a SpaceX manifest for ’22 to be 40 launches. That this new higher number comes from NASA’s corrupt safety panel, and was touted as a reason to raise questions about SpaceX, makes me suspicious of it.

Still, a launch pace by SpaceX of one launch per week is wholly possible. For one thing, the company needs to get a lot of Starlink satellites into orbit as quickly as possible. With its development of Starship blocked by government interference, it might have decided to up the pace of launches using Falcon 9.

Furthermore, because most of the rocket is reused, SpaceX has a far greater launch capacity. For every Falcon 9 it builds it gets ten or more launches from its first stage. This means SpaceX does not have to build as much to maintain a high launch pace.

As for the safety panel’s fears about such a pace, who cares? That safety panel has been consistently wrong about everything it has said about SpaceX and commercial space now for almost a decade. It is very likely wrong now. In a more rational world, NASA would have shut it down two years ago for doing such a bad job. Sadly, we no longer live in a rational world.

Webb successfully inserted in final orbital position at the Sun-Earth Lagrange point

The James Webb Space Telescope today successfully completed a five minute firing of its engines to place it at the Sun-Earth Lagrange point dubbed L2.

Webb’s orbit will allow it a wide view of the cosmos at any given moment, as well as the opportunity for its telescope optics and scientific instruments to get cold enough to function and perform optimal science. Webb has used as little propellant as possible for course corrections while it travels out to the realm of L2, to leave as much remaining propellant as possible for Webb’s ordinary operations over its lifetime: station-keeping (small adjustments to keep Webb in its desired orbit) and momentum unloading (to counteract the effects of solar radiation pressure on the huge sunshield).

Engineers will spend the next three months aligning the segments of Webb’s large primary and secondary mirrors, while they wait for the telescope to cool down to the ambient very cold temperatures required for it to detect the tiny infrared heat emissions from very faint very very very distant objects.

NASA: No further Artemis Moon landings for at least two years after first in 2025

The tortoise appears to be dying: NASA today announced that there will be a two-plus year pause of Artemis missions to the lunar surface after it completes its hoped-for first manned Moon landing in 2025.

In presentations at a two-day meeting of the NASA Advisory Council’s Human Exploration and Operations Committee Jan. 18 and 19, agency officials said the Artemis 4 mission, the first after the Artemis 3 mission lands astronauts on the moon, will not attempt a landing itself.

Instead, Artemis 4 will be devoted to assembly of the lunar Gateway. The mission will deliver the I-Hab habitat module, developed by the European Space Agency and the Japanese space agency JAXA, to the Gateway. It will be docked with the first Gateway elements, the Power and Propulsion Element and Habitation and Logistics Outpost, which will launch together on a Falcon Heavy in late 2024 and spend a year spiraling out to the near-rectilinear halo orbit around the moon.

Essentially, the Biden administration appears to be switching back to NASA’s original plans, to require use of the Lunar Gateway station for any future lunar exploration, thus delaying that exploration considerably. Do not expect any of this schedule to take place as promised. The 2025 lunar landing will be delayed, as will all subsequent SLS launches for Artemis. The rocket is simply too complicated and cumbersome to even maintain one launch per year, while inserting Gateway into the mix only slows down lunar exploration even more.

NASA officials also revealed that they are limiting their lunar landing Starship contract with SpaceX to only that single planned ’25 Moon mission. For future manned missions to the Moon the agency will request new bids from the entire industry.

NASA’s Human Landing System (HLS) Option A award to SpaceX last year covers only development of a lander and a single crewed flight on Artemis 3. NASA will acquire future landings through a separate effort, called Lunar Exploration Transportation Services (LETS). The goal of LETS is to select one, and possibly more, companies to provide “sustainable” landing services.

The timing of LETS — a draft request for proposals is scheduled for release this spring — means there will be a gap of a couple years before the first landing service acquired through that program would be ready. “It’ll be about two years from the Option A award to the LETS award before we’ll have this sustainable lander,” Kirasich said. “It’s a different lander with more aggressive requirements than Option A.”

It appears that Jeff Bezos’ political lobbying efforts have paid off, and that NASA is now reopening bidding so that his consortium, led by Blue Origin, can once again compete for that lunar lander contract. Whether the Bezos’ team will be able to propose anything comparable to Starship is however very questionable.

None of this really hurts SpaceX. Its contract with NASA helps them develop a Starship lunar lander. Then, while NASA twiddles its thumbs building Gateway, it will be free to fly its own lunar missions, selling tickets on the open market. I suspect that — should NASA succeed in landing humans in ’25 — the next American manned landing on the Moon will be a bunch of SpaceX customers, not that second Artemis mission sometime in the late 2020s.

SpaceX of course will also be able to bid on that second lunar landing competition. And it will be hard for NASA not to award Starship a further contract, even if others are competing against it. Starship will be operational. The others will merely be proposed.

Flight dates for SpaceX’s next two manned flights to ISS revised

Capitalism in space: A NASA official yesterday announced that the flight dates for SpaceX’s next two manned flights have been firmed up, with the private commercial Axiom AX-1 flight delayed from February 21st to March 31st, followed two weeks later by NASA’s own manned mission on April 15th.

Axiom has also noted that this commercial flight, piloted by a former NASA astronaut and carrying three passengers, will be its only commercial manned flight in ’22.

…Commanded by former NASA astronaut Michael López-Alegría, Ax-1 will only carry private citizens. Each paying $55 million for the privilege, the mission’s three customers are Larry Connor, Mark Pathy, and Eytan Stibbe – all businessmen who’ve respectively amassed multmillion-dollar fortunes in real estate; entertainment and shipping; and military equipment and venture capitalism.

Their Dragon spacecraft will be Resilience, making its third flight.

Axiom’s next private commercial flight has now been delayed until ’23.

Boeing and NASA still aiming for a May launch of unmanned Starliner test demo

Capitalism in space: Boeing and NASA are still targeting a May launch of Starliner’s unmanned test demo flight to ISS, delayed since August because of a valve issue in the service module.

Though they think they have identified and fixed that sticky valve problem, they have also decided to replace the service module for the demo flight, using the module originally planned for the first manned flight that will follow.

Update on SLS: Still aiming for very unlikely March launch

A detailed update on the work being done by NASA and Boeing engineers to prepare SLS for its first unmanned test launch suggests that though a March launch is still the target, it is likely to be delayed.

The update at the link is very thorough, and outlines a large number of tests that need to be done to get this very cumbersome and complicated rocket ready for launch. They are just about done with the prep work for the core stage, and are now shifting to final testing of the upper stage, followed by some countdown sequence testing and a test of the flight termination system. In addition there are a number of other tests they wish to perform, all of which will take time.

Once these are done they will be ready to roll the rocket out to the launchpad for a final dress rehearsal countdown — dubbed the Wet Dress Rehearsal (WDR), now scheduled for mid- to late-February.

NASA will not set a launch date until after the WDR is completed and they can factor in any additional tasks with already-known work. “We’ve continually said that until we get through WDR we won’t set a launch date, so us getting out in mid-February for WDR allows them to look at March and April as opportunities,” Lanham said.

“I really can’t put my finger on it again until we come back from WDR and see if we have any issues there that we’ve got to go correct.” After the WDR test, the vehicle and Mobile Launcher will be rolled back to the VAB for final pre-launch maintenance and servicing.

Some have said the earliest realistic launch date is May, with the mid-summer more likely. We shall have to wait and see.

House Democrats attempt end-around of filibuster to pass election law using NASA bill

A bill initially written to give authorization to NASA lease its property to others and and passed by the Senate has been stripped entirely of that language by House Democrats and replaced with their proposal to federalize elections nationwide.

H.R. 5746 was introduced in October by Rep. Don Beyer (D-Va.), chair of the House Science Committee’s space subcommittee. The bill extended NASA’s authorization to enter into what are known as enhanced use leases, or EULs, of agency property to companies, government agencies, or educational institutions, for 10 years. The House passed the bill by a voice vote Dec. 8.

The Senate amended the bill, extending the EUL authorization by only three months instead of 10 years, and passed it by unanimous consent, sending it back to the House.

The Democratic leadership of the House, in an unusual move, then took the Senate-amended bill and stripped out the NASA provisions, replacing it with the text of two voting rights bills and now called the “Freedom to Vote: John R. Lewis Act.” They did so because H.R. 5746 had already passed the House and Senate, so the amended version could go directly to the Senate floor without the threat of a filibuster from Senate Republicans, who oppose the voting rights legislation. [emphasis mine]

The level of corruption exhibited by this Democratic Party action is beyond words. The Senate approved one bill. The House Democrats have now turned it into another bill that the Senate did not vote on initially.

In the past, such a corrupt action by the House would never have been attempted because the House would have known that the entire Senate would have rejected this tactic immediately as an insult to its legislative rights. Today however the Democrats care nothing for legalities or law or legislative rights. All they care about is power, and they are willing to do anything to get it. You can expect for certain that all but two Democrats in the Senate will support this crooked action.

That vote’s passage however rests with those two Democrats. Since this tactic is a direct attack on the filibuster, and if successful would forever make it null, we must wonder if Senators Kysten Sinema (D-Arizona) and Joe Manchin (D-West Virginia) will vote against it. If they don’t, their high-minded claims that they will not end the filibuster rule will be proven to be empty words.

NASA’s safety panel claims management expertise in ’21 annual report, demanding that NASA run Artemis using a “top-down” approach

NASA’s safety panel today issued its 2021 annual report, and rather than review issues of safety in the operations of the agency’s various manned programs, the panel focused on proposing a redesign of the management structure of NASA manned programs, demanding that NASA run Artemis using a “top-down” approach, taking power and control away from private commercial space and putting it in the hands of NASA’s bureaucracy. From the press release:

Specifically, the report recommends that NASA should develop a strategic vision for the future of space exploration and operations; establish and provide leadership through a “board of directors” that includes agency center directors and other key officials, with the emphasis on providing benefit to the agency’s mission as a cohesive whole; and manage Artemis as an integrated program with top-down alignment. The panel also reiterated a recommendation from its 2020 report that Congress designate a lead federal agency for civil space traffic management.

This summary captures nicely the substance of the entire report [pdf]. Rather than review the specific safety issues in each of NASA’s manned programs — the panel’s actual job — the panel decided it would look at how Congress, the White House, and NASA’s leadership have organized the management of its manned program, and tell them all how to do things.

None of this is the safety panel’s business. Such recommendations should come from Congress or the White House, or from a specific panel created by those elected officials or NASA’s top management, tasked with the specific job.

The panel meanwhile ignored its real job, to review the engineering of NASA’s manned program and spot areas where such work might need to be revised or fixed. While the panel spent its time in 2020 putting together this inappropriate report, it apparently missed entirely the valve problem in Boeing’s Starliner capsule that has caused an additional year delay in its launch.

This panel continues to demonstrate its corrupt and power-hungry attitude about how the U.S. should explore space. For years it did whatever it could to stymie NASA’s efforts to transfer ownership to the private sector, putting up false barriers to the launch of SpaceX’s manned Dragon capsule that made no sense and were really designed to keep all control within the government bureaucracy.

Now this panel has decided its job is no longer to review the specific technical and engineering issues that could cause a manned spacecraft failure, such as with Boeing’s Starliner. Instead it now believes it should be the designer of NASA’s entire management.

It is long past time that this panel is shut down. It isn’t doing its actual job, and is instead interfering with everyone else’s.

Engineers replace engine controller on SLS core; launch to be delayed

Engineers have successfully replaced the failed engine controller on the core stage of NASA’s SLS rocket.

Last week engineers and technicians successfully removed and replaced an engine controller from one of four RS-25 engines after the team identified an issue during a power-up test of the rocket’s core stage. Engineers are now performing standard engine controller diagnostic tests and check-outs, including controller power-up and flight software load. Subsequently, the team will work to complete all remaining SLS pre-flight diagnostic tests and hardware closeouts in advance of a mid-February rollout for a wet dress rehearsal in late February. NASA will set a target launch date after a successful wet dress rehearsal test.

The official schedule still lists the launch for February, but NASA has already admitted this is now impossible. Once they complete the wet dress rehearsal on the launchpad they will have to roll the rocket back into the Vehicle Assembly Building to do further tests. While it remains possible for NASA to meet an April launch window, more likely the agency will push back to windows during the summer.

Thus, the race between SLS and Starship for completing the first orbital flight remains neck-and-neck. Starship could launch this spring, but it faces an uncertain schedule determined not by SpaceX but by the bureaucracy in the federal government, which is reviewing the FAA’s environment reassessment for the Boca Chica launch site and really has no requirement to meet any schedule at all. The FAA says it plans to approve the reassessment by the end of February, but that is simply made up deadline. It could revise it at will at any time.

NASA meanwhile is still pushing to launch SLS in April, but this launch date is entirely unrealistic. Expect NASA to announce a new target date sometime in the summer in the coming weeks.

Webb deploys heat radiator

Engineers today successfully deployed the heat radiator on the James Webb Space Telescope, allowing for unfolding of its 21-foot-diameter primary mirror over the next two days, the final step in the telescope’s deployment.

At about 8:48 a.m. EST, a specialized radiator assembly necessary for Webb’s science instruments to reach their required low and stable operating temperatures deployed successfully. The Aft Deployable Instrument Radiator, or ADIR, is a large, rectangular, 4 by 8-foot panel, consisting of high-purity aluminum subpanels covered in painted honeycomb cells to create an ultra-black surface. The ADIR, which swings away from the backside of the telescope like a trap door on hinges, is connected to the instruments via flexible straps made of high-purity aluminum foil. The radiator draws heat out of the instruments and dumps it overboard to the extreme cold background of deep space.

The whole operation took fifteen minutes.

If all goes well, by Saturday night (January 8th) engineers and scientists will have in their hands the world’s largest infrared telescope, and it will be operating in space. Actual scientific observations however will not begin immediately. It will still take several weeks for the telescope to cool down to the very cold temperatures it needs to see faint infrared objects, and then about five more months of additional testing to precisely align the mirrors while figuring out how the telescope itself operates in space.

We should expect the first raw and unaligned infrared images in about a month, with the first official observations released sometime in the very early summer.

NASA finally makes available to the aerospace industry its new flight termination software

After what appears to be about a year and a half delay, NASA finally today made available its new flight termination software so that the aerospace industry can now test it.

“This is a major milestone that enables Rocket Lab and other U.S. launch companies to integrate the software now with their launch vehicle’s hardware and run performance simulations,” said David L. Pierce, Wallops Flight Facility director. “This is a key achievement toward enabling Rocket Lab launches from Wallops, in parallel with the NASA teams’ final safety certification steps, which are currently underway. Rocket Lab’s use of the NASA software will enable a high degree of confidence moving forward toward launch.”

Rocket Lab had hoped to launch from Wallops more than a year ago, but was blocked by NASA because the agency was apparently behind schedule in preparing this software. Now that it is finally available for testing, expect Rocket Lab to move swiftly, with a likely Wallops launch within months.

Webb engineers successfully deploy the telescope’s secondary mirror

Engineers today confirmed that the secondary mirror for the James Webb Space Telescope has successfully deployed, its tripod structure unfolding and locking into place.

In addition the cover protecting the Mid-Infrared Instrument (MIRI) was successfully unlocked. The instrument’s science team did not open the cover yet because the telescope hasn’t yet cooled enough, its sun shield only in place for a day or so.

Webb: Sun shield deployment completed

Engineers today successfully completed the full deployment of the sun shield of the James Webb Space Telescope.

The unfolding and tensioning of the sunshield involved 139 of Webb’s 178 release mechanisms, 70 hinge assemblies, eight deployment motors, roughly 400 pulleys, and 90 individual cables totaling roughly one quarter of a mile in length. The team also paused deployment operations for a day to work on optimizing Webb’s power systems and tensioning motors, to ensure Webb was in prime condition before beginning the major work of sunshield tensioning.

The process took eight days, and was by far the most complex such remote deployment ever attempted by an unmanned spacecraft. The shield is now in place to shade Webb from sunlight and heat and thus allow it to observe very faint infrared objects billions of light years away.

Next comes the deployment of Webb’s secondary mirror, followed by the unfolding of its main mirror.

Webb deployment resumes, with continuing success

After a day delay to assess the telescope’s earlier operation in space, engineers yesterday resumed the deployment of the James Webb Space Telescope’s sun shield.

First they began tensioning the shield’s first of five layers, completing that operation in about five and a half hours.

Next the engineers proceeded to tighten layers two and three, completing that task in about three hours.

Today they have begun tightening the last two layers. A live stream of this slow and relatively unexciting process (as long as nothing goes wrong) is available from NASA here.

Based on what has been done so far, it appears that the deployment of the sun shield, considered the most challenging part of Webb’s deployment, is going to complete successfully. While the unfolding and deployment of the mirror still must be done, getting the sun shield deployed eliminates one of the great concerns that has kept both astronomers and engineers awake nights for decades.

The unfurling of Webb’s sun shield begins

Engineers have begun the multi-day unfurling and deployment of the sun shield on the James Webb Space Telescope.

The first step is to deploy two booms on each side of the telescope that draw the shield itself outward.

The deployment of the first boom was held up several hours to give engineers time to make sure the protective covers had, in fact, rolled off to the side of the sunshade pallets as required.

“Switches that should have indicated that the cover rolled up did not trigger when they were supposed to,” NASA said in a blog post. “However, secondary and tertiary sources offered confirmation that it had.”

“The deployment of the five telescoping segments of the motor-driven mid-boom began around 1:30 p.m., and the arm extended smoothly until it reached full deployment,” NASA said.

Engineers then sent commands to deploy the second sunshade boom, which extended smoothly and locked in place at 10:13 p.m., finally giving Webb its iconic kite-like shape.

Next the shield has to be tightened in place, which will also separate and tighten in place the shield’s five layers. According to the schedule, the four layers will be tensioned today, with the fifth tomorrow.

The step-by-step deployment is outlined in detail here, and updates to the most recently completed step after it is finished.

1st stage of Webb sun shield deployment completed

The deployment of the forward and aft pallets required to support the sun shield for the James Webb Space Telescope has apparently been successfully completed.

The link takes you to the website that outlines each step in Webb’s entire 30-day deployment sequence, and is updated to show you the next required step as the process continues. Though I have yet to see any official announcement, this page now shows that both pallets have successfully unfolded and that the next step is removal of the covers that have protected the sun shield membrene during assembly and launch.

Deployment of Webb’s critical sunshield has begun

The deployment of the complex sunshield for the James Webb Space Telescope has successfully begun, and if all continues as planned, will continue for the next five days.

Early this afternoon the Webb mission operations team concluded the deployment of the first of two structures that hold within them Webb’s most unpredictable and in many ways complicated component: the sunshield.

The structures – called the Forward and Aft Unitized Pallet Structures – contain the five carefully folded sunshield membranes, plus the cables, pulleys, and release mechanisms that make up Webb’s sunshield. The team completed the deployment of the forward pallet at approximately 1:21 p.m. EST, after beginning the entire process about four hours earlier. The team will now move on to the aft pallet deployment.

Over the next five days the aft pallet must be deployed, along with a tower assembly that will raise the telescope itself away from the sunshield to better keep Webb cold. After this the deployment of the many additional parts of the shield will take place, a process that is probably the most complex in-space spacecraft deployment ever.

It is good news that so far all is proceeding as planned, and gives hope that all will continue to do so.

Webb: Course correction burn and main antenna deployment both a success

Over the weekend engineers for the James Webb Space Telescope successfully completed a course correction burn that put the telescope on route to is planned location a million miles from Earth.

They also successfully deployed the telescope’s main antenna.

Other steps completed on Webb’s first full day in space included the switch-on of temperature sensors and strain gauges on the telescope, used for monitoring Webb’s thermal and structural parameters, NASA said. The antenna release and first mid-course correction burn set the stage for the next step of Webb’s post-launch commissioning — the deployment and tensioning of the observatory’s tennis court-sized sunshield.

These next steps are likely the most risky part of the telescope’s deployment, as it involves the most moving parts and is the most complex. While similar such unfoldings have been done successfully many times before, they have also been the very prone to failure.

The sunshield must work however for Webb to operate. As an infrared telescope, it essentially detects heat, and if it is not well shielded from sunlight its images will be fogged.

The deployment is presently set to begin tomorrow.

Webb telescope reaches launchpad on Ariane 5 + how to watch launch

The James Webb Space Telescope, stacked on top of Arianespace’s Ariane 5 rocket, has finally reached its launchpad in French Guiana after twenty years of development costing 20 times its original budget.

The launch itself is now scheduled for December 25, 2021 at 7:20 am (Eastern). It will be live streamed by both NASA (in English) and Arianespace (with options in English, French, or Spanish).

I have embedded below NASA’s feed. As always, expect NASA to pump you with lots of propaganda during its live stream.

When all is said and done, Webb has the chance to show us things about the universe we’ve never seen before. Optimized for deep space cosmology, it will provide us a window into the earliest moments of the universe’s existence. And is infrared capabilities will allow it to peer into many nearer places obscured by dust with a resolution unmatched by previous telescopes.

Keep your fingers crossed all goes as planned.
» Read more

A detailed review of SLS’s present launch status

Link here. The article provides a detailed look at the engine controllers in the former shuttle engines that SLS is using on its core first stage, including some details about the failed unit and the issues involved in replacing it.

I found this historical data in the article most interesting:

The first attempt to launch Orbiter Atlantis and the STS-43 Shuttle vehicle was scrubbed before dawn on July 24, 1991, when the primary computer, DCU A, failed while propellants were being used loaded into the External Tank. … As a result, the launch was scrubbed to allow replacement of the controller, and the launch was rescheduled for August 1, 1991. The failure analysis of the controller revealed a broken blind lap solder joint connection of the bit jumper to the half stack, which is not a generic design problem.”

According to contemporaneous Shuttle Status Reports issued by NASA Public Affairs at KSC in late July, 1991, after the launch was scrubbed and the External Tank was drained and inerted, access to the engine area for maintenance was established on July 26. The broken engine controller was removed, and a new one was installed on July 27, followed by testing to verify the new controller on July 28; the three-day countdown was started over from the top on July 29 for the next launch attempt on the morning of August 1.

It took NASA less than a week to replace an engine controller in 1991. Now, it appears it might take NASA several months, including testing, to do the same thing on SLS. Moreover, the article suggests that there are other subcontractors and organizations (such as the range safety) that are also having trouble being ready for the presently scheduled mid-February launch.

All in all, this report suggests that SLS will not launch in February, will be delayed until April, with a strong chance that even that April date might not be met.

The report also illustrates the sluggish manner in which NASA operates today. Nothing is done with any speed. No task is done in one day if it can take a week. This is bad management, and also a very dangerous way to operate, as it actually encourages sloppiness because no one is under any pressure to work hard. The result has been endless niggling failures, each of which delays things interminably.

SLS likely facing another launch delay

Engineers for NASA’s SLS rocket have determined that they need to replace the flight controller on one of the engines in the rocket’s core stage, an action that will likely force a delay from the presently scheduled February launch date.

After performing a series of inspections and troubleshooting, engineers determined the best course of action is to replace the engine controller, returning the rocket to full functionality and redundancy while continuing to investigate and identify a root cause. NASA is developing a plan and updated schedule to replace the engine controller while continuing integrated testing and reviewing launch opportunities in March and April.

It appears they hope to make this change-out quickly and only have to delay one or two months, though at the moment it is also unclear this will be possible.

NASA approves Axiom’s second commercial flight to ISS

In a strangely worded NASA press release, the agency announced that it has “selected” Axiom for the second private commercial manned mission to ISS.

NASA has selected Axiom Space for the second private astronaut mission to the International Space Station. NASA will negotiate with Axiom on a mission order agreement for the Axiom Mission 2 (Ax-2) targeted to launch between fall 2022 and late spring 2023.

As at present there appears to be no other American company planning commercial manned flights to ISS, NASA wasn’t “selecting” Axiom at all. All NASA was doing was approving Axiom’s proposal to fly the mission to NASA’s space station, while confirming that Axiom will pay NASA’s greatly increased charges, raised about 700% more than the older price list.

The language of this announcement, combined with the exorbitant NASA charges, is only going to accelerate the effort of private companies, including Axiom, to build their own independent space stations. It isn’t NASA’s place to “select” any privately funded commercial flight into space, ever. That this government agency is making believe it has that right is only going to alienate the new private space industry, giving them reason to get away from NASA as fast as possible.

Meanwhile, Axiom is already scheduled to fly its first tourist flight to ISS in February 2022. The second flight that NASA “selected” today is to be followed by two more, for a total of four tourist flights. At that point, around 2024, Axiom will then launch its first module to ISS, beginning the process of relying less on NASA and leading to the undocking of Axiom’s station from ISS.

SpaceX launches NASA X-ray telescope

Capitalism in space: SpaceX early this morning successfully launched NASA’s Imaging X-ray Polarimetry Explorer (IXPE), a small X-ray telescope designed to black holes and neutron stars.

The first stage, making its fifth flight, successfully landed on a drone ship in the Atlantic.

This launch, SpaceX’s 28th for 2021, extends once again the company’s all time record for the most launches in a year by a private company.

The leaders in the 2021 launch race:

46 China
28 SpaceX
21 Russia
6 Europe (Arianespace)
5 ULA
5 Rocket Lab

China’s lead over the U.S, in the national rankings has now shrunk to 46 to 45. The launch was the 121st in 2021, making this year tied as the seventh most active year in the history of space, a ranking that is sure to go up before the end of the year.

NASA upgrades software for monitoring potentially dangerous asteroids

NASA has installed a major upgrade to the software it uses for monitoring, tracking, and predicting the future orbits of potentially dangerous asteroids.

Sentry [the original software used for the past 20 years] was very effective at calculating orbital paths based on how an asteroid is affected by the gravitational pull of the Sun and planets, but there were a few factors that it couldn’t account for. In the long run, these uncertainties can snowball into many possible orbits that may or may not impact Earth.

The Yarkovsky effect, for instance, is where the Sun unevenly heats the surface of an asteroid as it spins, creating thermal forces between the “day” and “night” sides of the rock that can produce thrust. Other times, asteroids that swing past Earth very closely could be nudged into different orbits by the planet’s gravity, changing the paths of their eventual return.

The first Sentry system couldn’t incorporate either of these two factors, meaning that for special case asteroids like Bennu or Apophis, astronomers would have to manually analyze their orbits, which is a complex and time-consuming process.

But Sentry-II is designed to account for things like these. This latest version uses a different algorithm that models thousands of random points within the uncertainty space of an asteroid’s orbit, then figures out which ones have a chance of striking Earth in future. This, the team says, could help find scenarios that have very low probability of impact.

What this upgrade means is that as new asteroids are discovered the software will be able to very quickly calculate with better accuracy any potential impacts in the coming centuries. The results won’t be perfect, but less manual work will be necessary, meaning fewer dangerous asteroids will fall through the cracks.

Astra’s next launch to be in Florida

According to statements by Astra and the Space Force, the startup’s next launch, its first operational mission intended to place payloads in orbit, will occur in Florida at Cape Canaveral.

Astra announced that it will conduct a launch of its Rocket 3.3 vehicle from Space Launch Complex 46 at Cape Canaveral Space Force Station in January. The pad, originally developed for tests of the Trident submarine-launched ballistic missile, is now operated by Space Florida. It has been used for launches of Athena rockets and, in 2019, a test of the launch abort system for NASA’s Orion spacecraft.

..Astra said in the statement that it will carry a payload for NASA on that flight but did not disclose additional details. A company spokesperson said this launch will be for NASA’s Venture Class Launch Services (VCLS) program, under a VCLS Demo 2 contract the company won a year ago.

That launch, designated ELaNa 41 by NASA, will carry five cubesats, according to a NASA manifest. Four of the cubesats are from universities: BAMA-1 from the University of Alabama, CURIE and QubeSat from the University of California Berkeley and INCA from New Mexico State University. The fifth, R5-S1, is from NASA’s Johnson Space Center.

No specific date for the launch has as yet been announced.

NASA buys more Dragon manned flights

Capitalism in space: To give it some coverage because of continuing delays in Boeing’s Starliner manned capsule, NASA announced yesterday that it has awarded SpaceX contracts for three more manned Dragon manned flights to ISS.

NASA issued a contract notification announcing its plans to issue a sole-source award to SpaceX for three missions. Those missions would be in addition to the six “post-certification missions,” or PCMs, that SpaceX won as part of its $2.6 billion Commercial Crew Transportation Capability (CCtCap) contract in 2014. The announcement did not state the price of those three new missions.

This is money that would have gone to Boeing, if it had gotten its act together and gotten Starliner flying on schedule. Instead, SpaceX is making the profits.

There has been no updates from Boeing since October on the valve issue that now stalls Starliner. While Boeing claims it is aiming for an unmanned demo flight to ISS in early ’22, this remains entirely speculative at this moment.

More delays for SLS?

According to a report today at Ars Technica, there is an engine issue with the SLS rocket presently being prepared for a February unmanned test flight that could delay the launch for months.

The info is buried at the very bottom of the article:

There’s an issue with an SLS engine controller. This past weekend, rumors emerged about a problem with the controller for one of the four RS-25 engines that power the Space Launch System. NASA has not officially commented, but Aviation Week’s Irene Klotz spoke with Aerojet’s RS-25 program manager, Jeff Zotti. Troubleshooting the problem began on November 22, Aviation Week reported.

Schedule impacts yet to be determined … If necessary, “replacing a line or a component … we’re probably talking about multiple days. Replacing an engine, we’re probably talking about multiple weeks,” Zotti told the publication. “On top of that, we have to assess what that does and how that affects the vehicle and the integration activities that are going on,” he added. All of that must be factored into a potential delay of the launch, presently scheduled for February 12. A summer launch for the SLS now seems far more likely than spring.

Any delay beyond March poses a very serious and complex problem. The solid rocket strap-ons have a one year life expectancy once stacked, and both were initially stacked about a year ago. The February launch pushes that life span somewhat. A longer delay is more than can be waived.

NASA awards contracts to three private space station projects

Capitalism in space: NASA today announced development contract awards to three different private space station projects.

  • Nanoracks Starlab concept won $160 million. Partners include Voyager Space and Lockheed Martin.
  • Blue Origin’s Orbital Reef project was awarded $130 million, partnering with Sierra Space, Boeing, and Redwire.
  • Northrop Grumman won $125.6 million on a concept based on upgrades to its Cygnus freighter.

All three contracts are Space Act agreements, designed by NASA to jumpstart the companies and their design efforts. All three are in addition to the effort by Axiom to build its own ISS modules that will eventually detach to form its own independent station.

That’s four private American space stations now in the works. All are aiming to launch before this decade is out.

Astronauts successfully complete spacewalk, replace broken antenna

After a two day delay caused by the danger of impact from debris from the Russian anti-sat test, two astronauts today successfully completed a six-hour-plus spacewalk to replace a malfunctioning antenna on ISS.

NASA astronauts Thomas Marshburn and Kayla Barron concluded the first Expedition 66 spacewalk at 12:47 p.m. EST, after 6 hours and 32 minutes. Marshburn and Barron successfully installed an S-band Antenna Subassembly (SASA) on the Port-1 truss structure and stowed the failed antenna. Additionally, the pair completed get-ahead tasks on the Port-4 truss structure, including resetting the torque on a set of bolts.

This was the fifth spacewalk for Marshburn, the first for Barron, and the 13th spacewalk at the International Space Station this year. Marshburn has now spent a total of 31 hours and one minute spacewalking, and Barron’s spacewalking time is now 6 hours and 32 minutes. Space station crew members have now spent a total of 64 days, 12 hours, and 26 minutes working outside the station conducting 245 spacewalks in support of assembly and maintenance of the orbiting laboratory.

It is unclear if any debris that canceled the spacewalk earlier in the week ever came close to the station. It is just as likely that NASA was overly cautious.

1 18 19 20 21 22 70