Webb’s primary mirror successfully deployed

Today engineers successfully completed the unfolding of the primary mirror on the James Webb Space Telescope.

The two wings of Webb’s primary mirror had been folded to fit inside the nose cone of an Arianespace Ariane 5 rocket prior to launch. After more than a week of other critical spacecraft deployments, the Webb team began remotely unfolding the hexagonal segments of the primary mirror, the largest ever launched into space. This was a multi-day process, with the first side deployed Jan. 7 and the second Jan. 8.

Mission Operations Center ground control at the Space Telescope Science Institute in Baltimore began deploying the second side panel of the mirror at 8:53 a.m. EST. Once it extended and latched into position at 1:17 p.m. EST, the team declared all major deployments successfully completed.

Next step over the next few months will be aligning the primary mirrors 18 segments with each other as well as the secondary mirror. First science images are expected during the summer, but do not be surprised if NASA releases some test images before then, should all be well and it obtains some eye candy.

Webb deploys heat radiator

Engineers today successfully deployed the heat radiator on the James Webb Space Telescope, allowing for unfolding of its 21-foot-diameter primary mirror over the next two days, the final step in the telescope’s deployment.

At about 8:48 a.m. EST, a specialized radiator assembly necessary for Webb’s science instruments to reach their required low and stable operating temperatures deployed successfully. The Aft Deployable Instrument Radiator, or ADIR, is a large, rectangular, 4 by 8-foot panel, consisting of high-purity aluminum subpanels covered in painted honeycomb cells to create an ultra-black surface. The ADIR, which swings away from the backside of the telescope like a trap door on hinges, is connected to the instruments via flexible straps made of high-purity aluminum foil. The radiator draws heat out of the instruments and dumps it overboard to the extreme cold background of deep space.

The whole operation took fifteen minutes.

If all goes well, by Saturday night (January 8th) engineers and scientists will have in their hands the world’s largest infrared telescope, and it will be operating in space. Actual scientific observations however will not begin immediately. It will still take several weeks for the telescope to cool down to the very cold temperatures it needs to see faint infrared objects, and then about five more months of additional testing to precisely align the mirrors while figuring out how the telescope itself operates in space.

We should expect the first raw and unaligned infrared images in about a month, with the first official observations released sometime in the very early summer.

Webb engineers successfully deploy the telescope’s secondary mirror

Engineers today confirmed that the secondary mirror for the James Webb Space Telescope has successfully deployed, its tripod structure unfolding and locking into place.

In addition the cover protecting the Mid-Infrared Instrument (MIRI) was successfully unlocked. The instrument’s science team did not open the cover yet because the telescope hasn’t yet cooled enough, its sun shield only in place for a day or so.

Webb: Sun shield deployment completed

Engineers today successfully completed the full deployment of the sun shield of the James Webb Space Telescope.

The unfolding and tensioning of the sunshield involved 139 of Webb’s 178 release mechanisms, 70 hinge assemblies, eight deployment motors, roughly 400 pulleys, and 90 individual cables totaling roughly one quarter of a mile in length. The team also paused deployment operations for a day to work on optimizing Webb’s power systems and tensioning motors, to ensure Webb was in prime condition before beginning the major work of sunshield tensioning.

The process took eight days, and was by far the most complex such remote deployment ever attempted by an unmanned spacecraft. The shield is now in place to shade Webb from sunlight and heat and thus allow it to observe very faint infrared objects billions of light years away.

Next comes the deployment of Webb’s secondary mirror, followed by the unfolding of its main mirror.

Webb deployment resumes, with continuing success

After a day delay to assess the telescope’s earlier operation in space, engineers yesterday resumed the deployment of the James Webb Space Telescope’s sun shield.

First they began tensioning the shield’s first of five layers, completing that operation in about five and a half hours.

Next the engineers proceeded to tighten layers two and three, completing that task in about three hours.

Today they have begun tightening the last two layers. A live stream of this slow and relatively unexciting process (as long as nothing goes wrong) is available from NASA here.

Based on what has been done so far, it appears that the deployment of the sun shield, considered the most challenging part of Webb’s deployment, is going to complete successfully. While the unfolding and deployment of the mirror still must be done, getting the sun shield deployed eliminates one of the great concerns that has kept both astronomers and engineers awake nights for decades.

1st stage of Webb sun shield deployment completed

The deployment of the forward and aft pallets required to support the sun shield for the James Webb Space Telescope has apparently been successfully completed.

The link takes you to the website that outlines each step in Webb’s entire 30-day deployment sequence, and is updated to show you the next required step as the process continues. Though I have yet to see any official announcement, this page now shows that both pallets have successfully unfolded and that the next step is removal of the covers that have protected the sun shield membrene during assembly and launch.

Deployment of Webb’s critical sunshield has begun

The deployment of the complex sunshield for the James Webb Space Telescope has successfully begun, and if all continues as planned, will continue for the next five days.

Early this afternoon the Webb mission operations team concluded the deployment of the first of two structures that hold within them Webb’s most unpredictable and in many ways complicated component: the sunshield.

The structures – called the Forward and Aft Unitized Pallet Structures – contain the five carefully folded sunshield membranes, plus the cables, pulleys, and release mechanisms that make up Webb’s sunshield. The team completed the deployment of the forward pallet at approximately 1:21 p.m. EST, after beginning the entire process about four hours earlier. The team will now move on to the aft pallet deployment.

Over the next five days the aft pallet must be deployed, along with a tower assembly that will raise the telescope itself away from the sunshield to better keep Webb cold. After this the deployment of the many additional parts of the shield will take place, a process that is probably the most complex in-space spacecraft deployment ever.

It is good news that so far all is proceeding as planned, and gives hope that all will continue to do so.

Webb: Course correction burn and main antenna deployment both a success

Over the weekend engineers for the James Webb Space Telescope successfully completed a course correction burn that put the telescope on route to is planned location a million miles from Earth.

They also successfully deployed the telescope’s main antenna.

Other steps completed on Webb’s first full day in space included the switch-on of temperature sensors and strain gauges on the telescope, used for monitoring Webb’s thermal and structural parameters, NASA said. The antenna release and first mid-course correction burn set the stage for the next step of Webb’s post-launch commissioning — the deployment and tensioning of the observatory’s tennis court-sized sunshield.

These next steps are likely the most risky part of the telescope’s deployment, as it involves the most moving parts and is the most complex. While similar such unfoldings have been done successfully many times before, they have also been the very prone to failure.

The sunshield must work however for Webb to operate. As an infrared telescope, it essentially detects heat, and if it is not well shielded from sunlight its images will be fogged.

The deployment is presently set to begin tomorrow.

Webb successfully launched

Early this morning an Ariane 5 rocket successfully launched the James Webb Space Telescope from French Guiana.

The key moment that indicated the launch was success was, after Webb was deployed from the rocket’s upper stage, its solar panels deployed and the telescope began receiving power from them.

The launch itself was something that has been done by the Ariane 5 rocket many many times, without failure. Now comes the part of this operation that has never been done before.

Now “30 days of terror” begin, as JWST starts its career in space. First, it will take the space telescope 30 days to reach the start of its halo orbit at L2. On its way, the telescope must unfurl its 18 gold-plated beryllium mirror segments using 132 actuators. It will also have to deploy its five-layer, origami sunshield and cool down to below 50K (-223°C or -370°F) to begin the start of science operations in 2022.

NASA has a webpage that shows the step-by-step deployment, and allows you to see the status at any time during the next 30 days.

After almost twenty years of development and a budget that went 20x over its original estimate, let’s us all hope that Webb deploys properly and begins collecting data as intended. If it does, it will allow astronomers to make ground-breaking discoveries, and we shall gain a better idea of what lies hidden behind that black sky that surrounds us.

As for the 2021 launch race, this is the updated leader board:

49 China
31 SpaceX
22 Russia
7 Europe (Arianespace)

China will likely be the winner in the national rankings, 49 to 48 over the U.S. This was the 130th successful launch in 2021, only the second time in the history of space exploration that the world reached that number of launches in a single year.

Webb telescope reaches launchpad on Ariane 5 + how to watch launch

The James Webb Space Telescope, stacked on top of Arianespace’s Ariane 5 rocket, has finally reached its launchpad in French Guiana after twenty years of development costing 20 times its original budget.

The launch itself is now scheduled for December 25, 2021 at 7:20 am (Eastern). It will be live streamed by both NASA (in English) and Arianespace (with options in English, French, or Spanish).

I have embedded below NASA’s feed. As always, expect NASA to pump you with lots of propaganda during its live stream.

When all is said and done, Webb has the chance to show us things about the universe we’ve never seen before. Optimized for deep space cosmology, it will provide us a window into the earliest moments of the universe’s existence. And is infrared capabilities will allow it to peer into many nearer places obscured by dust with a resolution unmatched by previous telescopes.

Keep your fingers crossed all goes as planned.
» Read more

ESA delays Webb launch one day due to weather

The European Space Agency (ESA) announced late yesterday that, due to “adverse weather conditions” in French Guiana, it has delayed the launch of the James Webb Space Telescope on an Ariane 5 rocket one day to December 25th.

The announcement also stated that the final launch readiness review also approved the launch, though no update has yet been issued on the ground control communications problem that had caused a two day delay last week.

Meanwhile, this story and its headline encapsulates the terror I think many astronomers presently feel about this telescope:

Why Astronomers Are “Crying and Throwing Up Everywhere” Over the Upcoming Telescope Launch

The sense is one of helpless panic among astronomers who want to use Webb. They know it will do really cutting edge science, but they also know that many things can go wrong, and the history of the telescope (ten years late and 20x overbudget) will likely make replacing it impossible.

And many things can go wrong. Below is NASA’s video showing the telescope’s complex unfolding, step-by-step, after launch.
» Read more

Webb launch confirmed for December 24, 2021

Ten years late and twenty times over budget the European Space Agency (ESA) yesterday confirmed that the launch of NASA’s infrared James Webb Space Telescope is now scheduled for December 24, 2021.

The ESA announcement is only a couple of sentences long, and does not mention if engineers had solved the intermittent ground communications issue with the telescope. Further tweets from ESA and NASA also said nothing about the communication issue.

A final readiness review is set for December 21st where a final launch decision will be made.

Engineers: Webb undamaged by “incident”, ready for December 22nd launch

Arianespace engineers have confirmed after testing that the James Webb Space Telescope was undamaged by “incident” that occurred during stacking, and have okayed the resumption of the telescope’s preparation for launch.

On Wednesday, Nov. 24, engineering teams completed these tests, and a NASA-led anomaly review board concluded no observatory components were damaged in the incident. A “consent to fuel” review was held, and NASA gave approval to begin fueling the observatory. Fueling operations will begin Thursday, Nov. 25, and will take about 10 days.

The launch is now set for December 22nd.

NASA now targets December 18, 2021 for launch of Webb

NASA today announced that it and the European Space Agency have scheduled the Ariane 5 launch of the James Webb Space Telescope from French Guiana for December 18, 2021.

The agency set the new target launch date in coordination with Arianespace after Webb recently and successfully completed its rigorous testing regimen – a major turning point for the mission. The new date also follows Arianespace successfully launching an Ariane 5 rocket in late July and scheduling a launch that will precede Webb. The July launch was the first for an Ariane 5 since August 2020.

Launching before the end of ’21 will allow NASA to claim that Webb is only be ten years behind schedule, not eleven. The cost overruns however remain astronomical (no pun intended). Initially budgeted at $500 million, Webb is now estimated to have cost $10 billion.

Once launched the telescope will take about six months to slowly move to its Lagrange point location about a million miles from the Earth, in the Earth’s shadow. During that time it will also be steadily deploying its many segmented mirror for infrared observations (an important detail as Webb is not a replacement for Hubble, which does most of its observations in the optical wavelengths).

Should deployment and placement go as planned, Webb will undoubtedly do ground-breaking astronomy, especially in the field of deep space cosmology. If anything should go wrong, any repair mission will take at a minimum five years to mount, if ever.

Keep those fingers and toes crossed!

Webb telescope finally completed, ready for shipment to launchpad

After more than two decades of construction (ten years behind schedule) and more than $10 billion (20 times the original cost), the infrared James Webb Space Telescope has finally completed its testing and is ready for shipment to its launch site in French Guiana to be mounted on an Ariane 5 rocket.

Now that observatory testing has concluded, shipment operations have begun. This includes all the necessary steps to prepare Webb for a safe journey through the Panama Canal to its launch location in Kourou, French Guiana, on the northeastern coast of South America. Since no more large-scale testing is required, Webb’s clean room technicians have shifted their focus from demonstrating it can survive the harsh conditions of launch and work in orbit, to making sure it will safely arrive at the launch pad. Webb’s contamination control technicians, transport engineers, and logistics task forces are all expertly prepared to handle the unique task of getting Webb to the launch site. Shipping preparations will be completed in September.

If all goes well, NASA and ESA hope to launch the telescope in late October. It will then take about six months for the telescope to unfold and reach its operating position a million miles from Earth in the Earth’s shadow.

Let us all pray that everything works. If it does not, there will be nothing that can be done to fix it for probably at least five years, if then, as it will be out of reach of any maintenance mission, manned or unmanned.

Problem with Ariane 5 rocket causes Arianespace to delay Webb telescope launch

As first revealed in mid-May, Arianespace has been forced to delay the launch of the James Webb Space Telescope by at least one month because of a problem with the fairing on its Ariane 5 rocket, found during an August 2020 launch.

There have been no Ariane 5 launches since. According to yesterday’s press briefing, however:

“The origin of the problem has been found. Corrective actions have been taken,” Daniel de Chambure, acting head of Ariane 5 adaptations and future missions at ESA, said. “The qualification review has started, so we should be able to confirm all that within a few days or weeks.” He did not elaborate on the problem or those corrective actions, beyond stating that the problem took place during separation of the payload fairing. Industry sources said in May that, on the two launches, the separation system imparted vibrations on the payload above acceptable limits, but did not damage the payloads.

It appears this new delay to Webb’s launch is because two commercial payloads must lift off first before Webb, with the first now scheduled for July. According to Arianespace, it will take two months prep for the next commercial launch, followed by two months prep for the Webb launch. That puts the launch of Webb in November.

Overall this particular delay is slight, only a few weeks, and pales in comparison to the ten years of delays experienced by NASA during development and construction of Webb. It also will add very little to the telescope’s overall budget, which has grown from an original price of $500 million to now about $10 billion.

GAO finds more NASA cost overruns in Webb, SLS, and Orion

GAO graph documenting NASA's big project delays and cost overruns

The annual Government Accountability Office’s (GAO) report on major NASA-led programs has found that the cost overruns and scheduling problems it has documented now for years continued in 2020.

You can obtain the report here. The graph to the left, from the report, summarizes the data quite succinctly.

The cumulative cost overrun of 20 major programs in development, defined as those with total costs of at least $250 million, grew to more than $9.6 billion in the report. Three programs — the James Webb Space Telescope, Orion spacecraft and Space Launch System — account for $8 billion of that total, including $4.4 billion for JWST alone.

SLS and the Exploration Ground Systems program accounted for effectively all of the $1.1 billion in overruns in 2020. … SLS alone accounted for nearly $990 million in cost increases. About two-thirds of that increase came from NASA adopting a GAO recommendation to lower the original baseline cost estimate for SLS to properly account for work that had been shifted to later phases of the program.

The report also documented almost 20 years of cumulative delays, with Webb leading the way with delays of more than seven years. The new report added 37 more months of delays during the last year.

The report, and NASA, laid the blame for many of the more recent delays and cost overruns on last year’s COVID epidemic, but if so those delays were imposed by choice, not necessity, considering how both China and SpaceX moved forward without any delays during the same time period. In reporting on NASA for the last three decades I have found it willing to initiate long delays at the drop of a hat, sometimes for reasons, such as a storm that causes some minor damage, that do not justify either the delay or its length. The COVID panic was just another example of this.

NASA confident Webb will launch in October

In a briefing held yesterday, NASA officials — in summarizing the status of the James Webb Space Telescope — stated they were presently confident that its launch will take place in October this year, as presently planned.

[Eric Smith, JWST program scientist> said the program is dealing with one new technical issue. Two communications transponders suffered separate problems during testing in January. Engineers have tracked down the problems with the two units and started repairs this week. “Those boxes will be back in time for us to make our planned shipping date,” he said.

That issue, he acknowledged, will use some of the remaining schedule margin. “The plan right now is that we’ll get them back in time so that we don’t have to use all of it,” he said. “That’s the main thing that we’re watching regarding the margin.”

If launched in October, Webb will only be a decade behind schedule and a mere 20 times over budget, having been initially proposed to launch in 2011 for a cost of $500 million. Instead, it will cost about $10 billion.

The article also notes that the Biden administration might change the telescope’s name because Webb as a bureaucrat early in his career apparently publicly opposed homosexual rights. Such opinions can no longer be allowed, and anyone who has them must be blackballed as quickly as possible.

No matter. Webb was merely NASA’s administrator through almost its entire first decade, leading the agency in its triumph over the Soviets in the race to the Moon. Such achievements cannot be honored as they illustrate the past greatness of America. Moreover, Webb was a white man, and this makes him totally unqualified to receive any laurels. Today’s modern America hates itself and all white men.

The article also notes a variety of issues that will cause more delays of the new big astronomy boondoggle at NASA, the Roman Space Telescope. They say its launch will likely be delayed to 2026 because of the Wuhan flu panic. I predict this is only a foretaste. Expect many more delays and budget overruns, probably pushing its launch into the 2030s.

But no matter. What is really important is that this new boondoggle is named for a woman!

Surprisingly low number of observation proposals from astronomers for Webb telescope

In preparation for the launch of the James Webb Space Telescope in ’21, the Space Telescope Science Institute (STScI) that will operate it has begun accepting observation proposals from astronomers, and has apparently discovered that the number of proposals, dubbed the subscription rate, is surprisingly low.

The stats of the James Webb space telescope cycle 1 proposal round came in the other day. In summary: an over subscription rate of 1:4. A little less even.

There was immediate spin how the stats were a good thing. Enthusiasm from around the globe! So many investigators! But that does not change that the 1:4 oversubscription is a disappointment. If I were part of the project, this would and should worry me.

If they got exactly the right number of proposals to precisely use all of the telescope’s observation time, the subscription rate would be 1. An oversubscription rate of 1.4 seems good, but in truth it is tiny compared to Hubble and other space telescopes, and horrible considering the cost of Webb (almost $10 billion, 20x what it was originally budgeted).

The author at the link provides some technical reasons for the low interest, some of which are the fault of the Webb management team (such as a very complicated proposal process) and some that are beyond their control (the Wuhan panic). He also provides suggestions that might help.

Either way, the relatively low interest I think is rooted in Webb’s initial genesis. It was pushed by the cosmological community and its design thus optimized for studying the early universe. Other astronomical fields were pushed aside or given a lower priority so that the telescope does not serve them as well.

The result is that a lot of astronomers have been finding other more appropriate and already functioning telescopes to do their work, bypassing Webb entirely. They are probably also bypassing Webb because it seems foolish to spend the inordinate amount of time putting together a proposal for a telescope a decade behind schedule that carries an enormous risk of failure once it is launched.

NASA confirms Webb launch delayed again

NASA officials yesterday confirmed that, due to the new work conditions and the lock down imposed by the Wuhan flu panic, the launch of the James Webb Space telescope will not occur in March 2021.

“We will not launch in March,” said Thomas Zurbuchen, the space agency’s associate administrator for science. “Absolutely we will not launch in March. That is not in the cards right now. That’s not because they did anything wrong. It’s not anyone’s fault or mismanagement.”

Zurbuchen made these comments at a virtual meeting of the National Academies’ Space Studies Board. He said the telescope was already cutting it close on its schedule before the COVID-19 pandemic struck the agency and that the virus had led to additional lost work time. “This team has stayed on its toes and pushed this telescope forward at the maximum speed possible,” he said. “But we’ve lost time. Instead of two shifts fully staffed, we could not do that for all the reasons that we talk about. Not everybody was available. There were positive cases here and there (in the surrounding area, not on site). And so, perhaps, we had only one shift.”

No new target date has been set, though the comments even hinted that they might not be able to do it in 2021.

Webb will cost 20 times more than originally budgeted ($500 million vs $10 billion) and is now more than a decade behind schedule. In the process, those overages and delays wiped out almost all of NASA’s other astronomy projects during the 2010s.

But don’t worry! Once Webb launches the task of wiping out more astronomy projects with overages and delays will be courageously taken up by NASA’s Roman Space Telescope (formerly WFIRST), already behind schedule and over budget, and it is still only in the design phase.

GAO warns of more Webb delays

The race to the bottom between Webb and SLS continues! A new Government Accountability Office (GAO) report warns that there is high likelihood that NASA will not meet its March 2021 target launch date for the James Webb Space Telescope.

The report noted that the program performed an updated joint confidence level analysis of the mission’s cost in schedule in October. “Because of schedule delays resulting from technical challenges coupled with remaining risks faced by the project, the analysis assessed only a 12 percent confidence level for the project’s ability to meet the March 2021 launch readiness date,” the report stated.

NASA missions usually set cost and schedule estimates at the 70% confidence level. Using that metric, the launch would likely take place in July 2021, a delay of four months, according to the report.

Webb is now more than a decade behind schedule, with its budget ballooning from $1 billion to just under $10 billion. These facts essentially wiped out almost all new astronomical projects in the 2010s.

Webb assembled for the first time

Northrop Grumman engineers have successfully completed, for the first time, the full assembly of the James Webb Space Telescope.

To combine both halves of Webb, engineers carefully lifted the Webb telescope (which includes the mirrors and science instruments) above the already-combined sunshield and spacecraft using a crane. Team members slowly guided the telescope into place, ensuring that all primary points of contact were perfectly aligned and seated properly. The observatory has been mechanically connected; next steps will be to electrically connect the halves, and then test the electrical connections.

…Next up for Webb testing, engineers will fully deploy the intricate five-layer sunshield, which is designed to keep Webb’s mirrors and scientific instruments cold by blocking infrared light from the Earth, Moon and Sun. The ability of the sunshield to deploy to its correct shape is critical to mission success.

Only a decade late and nine times over budget ($1 billion vs $9 billion). Let us all pray that when this spacecraft finally reaches its operational location a million miles from Earth it operates as designed.

Head of Webb investigation: Webb was “a step too far”

The head of an investigation panel into the James Webb Space Telescope admitted this week that, though he and the panel fully support the telescope’s completion and launch, he also believes the telescope was too ambitious and “a step too far.”

Speaking at a meeting of the Committee on Astronomy and Astrophysics of the National Academies’ Space Studies Board Oct. 29, Tom Young said that while the mission may ultimately be a success, its difficulties provide lessons as NASA considers future large astronomy missions in the next decadal survey.

“I, personally, have come to the conclusion that JWST had too many inventions, too much risk, and was a step too far,” he said at the end of a presentation about the review board’s work.

Young emphasized that he was neither opposed to JWST being completed nor had doubts it could be done successfully. “There are a group people who are diehard supporters of JWST, and there are others who support it, but they’re really angry at the cost growth and the schedule delays,” he said.

You think? Webb was supposed to cost about $500 million, and launch in 2007. Its budget is now almost $10 billion, and it will not launch before 2021. In the process it has destroyed the entire astronomy program at NASA, preventing the construction of any other space telescopes.

The key question is whether the astronomy community or NASA has learned anything from this disaster. I personally am doubtful, since they are still pushing for WFIRST, a similar big boondoggle that will cost billions and is already overbudget and behind schedule, though it is only in its design stage.

Webb faces more delays, cost overruns

A new GAO report released yesterday says that the James Webb Space Telescope faces further delays and cost overruns.

This is par for the course. Webb has become an incredible boondoggle. I hope it eventually gets launched and works, but its gigantic cost, $8 to $9 billion (compared to an original $1 billion budget), and delayed schedule suggests that this was not the right way for NASA or the astronomical community to build its space telescopes. Further, this quote from the story suggests something fundamentally wrong:

The GAO report also noted that, during the sunshield deployment exercises, Northrop discovered several tears in the material which it attributed to “workmanship error.” Those tears can be repaired but may consume more schedule reserve.

Is this thing really going to work? I really hope so, but have been increasingly doubtful as the delays and problems have piled up.

Meanwhile, NASA and the astronomical community is still pushing to get funding for its next “Webb,” the Wide-Field Infrared Survey Telescope (WFIRST). This project, similar in scope as Webb, is hardly off the ground and already has budget overrun issues. The Trump administration recommended cancelling in its budget proposal earlier this month, but I would be surprised if that recommendation goes through, considering the pork this new project represents.

Webb Space Telescope delayed again

NASA announced today that they are further delaying the launch of the James Webb Space Telescope from October 2018 to late spring 2019.

NASA’s James Webb Space Telescope now is planning to launch between March and June 2019 from French Guiana, following a schedule assessment of the remaining integration and test activities. Previously Webb was targeted to launch in October 2018. “The change in launch timing is not indicative of hardware or technical performance concerns,” said Thomas Zurbuchen, associate administrator for NASA’s Science Mission Directorate at Headquarters in Washington. “Rather, the integration of the various spacecraft elements is taking longer than expected.”

As part of an international agreement with the ESA (European Space Agency) to provide a desired launch window one year prior to launch, NASA recently performed a routine schedule assessment to ensure launch preparedness and determined a launch schedule change was necessary. The careful analysis took into account the remaining tasks that needed to be completed, the lessons learned from unique environmental testing of the telescope and science instruments at NASA’s Goddard Space Flight Center in Greenbelt, Maryland, and the current performance rates of integrating the spacecraft element.

Webb’s original launch date was supposed to be 2011, making its launch now verging on a decade late. The original budget for the telescope was supposed to be $1 billion. It is now expected to cost more than $9 billion. Like SLS/Orion, this project more resembles feather-bedding, providing NASA employees and the contractors involved a steady paycheck, regardless of whether they ever get anything done. In fact, both Webb and SLS/Orion seemed designed to encourage failure. The project never gets cancelled no matter what goes wrong. Instead, more money gets poured in.

Problems with the European Gaia space telescope

Shades of Hubble: The first data from Europe’s Gaia space telescope, launched to map a billion Milky Way stars, will be delayed 9 months while engineers grapple with several problems.

Gaia managers started taking test images early this year, but soon noticed three issues. For one, more light than anticipated is bending around the 10-metre sunshield and entering the telescope.

Small amounts of water trapped in the spacecraft before launch are being released now that the telescope is in the vacuum of space, and more ice than calculated is accumulating on the telescope’s mirrors. In addition, the telescope itself is expanding and contracting by a few dozen nanometres more than expected because of thermal variations.

Mission managers say the number of stars detected will remain the same even if these complications remain untreated, but the accuracy in measurements of the fainter stars will suffer.

Unlike Hubble, however, there is no way to send a shuttle and a team of astronauts to Gaia to fix it. And it sounds like these issues will have an impact on the telescope’s abilities to gather its intended data.

This story raises my hackles for another reason. Gaia was a very technically challenging space telescope to build, but it was far easier and less cutting edge than the James Webb Space Telescope. It also cost far less. What will happen when Webb gets launched later this decade? How likely is it to have similar issues? Based on a story I just completed for Sky & Telescope on the difficulties of building ground-based telescopes, I’d say Webb is very likely to have similar problems, with no way to fix them. The American astronomy community could then be faced with the loss of two decades of research because they had put all the eggs into Webb’s basket, and thus had no money to build anything else.

Detector Array Deterioration Poses New Problem for JWST

More problems for the James Webb Space Telescope: The detector arrays for several instruments are deteriorating, even as they sit on the shelf. And remember, the 2014 launch date is probably going to be delayed until 2016. Key quote:

“As you get further and further out with [the launch date], it really raises questions about how far down the [integration and test] process you go for the instruments … and how long you have to store all that before you actually launch,” [Webb program director Rick Howard] told the NASA Advisory Council’s astrophysics subcommittee during a Feb. 16 public meeting here. “And that just makes everybody even more nervous about this problem than anything else.”

More Webb budget troubles

According to its manager, the budget troubles of the James Webb Space Telescope will likely keep it on the ground until 2016.

This is terrible news for space-based astrophysics. Until Webb gets launched, NASA will have no money for any other space telescope project. And since all the space telescopes presently in orbit are not expected to be operating at the end of the decade, by 2020 the U.S. space astronomy program will essentially be dead.

Then again, there is the private sector, as Google Lunar X Prize is demonstrating.

1 3 4 5