Further SLS delays loom


Readers!
 
For many reasons, mostly political but partly ethical, I do not use Google, Facebook, Twitter. They practice corrupt business policies, while targeting conservative websites for censoring, facts repeatedly confirmed by news stories and by my sense that Facebook has taken action to prevent my readers from recommending Behind the Black to their friends.
 
Thus, I must have your direct support to keep this webpage alive. Not only does the money pay the bills, it gives me the freedom to speak honestly about science and culture, instead of being forced to write it as others demand.

 

Please consider donating by giving either a one-time contribution or a regular subscription, as outlined in the tip jar below.


 

Regular readers can support Behind The Black with a contribution via paypal:

Or with a subscription with regular donations from your Paypal or credit card account:


If Paypal doesn't work for you, you can support Behind The Black directly by sending your donation by check, payable to Robert Zimmerman, to
 
Behind The Black
c/o Robert Zimmerman
P.O.Box 1262
Cortaro, AZ 85652

 

You can also support me by buying one of my books, as noted in the boxes interspersed throughout the webpage. And if you buy the books through the ebookit links, I get a larger cut and I get it sooner.

A report by NASA’s inspector general finds that the planned first launch of the SLS rocket in November 2018 is threatened with delay because the ground facilities at Kennedy might not be ready.

In a report released Wednesday, NASA’s Office of Inspector General warned that Ground Systems Development and Operations, or GSDO, may be hard-pressed to have Kennedy Space Center’s launch facilities ready on time. Ground systems are a critical piece of the SLS-Orion infrastructure. All three elements are tightly integrated, with ground systems requiring significant input from the rocket and capsule designs. “GSDO cannot finalize and complete its requirements without substantial input for the other two programs,” said Jim Morrison, the assistant inspector general for audits. “And NASA is still finalizing the requirements for those programs.”

Gee, I guess SLS isn’t getting enough money, as its budget is only about $3 billion per year (about six times what the commercial space program gets per year, a program that has already created two freighter systems for ISS and is now creating two manned ferry systems for ISS). Why don’t we give them more, so that even more won’t be done with the money we spend?

Share

3 comments

  • Frank

    They could demote the manager like Russia does.

  • Tom Billings

    Promoting the manager, and others like him, is the whole idea in the first place, so that will never do. They will have to find a way to blame the construction at LS-13 for holding them up! That’s it!!

  • Tom Billings

    Sorry, …LC-13 is where the landing pads will be.