NASA has given SpaceX and Sierra Nevada six additional months, until March 2015, to complete their last contractual milestones for building their manned spacecraft.
An amendment signed by William Gerstenmaier, NASA’s associate administrator for human exploration and operations, on May 16 gives SpaceX until March 31, 2015, to complete the 14th and final milestone under its $440 million CCiCap agreement — a pad abort test of its Dragon capsule. The test originally was planned for April 2014.
On May 19, Gerstenmaier signed a similar amendment to Sierra Nevada’s $212.5 million CCiCap award to extend work associated with flight tests of the company’s Dream Chaser engineering test article until March 31, 2015.
NASA’s third Commercial Crew partner, Boeing, is on track to complete all its milestones, worth a combined $460 million, by the end of August,
The significance of this extension is that it reveals something about the dates for both SpaceX and Sierra Nevada’s next flight tests. The previously date for the pad abort test for Dragon had most recently been set for this summer. They are obviously not meeting that schedule and need more time. Sierra Nevada meanwhile wants to fly its Dream Chaser test vehicle some more, but apparently needs time to get it flight ready after it sustained damage during landing on its one and only flight test.
In addition, this extension suggests something about NASA’s assessment of the efforts of all three companies. The agency is supposed to down select to two companies by the end of the summer. The extension suggests that they are hoping to keep all three companies funded so that they all build their spacecraft.