NASA delays launch of its VIPER lunar rover to over concerns about commercial lander
VIPER’s planned route at the Moon’s south pole
In order to do more engineering tests of Astrobotic’s Griffin lunar lander, NASA has now delayed the launch of its VIPER lunar rover from November 2023 to November 2024.
NASA’s decision to pursue a 2024 delivery date results from the agency’s request to Astrobotic for additional ground testing of the company’s Griffin lunar lander, which will deliver VIPER to the lunar surface through CLPS. The additional tests aim to reduce the overall risk to VIPER’s delivery to the Moon. To complete the additional NASA-mandated tests of the Griffin lunar lander, an additional $67.8 million has been added to Astrobotic’s CLPS contract, which now totals $320.4 million.
Though the press release makes no mention of it, the launch of Astrobotic’s Griffin lander is partly dependent on the launch of Astrobotic’s first and smaller lunar lander, Peregrine, which was originally supposed to fly on the inaugural flight of ULA’s new Vulcan rocket, in 2021. That rocket’s first flight however has been delayed repeatedly because of delays by Blue Origin in completing development of the BE-4 rocket engine, to be used in Vulcan’s first stage. It is presently scheduled for early 2023, but that date remains tentative. This new delay of Griffin could be to make sure Peregrine flies first.
Regardless, this new budget increase means that the budget for Griffin has experienced a 62% cost overrun from its original $199 million number. This large increase in what is supposed to be a fixed price contract suggests that Astrobotic has been having some problems unstated by NASA, despite an inspector general report [pdf] that said all was going reasonably well.
VIPER’s planned route at the Moon’s south pole
In order to do more engineering tests of Astrobotic’s Griffin lunar lander, NASA has now delayed the launch of its VIPER lunar rover from November 2023 to November 2024.
NASA’s decision to pursue a 2024 delivery date results from the agency’s request to Astrobotic for additional ground testing of the company’s Griffin lunar lander, which will deliver VIPER to the lunar surface through CLPS. The additional tests aim to reduce the overall risk to VIPER’s delivery to the Moon. To complete the additional NASA-mandated tests of the Griffin lunar lander, an additional $67.8 million has been added to Astrobotic’s CLPS contract, which now totals $320.4 million.
Though the press release makes no mention of it, the launch of Astrobotic’s Griffin lander is partly dependent on the launch of Astrobotic’s first and smaller lunar lander, Peregrine, which was originally supposed to fly on the inaugural flight of ULA’s new Vulcan rocket, in 2021. That rocket’s first flight however has been delayed repeatedly because of delays by Blue Origin in completing development of the BE-4 rocket engine, to be used in Vulcan’s first stage. It is presently scheduled for early 2023, but that date remains tentative. This new delay of Griffin could be to make sure Peregrine flies first.
Regardless, this new budget increase means that the budget for Griffin has experienced a 62% cost overrun from its original $199 million number. This large increase in what is supposed to be a fixed price contract suggests that Astrobotic has been having some problems unstated by NASA, despite an inspector general report [pdf] that said all was going reasonably well.