NASA IG: NASA’s effort to build new SLS mobile launcher is an epic disaster
NASA’s bloated SLS mobile launchers
According to a new report [pdf] from NASA’s inspector general, both NASA and its contractor Bechtel have allowed the cost and schedule for the new larger SLS mobile launcher (ML-2) (on the right in the graphic) to go completely out of control, with the first launch on that platform to be delayed again until 2029.
NASA projects the ML-2 will cost over three times more than planned. In 2019, NASA estimated the entire ML-2 project from design through construction would cost under $500 million with construction completed and the ML-2 delivered to NASA by March 2023. In December 2023, NASA estimated the ML-2 project would cost $1.5 billion, including $1.3 billion for the Bechtel contract and $168 million for other project costs, with delivery of the launcher to NASA in November 2026. In June 2024, NASA established the Agency Baseline Commitment (ABC)—the cost and schedule baseline committed to Congress against which a project is measured—for a ML-2 project cost of $1.8 billion and a delivery date of September 2027. Even with the establishment of the ABC, NASA intends to keep Bechtel accountable to the cost and schedule agreed to in December 2023.
Despite the Agency’s increased cost projections, our analysis indicates costs could be even higher due in part to the significant amount of construction work that remains. Specifically, our projections indicate the total cost could reach $2.7 billion by the time Bechtel delivers the ML-2 to NASA. With the time NASA requires after delivery to prepare the launcher, we project the ML-2 will not be ready to support a launch until spring 2029, surpassing the planned September2028 Artemis IV launch date.
This quote actually makes things sounder better than they are. Bechtel’s original contract was for $383 million, which means the IG’s present final estimate of $2.7 billion is more than seven times higher. The contract was awarded in 2019 and was supposed to be completed by 2023, in four years. Instead, at best it will take Bechtel a decade to complete the job.
The IG notes that this contact was cost-plus, and considers this the main cause of these cost overruns. It also notes that NASA has had the option to convert the contract to fixed-price, but has chosen not to do so.
Possibly the most damning aspect of the IG report is its conclusion, which essentially admits that nothing can be done to fix this problem.
» Read more
NASA’s bloated SLS mobile launchers
According to a new report [pdf] from NASA’s inspector general, both NASA and its contractor Bechtel have allowed the cost and schedule for the new larger SLS mobile launcher (ML-2) (on the right in the graphic) to go completely out of control, with the first launch on that platform to be delayed again until 2029.
NASA projects the ML-2 will cost over three times more than planned. In 2019, NASA estimated the entire ML-2 project from design through construction would cost under $500 million with construction completed and the ML-2 delivered to NASA by March 2023. In December 2023, NASA estimated the ML-2 project would cost $1.5 billion, including $1.3 billion for the Bechtel contract and $168 million for other project costs, with delivery of the launcher to NASA in November 2026. In June 2024, NASA established the Agency Baseline Commitment (ABC)—the cost and schedule baseline committed to Congress against which a project is measured—for a ML-2 project cost of $1.8 billion and a delivery date of September 2027. Even with the establishment of the ABC, NASA intends to keep Bechtel accountable to the cost and schedule agreed to in December 2023.
Despite the Agency’s increased cost projections, our analysis indicates costs could be even higher due in part to the significant amount of construction work that remains. Specifically, our projections indicate the total cost could reach $2.7 billion by the time Bechtel delivers the ML-2 to NASA. With the time NASA requires after delivery to prepare the launcher, we project the ML-2 will not be ready to support a launch until spring 2029, surpassing the planned September2028 Artemis IV launch date.
This quote actually makes things sounder better than they are. Bechtel’s original contract was for $383 million, which means the IG’s present final estimate of $2.7 billion is more than seven times higher. The contract was awarded in 2019 and was supposed to be completed by 2023, in four years. Instead, at best it will take Bechtel a decade to complete the job.
The IG notes that this contact was cost-plus, and considers this the main cause of these cost overruns. It also notes that NASA has had the option to convert the contract to fixed-price, but has chosen not to do so.
Possibly the most damning aspect of the IG report is its conclusion, which essentially admits that nothing can be done to fix this problem.
» Read more