Tag Archives: ARM

Costs rise on Obama’s asteroid mission

The year delay in Obama’s as yet unfunded unmanned asteroid mission, a preliminary to a proposed manned asteroid mission, has caused its budget to grow from $1.25 billion to $1.4 billion.

More significantly,

NASA’s cost estimate for [the unmanned] ARRM excludes launch and operations. In a March 2016 report, the Government Accountability Office (GAO) review of NASA’s major programs showed a cost of $1.72 billion. Gates explained that the $1.72 billion includes the launch vehicle cost, set at approximately $500 million as a placeholder since NASA has not determined which of three launch vehicles will be used (Delta IV Heavy, Falcon Heavy, or the Space Launch System).

…The next administration will have to decide if the costs are worth the benefits. Although NASA has decided they are, the House Appropriations Committee disagrees. It denied funding for the program in its report on the FY2017 Commerce-Justice-Science (CJS) appropriations bill, which funds NASA. The bill has not passed the House yet, however, and there is no similar language in the Senate version, so NASA is not currently prohibited from spending money on the project.

So far, NASA has been funding this Obama project by stealing money from other projects in NASA, since Congress has consistently refused to appropriate extra money for it. This approach has worked up until now, as they are only funding initial design work. Where they think they will get the money for a full mission however remains a complete mystery to me.

NASA delays asteroid redirect mission one year

NASA has decided to delay by one year the planned launch dates for both its unmanned and manned missions to an asteroid.

And why might you ask?

Mr. Gerstenmaier further stated that “We had trouble getting the funding together for this thing. So this slip of the one year that you see wasn’t caused by technical. It was really caused by budget availability. We just didn’t have the budget available to go do this.”

Also, the article notes that the launch rocket for the unmanned mission, now set for 2021, will be one of three possible rockets.

No elaboration was given as to what those “three rockets” are, though SLS, one of SpaceX’s Falcon family of rockets, and Atlas V are understood to be the prime contenders at this time.

The unmanned mission might happen (though I wouldn’t bet on it). As for the manned mission, there is a reason NASA has had trouble getting funding. SLS/Orion cost too much. Congress simply doesn’t want to spend that much for the actual missions. They will dole out a lot of cash for development (and the pork that goes with it), but even they can’t afford the gigantic budgets NASA needs to actually fly real missions.