NASA delays launch of its VIPER lunar rover to over concerns about commercial lander
VIPER’s planned route at the Moon’s south pole
In order to do more engineering tests of Astrobotic’s Griffin lunar lander, NASA has now delayed the launch of its VIPER lunar rover from November 2023 to November 2024.
NASA’s decision to pursue a 2024 delivery date results from the agency’s request to Astrobotic for additional ground testing of the company’s Griffin lunar lander, which will deliver VIPER to the lunar surface through CLPS. The additional tests aim to reduce the overall risk to VIPER’s delivery to the Moon. To complete the additional NASA-mandated tests of the Griffin lunar lander, an additional $67.8 million has been added to Astrobotic’s CLPS contract, which now totals $320.4 million.
Though the press release makes no mention of it, the launch of Astrobotic’s Griffin lander is partly dependent on the launch of Astrobotic’s first and smaller lunar lander, Peregrine, which was originally supposed to fly on the inaugural flight of ULA’s new Vulcan rocket, in 2021. That rocket’s first flight however has been delayed repeatedly because of delays by Blue Origin in completing development of the BE-4 rocket engine, to be used in Vulcan’s first stage. It is presently scheduled for early 2023, but that date remains tentative. This new delay of Griffin could be to make sure Peregrine flies first.
Regardless, this new budget increase means that the budget for Griffin has experienced a 62% cost overrun from its original $199 million number. This large increase in what is supposed to be a fixed price contract suggests that Astrobotic has been having some problems unstated by NASA, despite an inspector general report [pdf] that said all was going reasonably well.
The support of my readers through the years has given me the freedom and ability to analyze objectively the ongoing renaissance in space, as well as the cultural changes -- for good or ill -- that are happening across America. Four years ago, just before the 2020 election I wrote that Joe Biden's mental health was suspect. Only in this year has the propaganda mainstream media decided to recognize that basic fact.
Fourteen years ago I wrote that SLS and Orion were a bad ideas, a waste of money, would be years behind schedule, and better replaced by commercial private enterprise. Even today NASA and Congress refuse to recognize this reality.
In 2020 when the world panicked over COVID I wrote that the panic was unnecessary, that the virus was apparently simply a variation of the flu, that masks were not simply pointless but if worn incorrectly were a health threat, that the lockdowns were a disaster and did nothing to stop the spread of COVID. Only in the past year have some of our so-called experts in the health field have begun to recognize these facts.
Your help allows me to do this kind of intelligent analysis. I take no advertising or sponsors, so my reporting isn't influenced by donations by established space or drug companies. Instead, I rely entirely on donations and subscriptions from my readers, which gives me the freedom to write what I think, unencumbered by outside influences.
Please consider supporting my work here at Behind the Black.
You can support me either by giving a one-time contribution or a regular subscription. There are five ways of doing so:
1. Zelle: This is the only internet method that charges no fees. All you have to do is use the Zelle link at your internet bank and give my name and email address (zimmerman at nasw dot org). What you donate is what I get.
2. Patreon: Go to my website there and pick one of five monthly subscription amounts, or by making a one-time donation.
3. A Paypal Donation:
5. Donate by check, payable to Robert Zimmerman and mailed to
Behind The Black
c/o Robert Zimmerman
P.O.Box 1262
Cortaro, AZ 85652
You can also support me by buying one of my books, as noted in the boxes interspersed throughout the webpage or shown in the menu above. And if you buy the books through the ebookit links, I get a larger cut and I get it sooner.
VIPER’s planned route at the Moon’s south pole
In order to do more engineering tests of Astrobotic’s Griffin lunar lander, NASA has now delayed the launch of its VIPER lunar rover from November 2023 to November 2024.
NASA’s decision to pursue a 2024 delivery date results from the agency’s request to Astrobotic for additional ground testing of the company’s Griffin lunar lander, which will deliver VIPER to the lunar surface through CLPS. The additional tests aim to reduce the overall risk to VIPER’s delivery to the Moon. To complete the additional NASA-mandated tests of the Griffin lunar lander, an additional $67.8 million has been added to Astrobotic’s CLPS contract, which now totals $320.4 million.
Though the press release makes no mention of it, the launch of Astrobotic’s Griffin lander is partly dependent on the launch of Astrobotic’s first and smaller lunar lander, Peregrine, which was originally supposed to fly on the inaugural flight of ULA’s new Vulcan rocket, in 2021. That rocket’s first flight however has been delayed repeatedly because of delays by Blue Origin in completing development of the BE-4 rocket engine, to be used in Vulcan’s first stage. It is presently scheduled for early 2023, but that date remains tentative. This new delay of Griffin could be to make sure Peregrine flies first.
Regardless, this new budget increase means that the budget for Griffin has experienced a 62% cost overrun from its original $199 million number. This large increase in what is supposed to be a fixed price contract suggests that Astrobotic has been having some problems unstated by NASA, despite an inspector general report [pdf] that said all was going reasonably well.
The support of my readers through the years has given me the freedom and ability to analyze objectively the ongoing renaissance in space, as well as the cultural changes -- for good or ill -- that are happening across America. Four years ago, just before the 2020 election I wrote that Joe Biden's mental health was suspect. Only in this year has the propaganda mainstream media decided to recognize that basic fact.
Fourteen years ago I wrote that SLS and Orion were a bad ideas, a waste of money, would be years behind schedule, and better replaced by commercial private enterprise. Even today NASA and Congress refuse to recognize this reality.
In 2020 when the world panicked over COVID I wrote that the panic was unnecessary, that the virus was apparently simply a variation of the flu, that masks were not simply pointless but if worn incorrectly were a health threat, that the lockdowns were a disaster and did nothing to stop the spread of COVID. Only in the past year have some of our so-called experts in the health field have begun to recognize these facts.
Your help allows me to do this kind of intelligent analysis. I take no advertising or sponsors, so my reporting isn't influenced by donations by established space or drug companies. Instead, I rely entirely on donations and subscriptions from my readers, which gives me the freedom to write what I think, unencumbered by outside influences.
Please consider supporting my work here at Behind the Black.
You can support me either by giving a one-time contribution or a regular subscription. There are five ways of doing so:
1. Zelle: This is the only internet method that charges no fees. All you have to do is use the Zelle link at your internet bank and give my name and email address (zimmerman at nasw dot org). What you donate is what I get.
2. Patreon: Go to my website there and pick one of five monthly subscription amounts, or by making a one-time donation.
3. A Paypal Donation:
5. Donate by check, payable to Robert Zimmerman and mailed to
Behind The Black
c/o Robert Zimmerman
P.O.Box 1262
Cortaro, AZ 85652
You can also support me by buying one of my books, as noted in the boxes interspersed throughout the webpage or shown in the menu above. And if you buy the books through the ebookit links, I get a larger cut and I get it sooner.
“Arianespace’s new Vulcan rocket”?
I think there’s some mix up here.
V-Man: Oy. My brain was not thinking. Fixed.
$68M & a year just to test the landing system?
That sounds like a lot more than just the landing system needs work.
This could be a problem of scope creep. It is one thing to say ‘we believe we are ready” but if the customer (NASA) doesn’t think so, then someone has to pay for the new testing. It can be quite aggravating when you think you have all of the requirements met only to find there are newer and more detailed requirements.
Not that I have experience in this area or anything…
Small liquids can get out from under you right quick. The hover tests of Kinetic Kill Vehicle prototypes over nets-how steady they were-still are more impressive than hoverslams. I wonder if Clementine turned some of that over to JPL to keep tribal knowledge intact alive through anti-SLI democrat administrations. Exchange students Minoxed the blueprints to China even before Loral. Thus a push for more in-house work and a fear of start-ups you don’t know from Adam. This explains skycrane and Chinese lander skills as SDI based. China’s solids trail-because we kept better tabs on solid receipes, as it were.