To read this post please scroll down.

 

The November 2026 fund-raising campaign!

 

We are now beginning the second week of this year's holiday season fund-raising campaign. The first week was good. Thanks to all who donated!

 

In recent campaigns donations in the second week routinely fall off. I beg those who are regular readers who have not donated or subscribed previously to finally do so. I can't keep writing this webpage every day if my readers won't support my work, and based on the numbers so far this year, it is getting harder and harder for me to consider continuing.

 

As I have noted repeatedly, my analysis of the space business and the exploration of the solar system is original, unique, and frequently years ahead of everyone else. I correctly predicted as early as 1998 that private enterprise and freedom would conquer the solar system, not government. My 2017 policy paper, Capitalism in Space, certainly helped make that happen.

 

In fact, I'm not the only one who thinks so. Behind the Black is now ranked by Feedspot as 14th among best Space Blogs to follow in 2026.

 

So please consider donating or subscribing to Behind the Black, either by giving a one-time contribution or a regular subscription. I could really use the support at this time. There are five ways of doing so:

 

1. Zelle: This is the only internet method that charges no fees. What you donate is what I get. At your bank's Zelle page you will need to give my name and email address. Click the button below to verify and copy that information.

Click below to verify and copy the Zelle recipient email. The email will not be displayed on this page.

 

2. Patreon: Go to my website there and pick one of five monthly subscription amounts, or by making a one-time donation. Takes about a 10% cut.

 

3. A Paypal Donation or subscription, which takes about a 15% cut:

 

4. Donate by check. I get whatever you donate. Make the check payable to Robert Zimmerman and mail it to

Behind The Black
c/o Robert Zimmerman
P.O.Box 1262
Cortaro, AZ 85652

 

You can also support me by buying one of my books, as noted in the boxes interspersed throughout the webpage or shown in the menu above.


NASA reconsiders cancellation of overbudget and behind schedule robotic refueling mission

Due to some pressure from Congress (which wants the 450 jobs the project employs), NASA is now reconsidering its cancellation of the On-Orbit Servicing, Assembly and Manufacturing (OSAM) 1 mission, designed in the late 2000s to demonstrate the robotic refueling of a dead satellite but is so overbudget and behind schedule that in the interim private enterprise accomplished the same goal now repeatedly for a fraction of the cost.

Language in the final fiscal year 2024 appropriations bill, released just days after NASA’s cancelation announcement, which fully funded OSAM-1 at $227 million, directed NASA to adjust the mission to launch in 2026 within the spending profile NASA included in its 2024 budget request. That could be done, the report accompanying the bill suggested, through “potential de-scoping of some non-essential capabilities,” adding that if it is not possible, NASA should conduct another continuation review in September.

In other words, Congress wants NASA to keep this project, even if it means cutting the budget of other more useful and valuable missions.

OSAM has cost a billion dollars so far, and after almost fifteen years has not yet flown. Meanwhile, Northrop Grumman’s MEV servicing robot has already provided fuel to several dead satellites, while orbital tug startups are flying missions and developing the same refueling capabilities for far less. The industry doesn’t need this demonstration mission anymore. It has already demonstrated it, and done so better.

Moreover, why the heck does OSAM require 450 people? That number is absurd, and likely exceeds the payrolls of all the orbital tug companies plus Northrop’s robotic servicing division combined.

There is hope for the American taxpayer. The legislative recommendations above come solely from the Senate. The House appears less interested in spending this money. And NASA has not yet decided what it will do.

Genesis cover

On Christmas Eve 1968 three Americans became the first humans to visit another world. What they did to celebrate was unexpected and profound, and will be remembered throughout all human history. Genesis: the Story of Apollo 8, Robert Zimmerman's classic history of humanity's first journey to another world, tells that story, and it is now available as both an ebook and an audiobook, both with a foreword by Valerie Anders and a new introduction by Robert Zimmerman.

The print edition can be purchased at Amazon or from any other book seller. If you want an autographed copy the price is $60 for the hardback and $45 for the paperback, plus $8 shipping for each. Go here for purchasing details. The ebook is available everywhere for $5.99 (before discount) at amazon, or direct from my ebook publisher, ebookit. If you buy it from ebookit you don't support the big tech companies and the author gets a bigger cut much sooner.


The audiobook is also available at all these vendors, and is also free with a 30-day trial membership to Audible.
 

"Not simply about one mission, [Genesis] is also the history of America's quest for the moon... Zimmerman has done a masterful job of tying disparate events together into a solid account of one of America's greatest human triumphs."--San Antonio Express-News

1 comment

One comment

Leave a Reply

Your email address will not be published. Required fields are marked *

Readers: the rules for commenting!

No registration is required. I welcome all opinions, even those that strongly criticize my commentary.

However, name-calling and obscenities will not be tolerated. First time offenders who are new to the site will be warned. Second time offenders or first time offenders who have been here awhile will be suspended for a week. After that, I will ban you. Period.

Note also that first time commenters as well as any comment with more than one link will be placed in moderation for my approval. Be patient, I will get to it.

Formatting buttons insert safe HTML. Links and comments with more than one link will still be moderated.