Blue Origin BE-4 engine delayed again
In an interview ULA’s CEO Tory Bruno revealed that Blue Origin is not going to deliver the first two flightworthy BE-4 engines this summer, as promised, with delivery now probably not until the end of the year.
“I will not get them before the end of the year,” said Tory Bruno, CEO of ULA, in an exclusive Denver Business Journal interview ahead of this week’s Space Symposium industry gathering in Colorado Springs. “It will be shortly into the beginning of the 2022 calendar year, and anywhere in there will support me being able to build up a rocket and have that Vulcan waiting on my customer, Astrobotic.”
…“We’ve actually be been able to accommodate this, but I’ll be straight with you, the dates we’ve set up for them now— we really don’t have the ability to make any big moves after this,” Bruno said. “I need them to diligently work through the plans we have and get done on time.”
ULA needs to launch its new Vulcan rocket twice in order to get approved for its first military launch, now expected in less than 12 months. They thus no longer have any schedule margin.
In an interview ULA’s CEO Tory Bruno revealed that Blue Origin is not going to deliver the first two flightworthy BE-4 engines this summer, as promised, with delivery now probably not until the end of the year.
“I will not get them before the end of the year,” said Tory Bruno, CEO of ULA, in an exclusive Denver Business Journal interview ahead of this week’s Space Symposium industry gathering in Colorado Springs. “It will be shortly into the beginning of the 2022 calendar year, and anywhere in there will support me being able to build up a rocket and have that Vulcan waiting on my customer, Astrobotic.”
…“We’ve actually be been able to accommodate this, but I’ll be straight with you, the dates we’ve set up for them now— we really don’t have the ability to make any big moves after this,” Bruno said. “I need them to diligently work through the plans we have and get done on time.”
ULA needs to launch its new Vulcan rocket twice in order to get approved for its first military launch, now expected in less than 12 months. They thus no longer have any schedule margin.