No more manned Soyuz purchased by NASA after 2019

The competition heats up: Both Boeing and SpaceX better get their manned capsules working by 2019, because NASA at this point has no plans to buy more seats on Russian Soyuz capsules after the present contract runs out.

Even as the commercial crew schedules move later into 2018, NASA officials say they are not considering extending the contract with Roscosmos โ€” the Russian space agency โ€” for more launches in 2019. The last Soyuz launch seats reserved for U.S. astronauts are at the end of 2018.

It takes more than two years to procure components and assemble new Soyuz capsules, so Russia needed to receive new Soyuz orders from NASA by some time this fall to ensure the spacecraft would be ready for liftoff in early 2019.

The second paragraph above notes that even if NASA decided it needed more Soyuz launches, it is probably too late to buy them and have them available by 2019.

3 comments

Boeing pushes back first Starliner flights

Boeing has delayed the first test flight of its Starliner manned capsule from the end of 2017 until June 2018.

Boeing says that production delays and problems with qualification tests are partly to blame for the timeline slip. The company also found a production flaw in September that forced them to get rid of a main element on one of their spacecrafts โ€” a dome that made up the pressure shell of the crew module. All of these complications combined prompted Boeing to push back the development timeline of Starliner by about six months.

0 comments

Budget constraints and technical challenges delay commercial crew

A NASA inspector general report released today cites both budget constraints imposed by Congress as well as technical challenges that will delay the first commercial manned mission to ISS until 2018.

When the commercial crew program began, NASA hoped to have routine flights by 2015, but that slipped in large part due to congressional underfunding in the early years. OIG noted today that its 2013 report found that adequate funding was the major challenge for the program. Congress has warmed up to the program, however, and now is approving the full President’s request so funding is not the issue it once was. Technical challenges now are the major hurdle according to today’s report.

The companies’ systems must be certified by NASA before beginning routine flights to ISS. Boeing anticipates receiving certification in January 2018 with its first certified flight in spring 2018, and SpaceX is working toward late 2017 for its first certified mission, the OIG report says. But it is skeptical: “Notwithstanding the contractors’ optimism, based on the information we gathered during our audit, we believe it unlikely that either Boeing or SpaceX will achieve certified, crewed flight to the ISS until late 2018.”

The report has been written prior to yesterday’s Falcon 9 launchpad failure, which will certainly impact the schedule negatively.

Essentially, the report claims that the program was delayed initially by about two to three years because of the refusal of Congress to fund it fully. The delays to come will be instead because of the technical challenges. While I tend to agree with this assessment, I also note that government reports like this are often designed to generate more funds for the agencies involved, not find a better way to do things. If we are not diligent and hard-nosed about how we fund this program I worry that with time commercial crew will become corrupted by the government’s sloppy and inefficient way of doing things, and become as bloated as Orion and SLS. This is one of the reasons I never complained when Congress short funded the program previously, as it forced the companies involved to keep their costs down.

0 comments

Starliner and Orion drop tests

The competition heats up: NASA and Boeing have begun drop tests on land and water respectively of their Orion and Starliner manned capsules.

Both sets of tests are taking place at Langley. With Orion they are dropping the mockup in water to test how it will respond to a variety of circumstances. With Starliner they have finished the water drop tests and have begun drop tests on land.

7 comments

Design problems for Starliner

In the heat of competition: Boeing is working to correct two serious design problems that cropped up during the construction of its Starliner manned capsule.

First the thing was weighing too much:

One issue involved the mass of the crew capsule, which outgrew the lift capability of the United Launch Alliance Atlas 5 rocket selected to put it into orbit. The CST-100 Starliner will ride an Atlas 5 rocket with two solid rocket boosters and a dual-engine Centaur upper stage, and although Boeing and ULA engineers considered adding a third strap-on motor to compensate for the capsuleโ€™s extra weight, managers now have the spacecraft back under its mass allowance, Ferguson said.

Second, the capsule has a shape problem:

Ferguson said Boeing has a model of the Atlas 5 rocket and CST-100 Starliner in a wind tunnel to verify a change to capsuleโ€™s outer shape devised to overcome higher-than-expected aerodynamic launch loads discovered in testing. โ€œThey had one issue, a non-linear aerodynamic loads issue, where they were getting some high acoustic loads right behind the spacecraft,โ€ said Phil McAlister, head of NASAโ€™s commercial spaceflight development office in Washington.

Something here is rotten. It seems to me that Boeing shouldn’t be having these very basic problems right off the bat. In the past, under the older cost-plus contracts NASA used to routinely hand out, these kinds of problems would simply have meant that Boeing would have gotten more money from NASA, This time, however the contract is fixed-price. If Boeing has problems or delays, the company will have to bear the cost, not NASA. I suspect these problems might have occurred because of some cultural laziness at Boeing. Their management is used to not having to eat the cost of these kinds of mistakes. Now, they will. I expect the culture to therefore begin changing.

5 comments

Russia negotiating with Australian investors to buy SeaLaunch

The competition heats up: Roscosmos revealed today that Russia is negotiating with investors in Australia to buy SeaLaunch.

I’m not sure how seriously we can take this announcement. The sale still has a lot of problems for any investors. Boeing is owed a lot of money by the SeaLaunch partners, specifically Russia, and the SeaLaunch floating launchpad is docked in the U.S. where they can hold it as collateral

0 comments

Boeing begins assembling second Starliner manned capsule

The competition heats up: With the arrival of the major capsule components to Boeing’s Florida facility the company has begun assembly of its second Starliner manned capsule.

Following closely behind the joining of the two major hull components for the Structural Test Article (STA) of the CST-100 Starliner, Boeing and NASA are marking the arrival of the upper dome, one half of the Starliner pressure vessel, for the second Starliner module. The three components will undergo separate outfitting operations in the Commercial Crew and Cargo Processing Facility (C3PF) where wiring lines, avionics and other systems will be installed and tested before the pieces are connected to form a complete Starliner.

This second Starliner module is known to Boeing as Spacecraft 1. Once completed inside C3PF, Starliner Spacecraft 1 will be outfitted with electrical and fluid systems before engineers will attach the outer thermal protection shielding and the base heat shield that will eventually protect crewmembers during re-entry. Starliner Spacecraft 1 will be used in the pad abort test to validate that the launch abort system will be able to lift astronauts away from danger in the event of an emergency during launch.

The article provides good detail about the upcoming Starliner test schedule.

0 comments

First manned Starliner flight delayed

Boeing has revealed that the first manned flight of Starliner will be delayed until 2018.

This delay for Boeing is not really a surprise. Unlike SpaceX, the company had done very little actual development work on the capsule before winning its contract from NASA. They therefore have a lot more to do to become flight worthy. My one worry is their contract. If the contract is fixed price, as with the original cargo contracts awarded SpaceX and Orbital ATK, Boeing will have no incentive to delay, as they won’t be paid anything until they achieve specific milestones and will get no additional monies to cover the added costs of the delay. If the contract is cost-plus, however, NASA’s traditional contract system used for SLS, Orion, and almost every other boondoggle since the 1960s, then Boeing will be paid regardless of the delay, and NASA will also be on the hook for paying the additional delay costs, thus giving Boeing an incentive to slow walk the construction.

I think the contract was fixed-price, but am not sure. Anyone out there have an answer?