SLS schedule changes impending

NASA’s refurbishment plans for the mobile launcher and SLS launchpad suggest that the first manned flight of SLS is increasingly likely to be delayed from its present 2021 launch date.

The situation is complicated. The SLS configuration that will launch an unmanned capsule in December 2018 will use a Delta rocket upper stage, and will only have the capability of launching about 70 metric tons into low Earth orbit. After this one flight NASA wants to begin using SLS’s own upper stage, which it calls the Exploration Upper Stage and which will raise the rocket’s payload capacity to 105 metric tons. Because these changes will make SLS taller, however, they have to refurbish both the mobile launcher that brings the rocket to the launchpad as well as the launch tower used to fuel the rocket during countdown. These changes, now scheduled, will shut down the launchpad from January 2019 until the end of 2020.

The problem with doing this is that SLS’s second flight, presently scheduled in 2021, is supposed to be manned. To use the Exploration Upper Stage untested on this manned flight is something NASA doesn’t really want to do. Flying another unmanned flight to test that upper stage however will require NASA to delay the first manned flight again, probably to 2023.

Based on the article at the link above, those delays now seem almost certain. Because NASA is moving to refurbish the launchpad right after that first unmanned flight in December 2018, this means all later SLS launches will use the Exploration Upper Stage. Since Congress has also ordered NASA to fly its upcoming Europa orbiter mission on SLS, it seems to me that NASA is now quietly moving to add a second unmanned SLS test flight between the rocket’s first flight in 2018 and the first manned flight and will use it to launch the Europa orbiter some time in 2021. This will in turn delay the launch of that first manned flight, probably until 2023, a date that is presently listed in many NASA documents as the latest SLS’s first manned mission will fly.

If this is the case, it means that it will have literally taken NASA two decades to build and fly a single manned Orion capsule, beginning when George Bush ordered the construction of the Crew Exploration Vehicle in January 2004.

Does no one but me see something wrong here?

5 comments

Orion faces more budget and schedule delays

A new inspector general report of NASA’s Orion has found that the program still faces significant budget and technical problems in meeting the planned August 2021 launch date for its first manned mission.

The report makes it clear that this launch will almost certainly be delayed until 2023, meaning that from the date President George Bush proposed Orion in 2004, it will have taken NASA a full two decades to launch the first manned Orion capsule.

Let me repeat that: Two decades to build and launch a single manned mission. Does anyone see something wrong here?

As for what will happen after that first flight, the report itself [pdf] makes it pretty clear that not much is likely. From page 11:

For Orion missions after 2023, NASA has adopted an incremental development approach. According to the Program Plan, the approach is cost-driven and will provide a core vehicle the Agency can upgrade to provide additional capabilities for missions beyond cis-lunar space. Each incremental upgrade will build on flight experience to ensure the vehicle’s design is based on viable technology and capabilities. Consistent with this incremental approach, NASA has not committed to specific missions after 2023 and therefore has not developed detailed plans, requirements, or costs for such missions. According to NASA officials, the Agency will instead focus on building capabilities through defined roadmaps that identify technology development paths and capability requirements for deep space exploration missions. Officials explained the Agency will fund basic research, pursue development of the technologies that appear most viable, and build capabilities based on available funding. Missions will be selected based on the progress and maturity of the developed technology.

A translation of this gobbly-gook into plain English can be summed up as follows: Congress has given us no money for future missions, so we can’t plan anything.

Considering the cost and the ungodly amount of time it took NASA to get to this one flight, and considering how badly this record compares with the numerous flights that private commercial space will achieve prior to this single flight, don’t expect Congress to fork up more money after 2023. SLS and Orion are going to die. Unfortunately, their slow death will have cost the American taxpayer billions of wasted dollars that NASA could have been better spent on other things.

3 comments

Starliner and Orion drop tests

The competition heats up: NASA and Boeing have begun drop tests on land and water respectively of their Orion and Starliner manned capsules.

Both sets of tests are taking place at Langley. With Orion they are dropping the mockup in water to test how it will respond to a variety of circumstances. With Starliner they have finished the water drop tests and have begun drop tests on land.

7 comments

The status of SLS for its first launch in 2018

Link here. The article gives an excellent and detailed overview of where construction of SLS presently sits, what the problems are that still remain, and what they have done to overcome them.

What struck me most however in reading the article was how long it takes them to do anything. For example, it appears they will assemble the rocket in the spring of 2018 for a December launch. In fact, the description of this assembly in this article partly explains to me why SLS will have the ungodly slow launch rate of at best once every two years.

In addition, the article describes how NASA has handled a number of engineering issues that have come up, and for each the approach seems to me to be more complicated than necessary. However, I am not an engineer and have never been part of this kind of work. Maybe everyone does it this way.

12 comments

NASA finalizes more cubesat deals for first SLS launch

Lockheed Martin and NASA have signed a deal to put a science cubesat on the first SLS rocket, planned for an unmanned launch of Orion in 2018.

The adapter ring that connects Orion to the rocket will include 13 bays for CubeSats, shoe-box sized payloads that until now haven’t been delivered in significant numbers into deep space. Each of those payload operators is working to finalize contracts with NASA for the ride into space, and on Monday, Lockheed Martin announced a few details of its 6U CubeSat, called SkyFire. Lockheed’s payload will capture high-quality images of the Moon. And in exchange for the ride into deep space, NASA will receive data from the mission.

“The CubeSat will look for specific lunar characteristics like solar illumination areas,” James Russell, Lockheed Martin SkyFire principal investigator, said in a news release. “We’ll be able to see new things with sensors that are less costly to make and send to space.”

This is without doubt a great opportunity for Lockheed Martin and others to test the use of a cubesat in interplanetary space. Whether it makes sense to use SLS to launch them is another matter entirely.

0 comments

NASA delays asteroid redirect mission one year

NASA has decided to delay by one year the planned launch dates for both its unmanned and manned missions to an asteroid.

And why might you ask?

Mr. Gerstenmaier further stated that “We had trouble getting the funding together for this thing. So this slip of the one year that you see wasn’t caused by technical. It was really caused by budget availability. We just didn’t have the budget available to go do this.”

Also, the article notes that the launch rocket for the unmanned mission, now set for 2021, will be one of three possible rockets.

No elaboration was given as to what those “three rockets” are, though SLS, one of SpaceX’s Falcon family of rockets, and Atlas V are understood to be the prime contenders at this time.

The unmanned mission might happen (though I wouldn’t bet on it). As for the manned mission, there is a reason NASA has had trouble getting funding. SLS/Orion cost too much. Congress simply doesn’t want to spend that much for the actual missions. They will dole out a lot of cash for development (and the pork that goes with it), but even they can’t afford the gigantic budgets NASA needs to actually fly real missions.

3 comments

GAO warns of more cost overruns for SLS/Orion

The Government Accountability Office today issued two reports, both of which said that the SLS and Orion programs are faced with more cost overruns and schedule delays.

The GAO found that cost overruns for Orion could be as high as $707 million and that work is “not being accomplished as scheduled.” It also found challenges with the capsule’s software and heat shield, and said that the space capsule’s cost and schedule “estimates are not reliable.”

Other than that, everything is peachy keen! These reports, (the Orion report is found here [pdf] and the SLS report here [pdf], especially the Orion one, also suggest that the first manned Orion mission, now scheduled for 2021, stands a good chance of being delayed again, possibly for two more years.

This just confirms what I have written in my soon-to-be published policy paper, Exploring Space in the 21st Century. In fact, I need to add these GAO reports to my sources!

1 comment

The Lie that is Orion

Several weeks ago NASA put out one of its periodic press releases touting the wonders of the engineering the agency is doing to prepare for its future missions to Mars. In this case the press release described a new exercise device, dubbed ROCKY (for Resistive Overload Combined with Kinetic Yo-Yo), for use in the Orion capsule.

“ROCKY is an ultra-compact, lightweight exercise device that meets the exercise and medical requirements that we have for Orion missions,” said Gail Perusek, deputy project manager for NASA’s Human Research Program’s Exploration Exercise Equipment project. “The International Space Station’s exercise devices are effective but are too big for Orion, so we had to find a way to make exercising in Orion feasible.

As is their habit these days in their effort to drum up support for funding for SLS and Orion, the press release was filled with phrases and statements that implied or claimed that Orion was going to be the spacecraft that Americans will use to explore the solar system.

…engineers across NASA and industry are working to build the Orion spacecraft and Space Launch System rocket that will venture to deep space for the first time together…

…Over the next several years, NASA’s Human Research Program will be refining the device to optimize it not only for near-term Orion missions with crew, but for potential uses on future long-duration missions in Orion…

These are only two examples. I have clipped them because both were very carefully phrased to allow NASA deniablity should anyone question these claims. For example, in the first quote they qualify “deep space” as specifically the 2018 unmanned lunar test flight. And the second quote is qualified as referring to missions to lunar space. Nonetheless, the implied intent of this wording is to sell Orion as America’s interplanetary spaceship, destined to take us to the stars!

Don’t believe me? Then take a look at NASA’s own Orion webpages, starting with the very first words on their Orion Overivew page.
» Read more

11 comments

A description of SLS’s first launch

This article provides a detailed look at the planned 2018 first launch of SLS, describing step-by-step the launch process that will send an unmanned Orion capsule toward the Moon.

As my readers know, I am not a fan of SLS. I consider it an incredible waste of money that will never accomplish anything. Nonetheless, that first launch will be a cool thing to watch, as the rocket will generate comparable energy as the Saturn 5.

6 comments

Europe announces a three month delay for Orion service module

Be still my heart: Delivery of the service module for NASA’s Orion capsule, being built by the European Space Agency, will be three months late due to engineering modifications.

Nico Dettman, head of ESA’s space transportation department, said the delay is partly a result of the fact that several components could not yet be assessed in the full critical design review and need more time to be integrated into the design. Dettman said another issue forcing the delay resulted from a reassessment by NASA of the stresses the service module needs to be capable of handling in orbit. These “in-orbit load” specifications have recently been tightened. But any design modifications will not affect the service module’s core structure, he said. “If it has an impact, it will be limited to the solar array wings, not the structure – nothing where flight hardware has been manufactured that we will have to touch,” Dettman said. “It’s a late modification, but not too late.”

Note that George Bush proposed Orion in January 2004. The first full up test flight, unmanned, is now scheduled for 2018. Thus, they only had 14 years to build this single capsule and service module.

It took NASA less than five years to build the first Apollo capsule and service module, and less than 8 years to fly seven to the Moon. Damn, it took the Allies less than four years to defeat Germany and Japan in World War II. Yet somehow the big government space programs of NASA and ESA can’t build a single manned capsule in less than 14 years.

Doesn’t anyone but me see something wrong with this picture?

7 comments

Airbus begins assembly Orion service module

My heart be still! Airbus has announced that it is beginning assembly of the first Orion capsule service module.

Considering the cost to build about three Orion flight capsules, about $25 billion, one would think that would be enough to also build the capsule’s service module, especially since this is not cutting edge technology, having already been done with Apollo.

Not however when you are dealing with pork-laden government operations, where the customer, the taxpayer, is a good mark that you can suck for as much money as possible without any bad consequences. Make it sound cool and they will buy it, hook, line, and sinker!