The first and second launch of the Space Launch System are likely to be delayed due to budget issues.

The first and second launch of the Space Launch System are likely to be delayed due to budget issues.

“It’s very clear that we could have slips of a year or two,” said [deputy administrator Lori] Garver, referring to both the 2017 launch โ€” which won’t have a crew โ€” and the first planned flight of NASA astronauts aboard the SLS rocket in 2021.

Garver claims that it is insufficient funds for SLS that will cause the delays, despite getting $3 billion per year, or ten times the money the private commercial program is getting.

I’m on a hike today, but so any additional comments about this insanity will have to wait.

5 comments

The Russians are including a bathroom in their next generation manned vehicle, something they note Orion will not have.

The competition heats up: The Russians are including a bathroom in their next generation manned vehicle, something they note Orion will not have.

A new Russian spaceship for trips to the moon or the International Space Station will have at least one crucial advantage over its American rival โ€“ a toilet, one of the craftโ€™s developers said Friday. โ€œI donโ€™t think I need to elaborate on how a waste-collection system is much more comfortable than the diapers that astronauts aboard the [US spacecraft] Orion will have to use,โ€ said Vladimir Pirozhkov of the Moscow Institute of Steel and Alloys, which is involved in the development of the Russian ship. โ€œBesides, the Russian segment of the International Space Station [ISS] has a limited number of toilets, which means a spacecraft with an extra โ€˜space toiletโ€™ will come in handy,โ€ he added.

As much as I am skeptical of Orion and SLS, I am equally skeptical of the Russian claims of a next generation manned spacecraft. They have been unveiling these proposals now for more than a decade, with nothing ever getting built. With Orion we at least have an existing capsule, even if its bulkhead needed to fixed.

Though I will agree with them on one point: Putting a toilet on a vehicle intended to go beyond Earth orbit, which Orion is supposed to be designed to do, makes common sense. That NASA didn’t include this essential item in Orion reveals to us the unseriousness of the spacecraft.

12 comments

While the launch industry eagerly awaits SpaceX’s first commercial Falcon 9 launch on September 10, Arianespace has been signing up customers.

The competition heats up: While the launch industry eagerly awaits SpaceX’s first commercial Falcon 9 launch on September 10, Arianespace has been signing up customers.

Arianespace Chief Executive Stephane Israel said Aug. 29 after the last Ariane 5 launch that the company has booked around 300 million euros ($400 million) in new orders in recent weeks, bringing this yearโ€™s total contract volume to 1 billion euros. Industry officials said the contracts are for government missions in Brazil and Japan, and commercial operators in Brazil, the United States, Mexico and Spain.

The Ariane 5 is incredibly reliable, having successfully completed more than fifty launches in a row. It is also much more expensive that Falcon 9, which is expected to cost a customer about half as much to get a payload into orbit.

Until SpaceX proves Falcon 9, Arianespace will be in a strong position to get customers. Once Falcon 9 starts flying regularly however, Arianespace will begin to lose business to this cheaper alternative. Thus, the new contracts will help tide the company over while they scramble to figure out how to reduce costs in order to compete.

In related news, SpaceX readies the new upgraded Falcon 9 for launch.

1 comment

A engineering problem during construction of one of the shuttle-derived solid rocket boosters for SLS is causing delays.

A engineering problem during construction of one of the shuttle-derived solid rocket boosters for SLS is causing delays.

[The] original test target of mid-2013 slipped when an issue with the aft segment [of the booster] was found. Inspection of the segment showed it was contained an area where propellant had debonded from the inside of the segment wall. Following analysis โ€“ which notably found no voids in the propellant itself โ€“ NASA decided to ask ATK to scrap the segment and cast a replacement.

Preparations … continued, with the shipping and integration of forward and center segments at the test site, while ATK went to work to replace the aft segment, following approval โ€“ post investigation โ€“ from NASAโ€™s Marshall Space Flight Center. After ATK successfully cast the replacement segment in July, technicians carried out routine ultrasound and x-ray tests. Unfortunately, the tests showed this segment had also had similar voids. [emphasis mine.]

The Space Launch System (SLS), was mandated by Congress to use as much shuttle-derived components as possible in order to supposedly save money as well as employ as many of the companies that built those components as possible. In reality, however, every one of those components has required significant redesign to make them work in SLS. In the case of the solid rocket boosters, the four segment shuttle boosters were not powerful enough. They had to be expanded to five segments.

Moreover, it appears from this article it was other technically unnecessary changes to the boosters that are now causing this problem.
» Read more

3 comments

NASA has put Orbital Sciences on notice that, assuming its demo cargo mission to ISS in two weeks is a success, the company might have to do it again as soon as December.

The competition heats up: NASA has put Orbital Sciences on notice that, assuming its demo cargo mission to ISS in two weeks is a success, the company might have to do it again as soon as December.

SpaceX is supposed to fly its next cargo mission first, but NASA thinks that flight will be delayed because of development issues with the upgraded Falcon 9 rocket.

2 comments

Orbital Sciences prepares its Cygnus capsule for its first flight to ISS, set for launch on September 17.

The competition heats up: Orbital Sciences prepares its Cygnus capsule for its first flight to ISS, set for launch on September 17.

Orbital officials said the Cygnus spacecraft was scheduled to be attached to the upper stage of the Antares launcher Wednesday. Final cargo loading into the Cygnus spacecraft’s pressurized module is set for Saturday, followed by its enclosure inside the rocket’s 12.8-foot-diameter payload fairing.

Rollout of the Antares rocket from its horizontal integration facility to the launch pad one mile away is expected Sept. 13.

September will be a busy and important month for private space. We also will have SpaceX’s first commercial launch with its Falcon 9 rocket. If both are successful, the trend away from a big government space programs shall accelerate.