First SLS launch faces more delays
No surprise here: The scheduled June 2020 first unmanned launch of NASA’s Space System Launch (SLS), already delayed by three years, appears threatened by more delays.
[NASA needs to perform]a similar structural test of the liquid oxygen fuel tank before what is known as a “green run” test. For this exercise, NASA will assemble the two large tanks and then integrate them with the rocket’s four main RS-25 engines. Then, at a test stand in southern Mississippi, the rocket will fire its engines through a standard launch of the rocket.
NASA has yet to formally set a date for this “green run” test, but whenever it does occur will be a key indicator for when we will see the first actual launch of the SLS rocket. If the green run test is conducted late in 2019, there would still be a chance for a 2020 launch. However, the agency and its prime contractor for the core stage, Boeing, are on a tight timeline that has little margin for technical problems that might occur during the structural tests of the tank or the green run tests. Historically, during this integration and test process with other large rocket programs, major problems have often occurred.
It is not clear how deeply the shutdown affected the SLS timeline, even though core stage work did proceed. “The shutdown impacted at least day for day,” one source said of the schedule. “But I am sure it was more than that.”
NASA originally planned to launch the SLS rocket on its maiden flight in November 2017, so the rocket will now be at least three years later than originally anticipated. The program’s budget is more than $2 billion a year, so these delays have cost the agency considerably.
The article also outlines the problems NASA is having developing the rocket’s upper stage.
I predict that the June 2020 launch will slip, maybe as much as six months, into 2021. This means the first manned flight will also be delayed into 2024, at the earliest.
That means it will have taken NASA more than twenty years and more than $60 billion to build and fly a single manned mission. Moreover, the cost and difficulty of operating SLS will make it impossible to get the second manned flight off the ground any earlier than three to four years later, at the earliest.
There is no chance the U.S. will put new footprints on the Moon if it continues to rely on this boondoggle. Worse, a continued reliance on SLS will force the government, for political reasons, to use its power to squelch competing private efforts, something we are seeing with the endless delays NASA has imposed on the commercial crew program.
Readers!
Please consider supporting my work here at Behind the Black. Your support allows me the freedom and ability to analyze objectively the ongoing renaissance in space, as well as the cultural changes -- for good or ill -- that are happening across America. Fourteen years ago I wrote that SLS and Orion were a bad ideas, a waste of money, would be years behind schedule, and better replaced by commercial private enterprise. Only now does it appear that Washington might finally recognize this reality.
In 2020 when the world panicked over COVID I wrote that the panic was unnecessary, that the virus was apparently simply a variation of the flu, that masks were not simply pointless but if worn incorrectly were a health threat, that the lockdowns were a disaster and did nothing to stop the spread of COVID. Only in the past year have some of our so-called experts in the health field have begun to recognize these facts.
Your help allows me to do this kind of intelligent analysis. I take no advertising or sponsors, so my reporting isn't influenced by donations by established space or drug companies. Instead, I rely entirely on donations and subscriptions from my readers, which gives me the freedom to write what I think, unencumbered by outside influences.
You can support me either by giving a one-time contribution or a regular subscription. There are four ways of doing so:
1. Zelle: This is the only internet method that charges no fees. All you have to do is use the Zelle link at your internet bank and give my name and email address (zimmerman at nasw dot org). What you donate is what I get.
2. Patreon: Go to my website there and pick one of five monthly subscription amounts, or by making a one-time donation.
3. A Paypal Donation or subscription:
4. Donate by check, payable to Robert Zimmerman and mailed to
Behind The Black
c/o Robert Zimmerman
P.O.Box 1262
Cortaro, AZ 85652
You can also support me by buying one of my books, as noted in the boxes interspersed throughout the webpage or shown in the menu above.
No surprise here: The scheduled June 2020 first unmanned launch of NASA’s Space System Launch (SLS), already delayed by three years, appears threatened by more delays.
[NASA needs to perform]a similar structural test of the liquid oxygen fuel tank before what is known as a “green run” test. For this exercise, NASA will assemble the two large tanks and then integrate them with the rocket’s four main RS-25 engines. Then, at a test stand in southern Mississippi, the rocket will fire its engines through a standard launch of the rocket.
NASA has yet to formally set a date for this “green run” test, but whenever it does occur will be a key indicator for when we will see the first actual launch of the SLS rocket. If the green run test is conducted late in 2019, there would still be a chance for a 2020 launch. However, the agency and its prime contractor for the core stage, Boeing, are on a tight timeline that has little margin for technical problems that might occur during the structural tests of the tank or the green run tests. Historically, during this integration and test process with other large rocket programs, major problems have often occurred.
It is not clear how deeply the shutdown affected the SLS timeline, even though core stage work did proceed. “The shutdown impacted at least day for day,” one source said of the schedule. “But I am sure it was more than that.”
NASA originally planned to launch the SLS rocket on its maiden flight in November 2017, so the rocket will now be at least three years later than originally anticipated. The program’s budget is more than $2 billion a year, so these delays have cost the agency considerably.
The article also outlines the problems NASA is having developing the rocket’s upper stage.
I predict that the June 2020 launch will slip, maybe as much as six months, into 2021. This means the first manned flight will also be delayed into 2024, at the earliest.
That means it will have taken NASA more than twenty years and more than $60 billion to build and fly a single manned mission. Moreover, the cost and difficulty of operating SLS will make it impossible to get the second manned flight off the ground any earlier than three to four years later, at the earliest.
There is no chance the U.S. will put new footprints on the Moon if it continues to rely on this boondoggle. Worse, a continued reliance on SLS will force the government, for political reasons, to use its power to squelch competing private efforts, something we are seeing with the endless delays NASA has imposed on the commercial crew program.
Readers!
Please consider supporting my work here at Behind the Black. Your support allows me the freedom and ability to analyze objectively the ongoing renaissance in space, as well as the cultural changes -- for good or ill -- that are happening across America. Fourteen years ago I wrote that SLS and Orion were a bad ideas, a waste of money, would be years behind schedule, and better replaced by commercial private enterprise. Only now does it appear that Washington might finally recognize this reality.
In 2020 when the world panicked over COVID I wrote that the panic was unnecessary, that the virus was apparently simply a variation of the flu, that masks were not simply pointless but if worn incorrectly were a health threat, that the lockdowns were a disaster and did nothing to stop the spread of COVID. Only in the past year have some of our so-called experts in the health field have begun to recognize these facts.
Your help allows me to do this kind of intelligent analysis. I take no advertising or sponsors, so my reporting isn't influenced by donations by established space or drug companies. Instead, I rely entirely on donations and subscriptions from my readers, which gives me the freedom to write what I think, unencumbered by outside influences.
You can support me either by giving a one-time contribution or a regular subscription. There are four ways of doing so:
1. Zelle: This is the only internet method that charges no fees. All you have to do is use the Zelle link at your internet bank and give my name and email address (zimmerman at nasw dot org). What you donate is what I get.
2. Patreon: Go to my website there and pick one of five monthly subscription amounts, or by making a one-time donation.
3. A Paypal Donation or subscription:
4. Donate by check, payable to Robert Zimmerman and mailed to
Behind The Black
c/o Robert Zimmerman
P.O.Box 1262
Cortaro, AZ 85652
You can also support me by buying one of my books, as noted in the boxes interspersed throughout the webpage or shown in the menu above.
I think Elon has pretty much said ‘eff it!’ with regards to showing up NASA at this point and knows it is a luxury he can no longer afford.
Starship may well land on the moon in time for the first crew of Orion to wave as they pass by overhead.
IMHO.
Because of the politics the next set of footsteps on the Moon will NOT be launched from Cape Canaveral, Florida but will depart, safely out of it’s reach, from Kopernik Shores, Texas
It is Elon’s “Hold my Beer” moment. Tom, Gwen & Co. will make it happen – the “stainless steely-eyed missile men and women”.
The company has sucked it up, trimmed expenses, picked up the pace to “ramming speed”, turned up the music to “11”, and is ready for a sprint to the Moon then Mars.
The Overton Window WRT spaceflight is continuing to move, the effects are being felt around the globe and soon in the heavens above.
As God and Robert Heinlein intended, envisioned by Chesley Bonestell and dreamed by many engineers.
Rest assured, NASA will have crew on board a SpaceX ship when Americans return to the Moon.
It is rather funny that after all this time, they choose to blame the shutdown. Can’t recall them making that excuse before but maybe they have.
What troubles me isn’t that this program staggers on through inertia but that the companies involved keep getting business from the government.