Engineers replace engine controller on SLS core; launch to be delayed

Engineers have successfully replaced the failed engine controller on the core stage of NASA’s SLS rocket.

Last week engineers and technicians successfully removed and replaced an engine controller from one of four RS-25 engines after the team identified an issue during a power-up test of the rocket’s core stage. Engineers are now performing standard engine controller diagnostic tests and check-outs, including controller power-up and flight software load. Subsequently, the team will work to complete all remaining SLS pre-flight diagnostic tests and hardware closeouts in advance of a mid-February rollout for a wet dress rehearsal in late February. NASA will set a target launch date after a successful wet dress rehearsal test.

The official schedule still lists the launch for February, but NASA has already admitted this is now impossible. Once they complete the wet dress rehearsal on the launchpad they will have to roll the rocket back into the Vehicle Assembly Building to do further tests. While it remains possible for NASA to meet an April launch window, more likely the agency will push back to windows during the summer.

Thus, the race between SLS and Starship for completing the first orbital flight remains neck-and-neck. Starship could launch this spring, but it faces an uncertain schedule determined not by SpaceX but by the bureaucracy in the federal government, which is reviewing the FAA’s environment reassessment for the Boca Chica launch site and really has no requirement to meet any schedule at all. The FAA says it plans to approve the reassessment by the end of February, but that is simply made up deadline. It could revise it at will at any time.

NASA meanwhile is still pushing to launch SLS in April, but this launch date is entirely unrealistic. Expect NASA to announce a new target date sometime in the summer in the coming weeks.

A detailed review of SLS’s present launch status

Link here. The article provides a detailed look at the engine controllers in the former shuttle engines that SLS is using on its core first stage, including some details about the failed unit and the issues involved in replacing it.

I found this historical data in the article most interesting:

The first attempt to launch Orbiter Atlantis and the STS-43 Shuttle vehicle was scrubbed before dawn on July 24, 1991, when the primary computer, DCU A, failed while propellants were being used loaded into the External Tank. … As a result, the launch was scrubbed to allow replacement of the controller, and the launch was rescheduled for August 1, 1991. The failure analysis of the controller revealed a broken blind lap solder joint connection of the bit jumper to the half stack, which is not a generic design problem.”

According to contemporaneous Shuttle Status Reports issued by NASA Public Affairs at KSC in late July, 1991, after the launch was scrubbed and the External Tank was drained and inerted, access to the engine area for maintenance was established on July 26. The broken engine controller was removed, and a new one was installed on July 27, followed by testing to verify the new controller on July 28; the three-day countdown was started over from the top on July 29 for the next launch attempt on the morning of August 1.

It took NASA less than a week to replace an engine controller in 1991. Now, it appears it might take NASA several months, including testing, to do the same thing on SLS. Moreover, the article suggests that there are other subcontractors and organizations (such as the range safety) that are also having trouble being ready for the presently scheduled mid-February launch.

All in all, this report suggests that SLS will not launch in February, will be delayed until April, with a strong chance that even that April date might not be met.

The report also illustrates the sluggish manner in which NASA operates today. Nothing is done with any speed. No task is done in one day if it can take a week. This is bad management, and also a very dangerous way to operate, as it actually encourages sloppiness because no one is under any pressure to work hard. The result has been endless niggling failures, each of which delays things interminably.

SLS likely facing another launch delay

Engineers for NASA’s SLS rocket have determined that they need to replace the flight controller on one of the engines in the rocket’s core stage, an action that will likely force a delay from the presently scheduled February launch date.

After performing a series of inspections and troubleshooting, engineers determined the best course of action is to replace the engine controller, returning the rocket to full functionality and redundancy while continuing to investigate and identify a root cause. NASA is developing a plan and updated schedule to replace the engine controller while continuing integrated testing and reviewing launch opportunities in March and April.

It appears they hope to make this change-out quickly and only have to delay one or two months, though at the moment it is also unclear this will be possible.

More delays for SLS?

According to a report today at Ars Technica, there is an engine issue with the SLS rocket presently being prepared for a February unmanned test flight that could delay the launch for months.

The info is buried at the very bottom of the article:

There’s an issue with an SLS engine controller. This past weekend, rumors emerged about a problem with the controller for one of the four RS-25 engines that power the Space Launch System. NASA has not officially commented, but Aviation Week’s Irene Klotz spoke with Aerojet’s RS-25 program manager, Jeff Zotti. Troubleshooting the problem began on November 22, Aviation Week reported.

Schedule impacts yet to be determined … If necessary, “replacing a line or a component … we’re probably talking about multiple days. Replacing an engine, we’re probably talking about multiple weeks,” Zotti told the publication. “On top of that, we have to assess what that does and how that affects the vehicle and the integration activities that are going on,” he added. All of that must be factored into a potential delay of the launch, presently scheduled for February 12. A summer launch for the SLS now seems far more likely than spring.

Any delay beyond March poses a very serious and complex problem. The solid rocket strap-ons have a one year life expectancy once stacked, and both were initially stacked about a year ago. The February launch pushes that life span somewhat. A longer delay is more than can be waived.

NASA IG: Artemis manned lunar landing will likely not happen in ’25

IG's estimate of SLS's per launch cost

According to a new NASA inspector general report released today [pdf], because of numerous technical, budgetary, and management issues, the planned Artemis manned lunar landing now set for 2025 is likely to be delayed several years beyond that date. From the report’s summary:

NASA’s three initial Artemis missions, designed to culminate in a crewed lunar landing, face varying degrees of technical difficulties and delays heightened by the COVID-19 pandemic and weather events that will push launch schedules from months to years past the Agency’s current goals. With Artemis I mission elements now being integrated and tested at Kennedy Space Center, we estimate NASA will be ready to launch by summer 2022 rather than November 2021 as planned. Although Artemis II is scheduled to launch in late 2023, we project that it will be delayed until at least mid-2024 due to the mission’s reuse of Orion components from Artemis I. … Given the time needed to develop and fully test [SpaceX’s Starship lunar lander] and new spacesuits, we project NASA will exceed its current timetable for landing humans on the Moon in late 2024 by several years. [emphasis mine]

Gosh, it sure didn’t long for my prediction from last week — that the new target date of ’25 was garbage — to come true.

Today’s report also states that it does not expect the first test launch of SLS to occur in February ’22, as NASA presently predicts, but later, in the summer of ’22. It then notes that the next SLS launch, meant to be the first manned launch of SLS and Orion and presently scheduled for late ’23, will almost certainly be delayed to mid-’24. And that’s assuming all goes well on the first unmanned test flight.

While the report lauds SpaceX’s fast development pace, it also does not have strong confidence in SpaceX’s ability to get its Starship lunar lander ready on time, and believes that NASA could see its completion occurring from three to four years later than planned.

The report also confirms an August 2021 inspector general report about NASA’s failed program to develop lunar spacesuits, stating that its delays make a ’24 lunar landing impossible.

The report states that Gateway is well behind schedule, and will likely not be operational until ’26, at the earliest. While the present plan for that first manned lunar landing does not require Gateway, Gateway’s delays and cost overruns impact the overall program.

Finally, the report firmly states that the per launch cost of SLS is $4.1 billion, a price that will make any robust lunar exploration program utterly unsustainable.

Before the arrival of Trump, NASA’s original plan for SLS and Gateway called for a manned lunar landing in 2028. The Trump administration attempted to push NASA to get it done by ’24. This inspector general report suggests to me that this push effort was largely wasted, that NASA’s Artemis program will likely continue to have repeated delays, announced piecemeal in small chunks. This has been the public relations strategy of NASA throughout its entire SLS program. They announce a target date and then slowly over time delay it in small amounts to hide the fact that the real delay is many years.

Expect this same pattern with the manned lunar landing mission. They announce a delay of one year from ’24 to ’25. After a year they will then announce another delay to ’26. A year later another delay to ’27. And so forth.

NASA admits manned lunar landing can’t happen before ’25

NASA administrator Bill Nelson admitted today that the goal of landing Americans back on the Moon by 2024 was impossible, and that the agency has now delayed that target date one year to 2025.

Nelson attempted to blame the delay on Blue Origin’s lawsuit against NASA for its award of the manned lunar lander contract to SpaceX.

He blamed the shifting timeline on a lawsuit over the agency’s moon lander, to be built by SpaceX, and delays with NASA’s Orion capsule, which is to fly astronauts to lunar orbit. “We’ve lost nearly seven months in litigation, and that likely has pushed the first human landing likely to no earlier than 2025,” Mr. Nelson said, adding that NASA will need to have more detailed discussions with SpaceX to set a more specific timeline.

This however is a bald-faced lie. The Trump 2024 deadline was never realistic. Moreover, delays in SLS and Orion have been continuous and ongoing for years, all of which made a ’24 landing quite difficult and if attempted extremely unsafe. Even as it is, trying this mission by ’25 is risky, especially if it depends on SLS. Moreover, as the article notes, how SLS, Orion, and SpaceX’s Starship will team up to get this mission — designed by a committee — to and from the Moon remains exceedingly unclear.

With great confidence I predict that if the lunar mission depends on SLS in any manner, it will not launch in ’25 either.

NASA sets target launch date for SLS in February ’22

As expected, the first unmanned demo launch of NASA’s SLS rocket has now been scheduled for a February launch window.

The first launch window for NASA’s Artemis I mission opens on February 12 at 5:56 p.m. EDT – yes, we have dates and times for this long-awaited mission. The February window lasts two weeks, with the first half of that window allowing a six-week mission and a four-week mission on the back half.

If for some reason NASA cannot launch in that firs window, they have back up windows in March and April. These windows exist because the plan is to send the Orion capsule to orbit the Moon from four to six weeks, and then return to Earth.

The announcement came the day after NASA had finally stacked the Orion capsule on top of the SLS rocket, essentially completing the rocket’s assembly.

NASA awards Aerojet Rocketdyne contract to build 20 Orion main engines

NASA announced yesterday that it has awarded Aerojet Rocketdyne the contract to build twenty Orion main engines for capsules on missions running through 2032, with the first to be used on the seventh Artemis launch..

This engine is the one that Orion will use to enter and leave lunar orbit.

Based on the pace that NASA expects to launch SLS, once per year, I expect the last engine in this contract will fly in 2048, not 2032, since it will take about 27 years to put that many Orions into space after SLS’s first launch, expected sometime in the next five months.

In other words, this is a contract to keep the jobs at Aerojet Rocketdyne in existence for the next three decades, even if that company’s engineers build little and accomplish less. Nice welfare work I must say.

GAO finds more NASA cost overruns in Webb, SLS, and Orion

GAO graph documenting NASA's big project delays and cost overruns

The annual Government Accountability Office’s (GAO) report on major NASA-led programs has found that the cost overruns and scheduling problems it has documented now for years continued in 2020.

You can obtain the report here. The graph to the left, from the report, summarizes the data quite succinctly.

The cumulative cost overrun of 20 major programs in development, defined as those with total costs of at least $250 million, grew to more than $9.6 billion in the report. Three programs — the James Webb Space Telescope, Orion spacecraft and Space Launch System — account for $8 billion of that total, including $4.4 billion for JWST alone.

SLS and the Exploration Ground Systems program accounted for effectively all of the $1.1 billion in overruns in 2020. … SLS alone accounted for nearly $990 million in cost increases. About two-thirds of that increase came from NASA adopting a GAO recommendation to lower the original baseline cost estimate for SLS to properly account for work that had been shifted to later phases of the program.

The report also documented almost 20 years of cumulative delays, with Webb leading the way with delays of more than seven years. The new report added 37 more months of delays during the last year.

The report, and NASA, laid the blame for many of the more recent delays and cost overruns on last year’s COVID epidemic, but if so those delays were imposed by choice, not necessity, considering how both China and SpaceX moved forward without any delays during the same time period. In reporting on NASA for the last three decades I have found it willing to initiate long delays at the drop of a hat, sometimes for reasons, such as a storm that causes some minor damage, that do not justify either the delay or its length. The COVID panic was just another example of this.

ESA contracts Airbus to build three more Orion service modules

The European Space Agency (ESA) late last week announced that it has awarded Airbus a contract to build three more service modules for NASA’s Orion capsule.

This new contract supplements the existing contract that already has Airbus building three service modules. With six service modules in the pipeline, the ESA is signaling that it is very confident the Artemis program will continue.

The key question remains: Will it continue with SLS as the rocket of choice? Right now there simply aren’t the funds to build six SLS rockets. Congress has only funded two. Moreover, the pace of construction for SLS means that, if funded, it will likely take a decade at least for it to launch these six capsule/service modules. Since SpaceX’s Starship/Super Heavy will likely be operational in about half that time, and will also be capable of much more for far less, I suspect that if these additional Orion capsules get launched, they will do so on something other than SLS.

NASA to do another static fire test of SLS’s core stage

NASA has now scheduled a second static fire test of the core stage of its SLS rocket, tentatively scheduled for the fourth week in February.

The first test, planned to last eight minutes, shut down after only one minute when the stage’s computers decided the parameters on engine #2 were outside their conservative margins. That burn also had a sensor issue with its fourth engine.

Conducting a second hot fire test will allow the team to repeat operations from the first hot fire test and obtain data on how the core stage and the engines perform over a longer period that simulates more activities during the rocket’s launch and ascent. To prepare for the second hot fire test, the team is continuing to analyze data from the first test, drying and refurbishing the engines, and making minor thermal protection system repairs. They are also updating conservative control logic parameters that resulted in the flight computer ending the first hot fire test earlier than planned. The team has already repaired the faulty electrical harness which resulted in a notification of a Major Component Failure on Engine 4. This instrumentation issue did not affect the engine’s performance and did not contribute to ending the first test early.

Assuming this test is successful, they will then need a month to get the stage ready for shipment by barge to Cape Canaveral, where it will take several more months to get it assembled with its two strap-on solid rocket boosters, its upper stage, and the Orion capsule on top.

Right now the unmanned test flight into orbit of this entire rocket and Orion is set for November ’21. While NASA has not announced a delay, this additional static fire test puts significant pressure on that schedule.

New Democrat head of House subcommittee covering NASA says he supports Artemis

The new Democrat head of the House appropriations subcommittee that covers NASA funding, Matt Cartwright (D-Pennsylvania), appears to support the Artemis program established during the Trump administration, though he has also indicated that he does not favor the timeline imposed by Trump to land a manned mission on the Moon by ’24.

Cartwright’s embrace of Artemis during [a] July 2020 webinar was a change from 2019 when he was one of several members reacting skeptically to a supplemental budget request from the Trump Administration after it unexpectedly accelerated the timeline for putting people back on the Moon from 2028 to 2024. He complained NASA did not even have a cost estimate for the entire effort, yet expected Congress to embrace it.

In 2018, he expressed concern about proposed cuts by the Trump Administration to NASA’s earth and space science activities especially climate programs and WFIRST (now the Roman Space Telescope). He urged NASA to follow the Decadal Surveys produced by the National Academies of Sciences, Engineering, and Medicine.

What his prior views presage now that he chairs the subcommittee remains to be seen. It is widely expected the 2024 deadline will be pushed back, perhaps to the 2028 date NASA originally planned, but Cartwright appears favorably disposed towards the agency overall.

Delaying the Moon landing by SLS forever is the real goal, so the jobs program can be extended without any risks. To actually fly might result in a failure, something that no politician wants.

In the end it will not be SLS anyway that gets Americans back to the Moon. It costs too much and is badly designed. It might fly once or twice, but after that Congress will drop it while keeping Artemis, albeit in a very different form. Instead of having NASA design and build things, the new Artemis will be built by the many companies who were awarded fixed priced contracts during the Trump administration to develop their own hardware as fast as possible and as inexpensively as possible.

The distinction is important, because the latter is more likely to succeed in a reasonable amount of time.

At the same time, with Congress on board and a Democrat in the White House, it is not surprising that the policy is immediately shifting to a slower timeline. Can’t get this done too fast! I must also add that 2028 was not NASA’s original date for its return to the Moon. Before the Trump administration took control of Artemis, NASA had wanted to complete Gateway first, which based on all of NASA’s previous schedules would have pushed a lunar landing into the 2030s. Do not be surprised if this sluggish schedule is reinstated.

In fact, with the present incompetents in charge in Washington, I fully expect China to own the Moon, while U.S. politicians brainlessly dither on how to spend pork.

Another SLS core stage abort during dress rehearsal

NASA today revealed that engineers were forced on December 20th to abort at about T-5 minutes their second attempt to do a fueled dress rehearsal countdown in preparation for the full core stage static fire test.

[S]ources said the terminal countdown started at T-10 minutes and counting and ran down to T-4 minutes and 40 seconds where an unplanned hold occurred. … The criteria for how long it should take for a liquid hydrogen replenish valve to close was violated at that point in the countdown when the valve was commanded to the close position as a part of the process to pressurize the liquid hydrogen tank for engine firing. After holding at the T-4:40 point for a few minutes, teams decided the terminal countdown test couldn’t continue.

Vehicle safing and recycle sequences were then executed.

Although the countdown ran for over half of its intended duration, the early cutoff left several major milestones untested. With the countdown aborted at that point, the stage’s propellant tanks weren’t fully pressurized, the hydraulic Core Stage Auxiliary Power Units (CAPUs) were never started, the final RS-25 engine purge sequence was never run, and the vehicle power transfer didn’t occur.

NASA management is debating now whether they can proceed directly to the full core stage static fire test, where the core stage engine will fire for the full duration of a normal launch. It could be that they will decide to waive testing what was not tested on this last dress rehearsal.

If they delay the full test to do another dress rehearsal, they risk causing a delay in the fall launch of SLS, as they need a lot of time to disassemble, ship, and reassembly the stage in Florida. If they don’t delay, they risk either a failure during the full static fire test, or (even worse) a failure during that first launch.

Considering the number of nagging problems that have plagued this test program, it seems foolish to me to bypass any testing. They not only do not have enough data to really understand how to fuel the core stage reliably, they don’t even have a lot of practice doing the countdown itself. All this bodes ill when they try to launch later this year, especially if they decide to not work the kinks out now.

NASA budget passed by Congress rejects ’24 lunar landing

No surprise: The NASA budget that was passed by Congress this week as part of a giant omnibus bill only gave NASA 25% of the requested funds the agency says it needs to develop a human lander required for an Artemis manned mission to the Moon by ’24.

Overall, NASA will receive $23.271 billion, almost $2 billion less than requested. Importantly for the Trump Administration’s Artemis program to return astronauts to the Moon by 2024, it provides only $850 million instead of $3.4 billion for Human Landing Systems.

…The Trump Administration requested a 12 percent increase for NASA in order to fund the Artemis program: $25.2 billion for FY2021 compared to the $22.9 billion it received in FY2020. While the goal of returning astronauts to the Moon has broad bipartisan support in Congress, the Trump deadline of 2024 — set because it would have been the end of his second term if he had been reelected — won lukewarm support at best from Republicans and none from Democrats who pointed to both budgetary and technical hurdles.

It was always clear that the Democrats were not going to cooperate with Trump to could get that lunar landing during his second term. Moreover, the real goal of Artemis is not space exploration, but distributing pork. Stretching out these missions so that they take many many years achieves that goal far better than a tight competitive schedule that gets things done. This is why SLS and Orion have been under construction, with no flights, for decades, even as SpaceX moves forward with Starship/Super Heavy in only a few years.

A Biden presidency actually increases the changes that Artemis will get better funding, but that funding will always be designed to stretch out the program for as long as possible. Our policymakers in Washington really do not care much for the interest of the nation. What they care about is their own power and aggrandizement.

NASA decides to fly Orion with failed power unit

Because a repair would delay the first SLS launch for months if not a year, NASA has decided to fly Orion on that November ’21 mission with failed electronics power unit.

In a Dec. 17 statement, NASA said it had decided to “use as is” one of eight power and data units (PDU) on the Orion spacecraft, which provide communications between the spacecraft’s computers and other components. One of two redundant channels in one of two communications cards in that PDU is not working.

…NASA, in its statement about deciding not to replace the PDU, did not go into details about the repair options, but said that the risks of damaging the spacecraft during the PDU repair outweighed any loss of data should the unit completely malfunction.

Engineers, the agency stated, “determined that due to the limited accessibility to this particular box, the degree of intrusiveness to the overall spacecraft systems, and other factors, the risk of collateral damage outweighed the risk associated with the loss of one leg of redundancy in a highly redundant system.”

“NASA has confidence in the health of the overall power and data system, which has been through thousands of hours of powered operations and testing,” the agency added, noting that the PDU in question was still “fully functional.”

Let’s then assess Orion. The contract was issued to Lockheed Martin in 2006. In the fourteen years since Congress has spent about $17 billion on this manned capsule. In that time it has flown once, during a test flight that was intended to test its heat shield, even though when that flight happened NASA had already decided that it was not going to use the heat shield design it was testing.

Orion’s second flight in November ’21 will be unmanned, but it will be flying with this failed unit. The next time it is supposed to fly will be in ’24, when NASA is hoping to send astronauts on a lunar landing missions. By that time NASA will have spent about $20 billion on Orion, and gotten two test capsules (both unrepresentative of the flight model) plus one manned mission.

Would you fly on this capsule under these circumstances? I wouldn’t, especially considering the non-track record of its rocket, SLS.

As the taxpayer, do you think you’ve gotten your money’s worth from this capsule? I don’t. I think it has been an ungodly waste of money, and a demonstration of the incapability of NASA and the big space contractors Boeing and Lockheed Martin of getting anything accomplished. Depend on them, and you will never go anywhere.

An update on the testing of SLS’s core stage

Link here. The article provides more information on the temperature issue that caused the seventh of eight fueling tests of the core stage to abort early.

The temperature issue arose when NASA transferred superchilled liquid oxygen, to fuel the rocket, from a holding facility to the core stage of the SLS. This procedure has been modeled and verified before, Julie Bassler, SLS stages manager at Marshall, told reporters during the same teleconference. But this was the first time the transfer actually took place.

“We were actually just a few degrees different than what we wanted to see coming in,” she continued, but said the temperature must be precise during the initial phases of filling the tank. The requirement is minus 290.57 degrees Fahrenheit (minus 179.21 degrees Celsius.) But the liquid oxygen was slightly cooler, at minus 296.67 degrees Fahrenheit (minus 182.59 degrees Celsius).

“We filled up [the tank] just enough to pass the phase where we knew we weren’t going to be able to get the temperature to a level that was going to be acceptable to meet the requirement, and that’s when they caught us … in the testing,” Bassler continued.

Despite this issue, NASA still hopes to do the last core stage test, dubbed the Green Run, in the last week in December. During that static fire test they will fuel the core stage entirely and then fire its engines for the full duration of an actual launch — almost ten minutes. If all goes well they will then pack up the stage and ship it to Florida for the planned November unmanned test mission sending Orion around the Moon.

They have no schedule margins, however, because all the components of this very expensive and complex rocket need a lot of time to get anything done. The two solid rocket boosters that will be attached to the sides of the core stage only have a twelve month lifespan once assembled, and they are holding off assembling them pending this test. The core stage itself needs two months to be disassembled, and then two months to be reassembled in Florida. And there remain the issue of a failed power unit in the Orion capsule that could take four to twelve months to repair.

The article however had this telling quote, based on comments from a NASA official, about future launch procedures, that sent a chill up my spine:
» Read more

New problem found on Orion that could delay its launch by a year

The failure of a power unit on the Orion capsule slated to fly on SLS’s first test flight late in ’21 could delay that test flight by as much as an additional year.

Replacing the PDU isn’t easy. The component is difficult to reach: it’s located inside an adapter that connects Orion to its service module — a cylindrical trunk that provides support, propulsion, and power for the capsule during its trip through space. To get to the PDU, Lockheed Martin could remove the Orion crew capsule from its service module, but it’s a lengthy process that could take up to a year. As many as nine months would be needed to take the vehicle apart and put it back together again, in addition to three months for subsequent testing, according to the presentation.

Lockheed has another option, but it’s never been done before and may carry extra risks, Lockheed Martin engineers acknowledge in their presentation. To do it, engineers would have to tunnel through the adapter’s exterior by removing some of the outer panels of the adapter to get to the PDU. The panels weren’t designed to be removed this way, but this scenario may only take up to four months to complete if engineers figure out a way to do it.

A third option is that Lockheed Martin and NASA could fly the Orion capsule as is. The PDU failed in such a way that it lost redundancy within the unit, so it can still function. But at a risk-averse agency like NASA, flying a vehicle without a backup plan is not exactly an attractive option. It’s still not clear what went wrong inside the unit, which was tested before it was installed on the spacecraft, according to a person familiar with the matter.

None of these options are good. The first two will certainly delay the planned November 2021 launch, which by the way is already four years behind schedule. The third will risk a failure of the mission, which though unmanned would certainly lead to further delays in the manned mission expected one or two years later.

That they don’t know why the unit failed and cannot fix it easily speaks very badly to the design of Orion and SLS. Compare this with SpaceX, which in the past month has demonstrated it can in only days switch out engines on both its commercial Falcon 9 rocket and its new next generation Starship rocket. Moreover, SpaceX has demonstrated repeatedly that once they identify an issue they move immediately to understand it and fix it.

With NASA, Orion, and Orion’s contractor Lockheed Martin, such flexibility and agility appears all but impossible. They have designed a monster that cannot be fixed easily, cannot launched quickly, and costs an ungodly amount of money.

I increasingly believe that Starship will reach orbit before SLS/Orion, even though the latter has been in development for almost three times longer, and will cost 25 times more.

Senate fails to fully fund manned lander for Trump’s 2024 lunar mission

The Senate appropriations committee’s budget recommendations for NASA, released yesterday, has refused to fully fund the development of the manned lander needed for Trump’s 2024 lunar mission.

The Senate Appropriations Committee released its recommendations for all 12 FY2021 appropriations bills today. The Commerce-Justice-Science (CJS) bill provides NASA with $23.5 billion, $1.75 billion less than requested. The House-passed bill keeps the agency at its current level of $22.6 billion, so the final compromise likely will be somewhere in that range. NASA’s request for Human Landing Systems (HLS) for the Artemis program was particularly hard hit on both sides of Capitol Hill.

NASA had requested $3.4 billion for building the lunar lander in time for 2024. The House appropriated $628 million. Today’s Senate recommendation budgeted $1 billion. This practically guarantees that no manned lunar mission will happen by 2024.

None of this is a surprise. The politicians in Congress from both parties don’t really want to rush this program. For them it is better to stretch it out for as long as possible, spending mucho bucks in their states and districts. Nothing will be accomplished, but they will be able to tell their constituents they brought the jobs home.

Useless and empty jobs, but jobs nonetheless.

NASA lays out Artemis budget and plan to get astronauts to Moon

In a obvious lobbying effort to get Congress to fund the Trump administration’s Artemis project to land humans on the Moon by 2024, NASA yesterday released a new updated plan and budget for the program.

More here.

The document [pdf] outlines the specific plans for each of the first three Artemis flights, with the first unmanned, the second manned and designed to fly around the Moon, and the third to land a man and a woman on the Moon. Overall the plan is budgeted at about $28 billion, with $3.2 billion needed immediately to fund construction of the lunar lander. From the second link:

Bridenstine said he remains optimistic Congress will fully fund lander development because of what he described as broad bipartisan support for the Artemis program. He said he’s hopeful an expected continuing resolution that would freeze NASA’s budget at last year’s spending levels will be resolved in an “omnibus” spending bill before Christmas or, if the CR is extended, by early spring. “It is critically important that we get that $3.2 billion,” he said. “And I think that if we can have that done before Christmas, we’re still on track for a 2024 moon landing. … If we go beyond March, and we still don’t have the human landing system funded, it becomes increasingly more difficult.”

And what happens then?

“It’s really simple. If Congress doesn’t fund the moon landing program, then it won’t be achieved (in 2024), I mean it’s really that simple,” Bridenstine said. But he quickly added: “I want to be clear, if they push the funding off, our goal will be to get to the moon at the earliest possible opportunity.”

I remain doubtful the present Congress, with the House controlled by the Democrats, will fund this 2024 lunar landing. Since 2016 the entire political platform of the Democratic Party has been “oppose anything Trump.” They will not fund this project if it means he will get this landing during his second term.

If however Trump loses in November, the lame duck Congress might then go ahead and fund it before December, since the landing in 2024 will then occur during the Biden presidency.

Technically the plan reveals that NASA is trying to accelerate the development of the rendezvous and docking software for Orion. During the second flight, the first manned, the crew will do proximity maneuvers with the upper stage of the rocket. Under previous management NASA had not included this ability, as they had not planned to have Orion do any rendezvouses or dockings. That lack makes it impossible for Orion to fly on any other rocket but SLS. This change means the Trump administration recognizes this is a problem, and wants to fix it, especially because they also recognize that SLS is a poor long term option for future lunar missions.

First manned Artemis Moon mission might not go to south pole

In order to meet the Trump administration’s 2024 deadline for the first Artemis manned lunar landing, NASA is now considering sending that first mission to an equatorial target, rather than the Moon’s south pole.

The Artemis program landing site issue came up at two separate events with agency leaders this week, beginning with NASA Administrator Jim Bridenstine’s comments to open a digital meeting held by a NASA advisory group called the Lunar Exploration Analysis Group, on Monday (Sept. 14).

“For the first mission, Artemis 3, our objective is to get to the south pole,” Bridenstine said. “But … it would not surprise me if, for example, if we made a determination that the south pole might be out of reach for Artemis 3, which I’m not saying it is or isn’t,” interest in the Apollo sites may win out.

The engineering to get to the polar regions is more challenging, so rather than delay that first mission they are considering simplifying it instead.

The fact remains that Congress has still not funded any Artemis missions beyond the first unmanned and first manned flights, neither of which will land on the Moon. Whether that money will ever be forthcoming really depends entirely on the November election, as well as the success or failure of the upcoming full-up static fire engine test of the SLS first stage.

Midnight repost: The Lie that is Orion

The tenth anniversary retrospective of Behind the Black continues: This essay, written in July 2016, might provide modern readers with some background and context into the uselessness of NASA’s over priced, over designed, and behind schedule Orion capsule. The only thing that has changed in the four years since is that NASA has stopped claiming Orion is an interplanetary spaceship. They now freely admit that to get to Mars they need to build and assemble much larger ships, of which Orion will only be a tiny part.

————————-
The Lie that is Orion

Several weeks ago NASA put out one of its periodic press releases touting the wonders of the engineering the agency is doing to prepare for its future missions to Mars. In this case the press release described a new exercise device, dubbed ROCKY (for Resistive Overload Combined with Kinetic Yo-Yo), for use in the Orion capsule.

“ROCKY is an ultra-compact, lightweight exercise device that meets the exercise and medical requirements that we have for Orion missions,” said Gail Perusek, deputy project manager for NASA’s Human Research Program’s Exploration Exercise Equipment project. “The International Space Station’s exercise devices are effective but are too big for Orion, so we had to find a way to make exercising in Orion feasible.

As is their habit these days in their effort to drum up support for funding for SLS and Orion, the press release was filled with phrases and statements that implied or claimed that Orion was going to be the spacecraft that Americans will use to explore the solar system.

…engineers across NASA and industry are working to build the Orion spacecraft and Space Launch System rocket that will venture to deep space for the first time together…

…Over the next several years, NASA’s Human Research Program will be refining the device to optimize it not only for near-term Orion missions with crew, but for potential uses on future long-duration missions in Orion…

These are only two examples. I have clipped them because both were very carefully phrased to allow NASA deniablity should anyone question these claims. For example, in the first quote they qualify “deep space” as specifically the 2018 unmanned lunar test flight. And the second quote is qualified as referring to missions to lunar space. Nonetheless, the implied intent of this wording is to sell Orion as America’s interplanetary spaceship, destined to take us to the stars!

Don’t believe me? Then take a look at NASA’s own Orion webpages, starting with the very first words on their Orion Overivew page.
» Read more

NASA delays 1st SLS launch again

NASA has now made official what had been expected for months, announcing a new delay of the first unmanned test flight of its SLS rocket from March 2021 to November 2021.

The article tries to put a lot of the blame for this new delay on the shut down over the Wuhan panic, but that shut down will only stop work for at most two months. The new delay however adds eight months to the schedule, showing that they probably were never going to meet that March 2021 deadline, and are using COVID-19 as a cover for the program’s continuing problems, delays, and cost overruns.

Should this unmanned flight take place in November 2021, it will have taken NASA about seventeen years and about $60 billion to get to that first flight. They say the first manned mission is scheduled in late 2022 or early 2023. If true would mean it took NASA about two decades to achieve a single manned flight since Bush Jr. proposed it.

Of course, that is making the very unlikely assumption that there will be no further delays before that first manned flight. I personally am very confident there will be.

NASA awards SpaceX deal to provide cargo to Gateway

Capitalism in space: Should NASA ever decide to build its proposed Gateway space station in orbit around the Moon (the odds of which have gone down recently), it announced today that it has signed a deal with SpaceX to use its Falcon Heavy rocket and an upgraded larger version of its Dragon capsule to ship cargo to that station.

The deal calls for at least two missions, and is SpaceX’s first deal in NASA’s Artemis program.

This deal is a major blow to SLS and Boeing, which up to now had a monopoly on all launches to supply and launch Gateway. In fact, Gateway was invented by Lockheed Martin, Boeing, and NASA (not Congress) in order to justify SLS’s existence. That NASA has now decided it is better off using the much cheaper and already operational Falcon Heavy for some Gateway missions suggests that SLS is increasingly vulnerable to cancellation. NASA is making it obvious that other commercial options exist. No need to wait years and spend billions for SLS, when they can go now, for much less.

NASA shuts down all in-house work, suspending SLS/Orion testing

In its panicky response to COVID-19, NASA is now requiring all workers to work from home, forcing the agency to suspend all in-house testing of SLS and Orion hardware.

NASA will temporarily suspend production and testing of Space Launch System and Orion hardware. The NASA and contractors teams will complete an orderly shutdown that puts all hardware in a safe condition until work can resume. Once this is complete, personnel allowed onsite will be limited to those needed to protect life and critical infrastructure.

We realize there will be impacts to NASA missions, but as our teams work to analyze the full picture and reduce risks we understand that our top priority is the health and safety of the NASA workforce.

This guarantees further delays to the first Artemis unmanned launch sometime in 2021. It also is par for the course for NASA’s entire effort to build this rocket. In just the past two weeks three different blistering inspector general reports have blasted different components of this project at NASA (overall management, construction of the launch systems, and development of software), proving that out-of-control cost overruns and endless delays in building SLS and Orion have been systemic throughout the agency.

Now they have shut down testing, even though the Wuhan virus is probably going to end up no more dangerous than the flu (now that treatment options exist).

NASA’s inspector general finds more budget overruns at Artemis

A new report [pdf] released today from NASA’s inspector general has found more budget overruns and managerial issues relating to developing the ground software required by both Orion and SLS.

There are two software components involved, called SCCS and GFAS for brevity. This report focuses on the latter. A previous report found that “SCCS had significantly exceeded its initial cost and schedule estimates with development costs increasing approximately 77 percent and release of a fully operational version of the software slipping 14 months.” According to that previous report [pdf], that increase went from $117 million to $207 million.

As for GFAS:

Overall, as of October 2019 GFAS development has cost $51 million, about $14 million more than originally planned.

This report, as well as yesterday’s, are quite damning to the previous management of NASA’s manned program under Bill Gerstenmaier. It appears they could not get anything done on time and even close to their budget.

It also appears to me that the Trump administration has removed the reins from its inspector general offices. During the Obama administration I noticed a strong reticence in IG reports to criticize government operations. Problems as outlined in both yesterday’s and today’s reports would have been couched gently, to obscure how bad they were. Now the reports are more blunt, and are more clearly written.

Also, this sudden stream of releases outlining the problems in Artemis might be part of the Trump administration’s effort to shift from this government program to using private commercial companies. To do this however the administration needs Congressional support, which up to now has strongly favored funding SLS and Orion. Having these reports will strengthen the administration’s hand should it propose eliminating these programs, as it is now beginning to do with Gateway.

More overruns in NASA’s SLS program, this time with the mobile launchers

A new inspector general report [pdf] has found massive cost overruns in NASA over the building of the two mobile launch platforms the agency will use to launch its SLS rocket.

The original budget for the first mobile launch was supposed to be $234 million. NASA has now spent $927 million.

Worse, this platform will see limited use, as it was designed for the first smaller iteration of SLS, which NASA hopes to quickly replace with a more powerful version. Afterward it will become obsolete, replaced by the second mobile launch platform, now estimated to cost $486 million.

That’s about $1.5 billion just to build the launch platforms for SLS. That’s only a little less than SpaceX will spend to design, test, build, and launch its new Starship/Super Heavy rocket. And not only will Starship/Super Heavy be completely reusable, it will launch as much if not more payload into orbit as SLS.

But don’t worry. Our geniuses in Congress will continue to support SLS no matter the cost, even if it bankrupts NASA and prevents any real space exploration. They see its cost overruns, long delays, and inability to accomplish anything as a benefit, pumping money into their states and districts in order to buy votes.

SLS likely launch mid- to late-2021

According to comments by one NASA official last week, the first flight of SLS will likely not occur until the middle or late 2021, a further delay than the most recent prediction of April 2021.

NASA Associate Administrator Steve Jurczyk said on Friday that the first launch of the Space Launch System (SLS) with an uncrewed Orion spacecraft, Artemis I, will take place in mid-late 2021. He also said NASA will award contracts “within weeks” for the Human Landing System (HLS) as NASA strives to meet the Trump Administration’s goal of landing astronauts on the Moon by 2024 — the Artemis program. Embracing Artemis is the first step towards a trillion dollar cislunar space economy according to space industry executive Tory Bruno who spoke at the same conference in Laurel, MD. He urged everyone to stop “squabbling” and support the program.

There is a lot more in the article, including a lot of advocacy by Jurczyk and others for Lunar Gateway. I also found certain aspects of the Trump administration’s effort to make their 2024 target date for manned lunar landing, specifically related to the quick development of that Human Landing System (HLS), somewhat concerning:

We can’t thrash on the requirements. So on HLS, we said 90 days, we’re going to nail down the requirements. And if we can’t agree, NASA’s just going to tell you, use ours. We’re going to negotiate technical standards. Either use ours or show equivalency to yours, but after 90 days if we can’t get agreement, you’re going to use ours. … 90 days and we’re done with Human Landing System requirements.

I am all for doing it fast but one needs to also do it smart. I wonder about this approach.

Jurczyk noted that the administration and NASA are doing a lot of work outlining their plans for the whole Artemis exploration program following that lunar landing, and hope to reveal it by the end of March. Since this program still remains unfunded by Congress, that announcement will be part of the political campaign to obtain those funds.

Boeing proposes manned lunar lander that bypasses Gateway

Capitalism in space: Boeing today announced its bid to build a manned lunar lander for NASA’s Artemis program, with its lander launched to go directly to the Moon rather than stopping at the proposed Lunar Gateway lunar space station.

The company said its “Fewest Steps to the Moon” proposal, submitted for NASA’s Human Landing Services program, minimized the number of launches and other “mission critical events” needed to get astronauts to the surface of the moon. “Using the lift capability of NASA’s Space Launch System Block 1B, we have developed a ‘Fewest Steps to the Moon’ approach that minimizes mission complexity, while offering the safest and most direct path to the lunar surface,” Jim Chilton, senior vice president for space and launch at Boeing Defense, Space and Security, said in a company statement.

The two-stage launched would launch on the enhanced Block 1B version of the rocket, which uses the more powerful Exploration Upper Stage (EUS), and go into lunar orbit. It would either rendezvous with the lunar Gateway or directly with an Orion spacecraft, where astronauts would board it for a trip to the lunar surface. The lander is designed to be launched as a single unit, rather than in separate modules that would be aggregated at the Gateway. The lander also doesn’t require a separate transfer stage to maneuver from a near-rectilinear halo orbit to low lunar orbit, as some other designs have proposed.

This approach, the company said in a statement, reduces the number of mission critical events, such as launches and dockings, to as few as five. Alternative approaches, Boeing claims, require 11 or more such events. [emphasis mine]

Boeing is essentially proposing a plan that makes Gateway unnecessary, a bidding ploy that very well might work with the Trump administration, which has already reduced Gateway’s initial construction to speed up its attempt to get to the Moon by 2024.

More important, Boeing’s proposal makes it very clear how unnecessary Gateway is, and how that boondoggle actually slows down our effort to return to the Moon. This is great news, for several reasons. First it shows that Boeing, one of the old big contractors that historically has depended on government dollars, is now publicly stating that it is not in favor of Gateway. This in turn makes it more politically acceptable for politicians to take this position. Expect more public advocacy against building Gateway.

Second, it shows that Boeing is trying to sell SLS. It wants Congress to appropriate more launches, and by showing Congress a cheaper way to use it the company is hoping legislators will buy into their proposal. SLS might be an exceedingly expensive rocket, but Gateway only makes it worse. Boeing is showing the world that there is a better and cheaper way to do things.

This also suggests that Boeing is recognizing the competition coming from SpaceX and others that might kill SLS, and is now trying to make SLS more competitive. While I am not a fan of SLS, if this proposal indicates an effort by Boeing is finally to make SLS more efficient and affordable I can only celebrate. The rocket has capabilities that are unique, and if its cost can be reduced in any way that can only benefit the U.S. effort to compete in the exploration and settlement of the solar system.

Shelby delivers big bucks to SLS, Gateway

The boondoggle that never ends! The Senate has passed a 2020 budget that includes an increase of $1.2 billion for NASA’s Artemis program and Trump’s 2024 manned lunar landing proposal, almost all of which will go to Alabama, the home state of Senator Richard Shelby (R-Alabama).

In the Exploration section of the budget that does include the Moon mission, the big new rocket called the Space Launch System (SLS) would get nearly $2.6 billion in 2020, a $1.2 billion jump from this year. SLS is managed by the Marshall Space Flight Center in Huntsville.

The Orion crew capsule program would get $1.4 billion for continued development, the planned Lunar Gateway would get $500 million and lunar landers would get $744 million.

If the Democratically-controlled House ever decides to do anything but pursue sham impeachment charges against President Trump (such as approve a budget or deal with the Senate’s proposed commercial space legislation), it remains doubtful it will approve similar increases. During recent hearings on the budget, when the House was actually doing its real job, the Democrats were very hostile to funding Trump’s 2024 Moon proposal.

And even if the House should eventually go along, unlikely as that is, the money will not really get us closer to the Moon. The bulk of this cash is targeted to pay the salaries of NASA bureaucrats at Marshall, not actually build anything.

Meanwhile the second link above, “Cruz criticizes House for lack of action on commercial space legislation,” highlights the irresponsibility of the House under Democratic control.

Cruz and several other senators from both parties reintroduced the Space Frontier Act in March. The bill, favorably reported by the Senate Commerce Committee in April, calls for reforms of commercial launch and remote sensing regulations, which are already in progress, extends the authorization of the International Space Station through 2030 and elevates the Office of Space Commerce within the Commerce Department to the Bureau of Space Commerce, led by an assistant secretary.

The House, though, has not introduced a companion bill or related legislation, a lack of action that Cruz criticized. “It’s now been nearly a year since the Space Frontier Act has been on the House floor, and airlines, airline pilots and commercial space companies are no closer to getting greater certainty or having more of a voice on how our national airspace is managed than they were a year ago,” he said.

The Democrats might not agree with the language in this Senate bill, but they have an obligation to offer some alternative. Instead, they spend their time trying to overturn a legal election that they lost.

1 2 3 4 5 9